BLD-Energy code compliance | 6/15/2020 | 6/16/2020 | 6/16/2020 | A | PASS |
Tell Riley
|
|
|
screened // Randy Phone #: ###-####//plans show r 49 insulation, let builder know to post on certification for final//
|
BLD-Framing/Rough-in | 6/12/2020 | 6/15/2020 | 6/15/2020 | P | CANC |
Tell Riley
|
|
|
|
BLD-Framing/Rough-in | 6/12/2020 | 6/12/2020 | 6/12/2020 | P | PASS |
Tell Riley
|
|
|
Screened- Randy Phone #: ###-####//add straps at portals// nail hangers, add overbuild bracing//ok to insulate//make sure tub gets insulation behind it//
|
BLD-Framing/Rough-in | 6/11/2020 | 6/11/2020 | 6/12/2020 | P | CANC |
Tell Riley
|
|
|
Randy Phone #: ###-####
|
BLD-Wall Bracing | 5/12/2020 | 5/13/2020 | 5/13/2020 | A | PASS |
Tell Riley
|
|
|
Screened-Randy Phone #: ###-####//corrections made//add nails at 3" oc at portal//
|
BLD-Other | 5/7/2020 | 5/7/2020 | 5/7/2020 | P | PART |
Tell Riley
|
|
|
Screened- sheeting inspection Randy Phone #: ###-####//add Hot Dip nails to PT plate//add nails at shear panels per plans//add PFH at walls on garage//other areas ok//
|
BLD-Wall Bracing | 4/8/2020 | 4/8/2020 | 4/8/2020 | P | PART |
Tell Riley
|
|
|
Randy **left voicemail** Phone #: ###-####//interior separation walls ok, two areas are gb braced wall panels ok per plans//
|
BLD-Foundation | 3/20/2020 | 3/23/2020 | 3/23/2020 | A | PART |
Tell Riley
|
|
|
Randy Phone #: ###-####//WIP//
|
BLD-Footing | 3/18/2020 | 3/19/2020 | 3/19/2020 | A | PART |
Tell Riley
|
|
|
Randy Phone #: ###-####/setbacks per plans//ACHD inspection discussed with plan review, was told not to worry with the permit being residential//
|
BLD-Footing | 3/17/2020 | 3/18/2020 | 3/18/2020 | A | NR |
Tell Riley
|
|
|
randy Phone #: ###-####//no plans onsite//no one onsite// still need to finish rebar and elevate//water standing in some areas of footings//
|