Information based on query as of Sunday, May 19, 2024.
Permit Information
Permit NumberELE19-02700
StatusIssued
Name LEA ELECTRIC LLC
Site Address 330 N 2ND ST
Project Name 
Customer Number3910
ePlanReviewNo
Description
New: Full electrical installation in new ground up building including underground, conduit, wiring, panels, gear, receptacles, lighting, lighting control, and lightning protection.// Adding HVAC Controls 1/9/20 TCH
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Electrical Rough-In8/11/20208/12/20208/12/2020APASS
DetailsRock A. Hudson
Switchgear inspection to energize.
Contact Brandon Robinson
Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek OK to energize switch gear 2NHASWD.
Electrical Rough-In7/30/20207/30/20207/30/2020APASS
DetailsJames Ady
Water Heater Room Wall rough in inspection.
Contact onsite electrician Cody Rhoades with any questions.
Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Moved wall in basement ok to cover
Electrical Rough-In7/27/20207/28/20207/28/2020PPASS
DetailsRock A. Hudson
Contact Brandon for level 1 exterior soffits. Phone #: ###-#### Inspection requested via web by Tom Betty Level 1 east soffit as noted on contractor print rough in ok cover.
Electrical Rough-In7/13/20207/14/20207/14/2020APASS
DetailsJames Ady
Rough in wall inspection on Level 2 North.
Contact Brandon Robinson.
Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek electrical room, Com room and special systems room. Walls only ok to cover. (Alsom as marked on print).
Electrical Rough-In6/29/20207/1/20207/1/2020APASS
DetailsDaryl DeGrange
Contact Brandon Robinson for rough in walls level 2. Phone #: ###-#### Inspection requested via web by Tom Betty Rough-in ok cover walls in pneumatic rm, generator roms as high lighted on print, signed, dated
Electrical Rough-In5/6/20205/7/20205/7/2020APASS
DetailsJames Ady
Contact Brandon for level 1 wall rough in. Phone #: ###-#### Inspection requested via web by Tom Betty Misc walls 1st floor as marked on contractor print ok to cover walls only
Electrical Rough-In5/4/20205/4/20205/4/2020APASS
DetailsJames Ady
Contact Brandon Robinson for rooftop parapet walls. Phone #: ###-#### Inspection requested via web by Tom Betty S,E and W parapet walls only ok to cover
Electrical Rough-In4/29/20204/30/20204/30/2020APASS
DetailsJames Ady
Contact Brandon R. for level 1 west wall and north stairwell rough in. Phone #: ###-#### Inspection requested via web by Tom Betty N Stair well Basement walls only, West exterior wall only ok to cover
Electrical Rough-In4/6/20204/8/20204/8/2020APASS
DetailsJames Ady
Contact Brandon for sub-basement wall rough in from elevators to south end of basement. Phone #: ###-#### Inspection requested via web by Tom Betty Lightning protection, Basement walls, Penthouse walls ok to cover
Electrical Rough-In2/27/20203/2/20203/2/2020APASS
DetailsJames Ady
Contact Brandon for west and north lightning protection ground loop system. Phone #: ###-#### Inspection requested via web by Tom Betty Remaining ground loop ok to cover
Electrical Rough-In2/27/20202/27/20202/27/2020PPASS
DetailsJames Ady
Contact Brandon for lightning protection ground loop system. Phone #: ###-#### Inspection requested via web by Tom Betty Grounding ring as mark on contractors print only ok to cover
Electrical Rough-In2/24/20202/25/20202/25/2020APASS
DetailsJames Ady
Contact Brandon for underground rough in at fuel tanks on east exterior of project. Phone #: ###-#### Inspection requested via web by Tom Betty Underground around Diesel fuel tanks only. ok to cover. (Note: Diesel fuel dispensary is not considered a hazerdous area. No seal offs required other spect by engineer)
Electrical Rough-In1/9/20201/10/20201/10/2020APASS
DetailsJames Ady
Underground Inspection.
Please contact electrician on-site Cody Rhoades.
Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Basement underground Column D through G ok to cover
Rough-In Permanent Service9/18/20199/20/20199/20/2019ACANC
DetailsJames Ady
Contact Brandon for UFER in west footing before 9:00 a.m. concrete pour. Phone #: ###-#### Inspection requested via web by Tom Betty
Electrical Rough-In9/20/20199/20/20199/20/2019PPASS
DetailsJames Ady
Contact Brandon for UFER in west footing before 9:00 a.m. concrete pour. Phone #: ###-#### Inspection requested via web by Tom Betty UFER only ok to cover
Rough-In Permanent Service9/18/20199/19/20199/18/2019ACANC
DetailsRock A. Hudson
Please inspect UFER ground on west footing before 9:00 a.m. concrete pour. Phone #: ###-#### >> Inspection requested via web by Tom Betty Inspection cancelled from web by: Tom Betty