BLD-Framing/Rough-in | 8/6/2020 | 8/7/2020 | 8/7/2020 | P | PASS |
Jim Storey
|
|
|
Requesting PM inspection for framing. Please call 30 minutes prior to meet at gate 50 to be escorted. Thanks!
Frank Phone #: ###-#### Inspection requested via web by Frank Loucks exterior wall ok
|
BLD-Concrete | 7/29/2020 | 7/30/2020 | 7/30/2020 | A | PART |
Jim Storey
|
|
|
Requesting inspection for a concrete/rebar ramp at Gate C8A for a 11:00AM concrete pour. Call 30 minutes prior to be escorted to job site MTI will be on site to witness the epoxy of smooth dowels and rebar. Thanks! Phone #: ###-#### Inspection requested via web by Frank Loucks // si on site pending report.
|
BLD-Foundation | 7/8/2020 | 7/8/2020 | 7/8/2020 | P | PASS |
Jim Storey
|
|
|
Requesting to call 30 min prior to meet at gate 50 to be escorted in SIDA badge area. Thanks! Phone #: ###-#### Inspection requested via web by Frank Loucks pending si report
|
BLD-Foundation | 7/1/2020 | 7/1/2020 | 7/1/2020 | P | PEND |
Dave Hannah
|
|
|
Please call before coming so I can meet you at gate 50 to be escorted into the job site. If you don''t know where gat 50 is, call me so I can you give directions Thanks! Phone #: ###-#### Inspection requested via web by Frank Loucks ok after spec inspection sign off
|