Permit Information
Permit NumberBLD20-00003
StatusFinaled
Name AMYX SIGNATURE HOMES
Site Address 13999 W WAINWRIGHT DR Unit: STE 203
Project NameHighland Chiropractic Ste 203
Customer Number 
ePlanReviewYes
Description
(HIGHLAND CHIROPRACTIC – SUITE #203) Permit is to combine an existing 1,383 sq. ft. business space with the adjacent 1,712 sq. ft. tenant space to create a new business tenant space that is 3,095 sq. ft. within the existing building. Approval is contingent upon adhering to the approved plans on file and plan review report. Work to include: removal of select interior nonbearing walls, removal of select door/door frames, construction of interior non-bearing walls, select wall infill, select new door/door frames, floor finishes, electrical work, plumbing work, mechanical work and interior finishes in compliance with Ch. 8 of the current IBC. Note: The common exit corridor is required to be maintained from the common restroom/breakroom area through the existing tenant space (shown hatched on the floor plan). The entire exiting path shall not be blocked, kept clear and maintained as a common exit corridor, exit access requirement is required to be met. This building is NOT Fire Sprinklered. **JG**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/21/20205/21/20205/21/2020PPASS
DetailsTell Riley
*screened* Todd Phone #: ###-####//Electrical passed//breakroom and restrooms all existing//phase one of project was inspected for framing etc, phase two was covered with ni inspection, trades passed, appears to meet plans//fire life safety red lines had been completed at final building inspection// appears to meet city approved plans//final complete//
BLD-Final5/19/20205/20/20205/20/2020APART
DetailsTell Riley
screened // Todd Phone #: ###-####//need to get electrical permit finaled that is open//did walk through, corrections made for Fire Life Safety as redlined//2nd phase was not inspected for framing, appears to be per plans//will need to come back after ele is final//
FIRE-Final Inspection5/18/20205/18/20205/18/2020PPASS
DetailsTroy Cobbley
Life safety passed. Contractor to remove the exit sign as previously discussed or provide correct single action hardware at the Exam Room door prior to a building inspection. Screened-Todd Phone #: ###-####
FIRE-Final Inspection5/12/20205/13/20205/13/2020AFAIL
DetailsTroy Cobbley
Repair and test exit signs/emergency lights, add exit sign as per plans, remove exit sign from the south west exam room door, the door swing does not match plan near restrooms, the partial wall in the exam room may not provide exit clearance to the exterior door, the installed wall does not match the plans at the exam room.Todd Phone #: ###-####
BLD-Energy code compliance2/26/20202/28/20202/28/2020APART
DetailsTell Riley
Todd Phone #: ###-####//fix insulation as noted on floor in red//ok to cover when fixed//
BLD-Framing/Rough-in2/26/20202/28/20202/28/2020APASS
DetailsTell Riley
Todd Phone #: ###-####
BLD-Framing/Rough-in2/24/20202/25/20202/25/2020ANR
DetailsTell Riley
Todd Phone #: ###-####//need to complete air seal of penetrations//re-insulate exterior walls//verify service counter areas will be A117.1 compliant//re-inspection required//