Permit Information
Permit NumberFIR13-00723
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 4632 W AERONCA ST
Project NameAviation Specialties Unlimited
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of protecting a group II hanger using a wet system. The following exception from IFC must be strictly adhered to since this will not be a foam system as required by NFPA 409. Extra hazard II design has been used per NFPA 13. There are two risers supplied by a new 8” underground and new 8” back flow preventer. One 6” riser for the existing hangar and one 8” riser for the new hangar. Since there is not a 3-hour separation between the hangars, they shall be treated as one fire area.

IFC: 914.8.2 - Exception: When a fixed base operator has separate repair facilities on site, Group II hangars operated by a fixed base operator used for storage of transient aircraft only shall have a fire suppression system, but the system shall be exempt from foam requirements.

The fire protection underground is under permit FIR13-00460

Aviation Specialties Unlimited - New hangar and office expansion - To construct a new 18,000 sq. ft. one story, pre-engineered metal building, group II aircraft hangar and office addition with a 3,425 sq. ft. basement and 3,475 sq. ft. office mezzanine. This addition is being constructed on the east side of an existing 8,900 sq. ft. one-story aircraft hangar and office building. This permit also includes the construction of a 400 sq. ft. accessible restroom and utility room area at the southeast corner of the existing hangar. This permit also includes related site improvements. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/24/20154/27/20154/27/2015APASS
DetailsTroy Cobbley
Permit finaled
INSP-Sprinkler Rough-in/Hydro4/10/20154/13/20154/13/2015APASS
DetailsKatie Marron
Overhead hydrostatic test pass
INSP-Sprinkler Rough-in4/9/20154/10/20154/10/2015APASS
DetailsTroy Cobbley
Piping in the existing office areas is ok to cover.
INSP-Sprinkler Rough-in1/20/20151/20/20151/20/2015APASS
DetailsTroy Cobbley
overhead rough in passed. Hard lids ok to cover. Will need an additional rough-in inspection when drops have been piped to grid.
INSP-Sprinkler Rough-in/Hydro12/4/201412/4/201412/4/2014PPASS
DetailsTroy Cobbley
overhead rough-in of the existing hanger passed
INSP-Final Inspection9/19/20149/22/20149/22/2014APART
DetailsTroy Cobbley
Forward flush passed and the alarm bell functioned. Need the work in the existing building completed.
INSP-Final Inspection9/11/20149/12/20149/12/2014AFAIL
DetailsTroy Cobbley
New hanger work is complete. Need the existing building work completed. Need electric alarm bell installed. Forward flush did not pass. Need backflow certified.
INSP-Sprinkler Rough-in8/18/20148/18/20148/18/2014PPASS
DetailsTroy Cobbley
The remaining second floor piping is ok to cover.
INSP-Sprinkler Rough-in/Hydro8/14/20148/14/20148/14/2014PPART
DetailsForrest France
OH hydrostatic testing completed acceptable.
INSP-Sprinkler Rough-in8/12/20148/13/20148/13/2014APART
DetailsForrest France
Fire sprinkler work above grid ceilings on the second and first floors okayed for cover at locations initialed and dated on approved plans. Discussed schedule for hydrostatic testing.
INSP-Sprinkler Rough-in8/6/20148/6/20148/6/2014PPART
DetailsForrest France
Okay to cover fire sprinkler work at the 1st floor lobby ceiling and aeronautics office as marked and dated on plans. Noted one head to be relocated at the west open office area.
INSP-Sprinkler Rough-in7/21/20147/22/20147/22/2014APASS
DetailsTroy Cobbley
2" overhead lines have been changed out to the previously approved 2 1/2". Hardlids ok to install as marked on the plans.
INSP-Sprinkler Rough-in7/15/20147/15/20147/15/2014PPASS
DetailsTroy Cobbley
The remaining basement ceiling can be installed and select areas, as marked, can be installed on the first floor. Second floor piping can not be covered until plan review gives me the ok on the pipe size changes/hydralic calculations.
INSP-Sprinkler Rough-in7/8/20147/8/20147/8/2014PPART
DetailsTroy Cobbley
Hanger area piping rough-in passed. Could not give approval for cover on the second floor due to the approved 2 1/2" branchlines being installed as 2".
INSP-Sprinkler Rough-in6/13/20146/13/20146/13/2014PPASS
DetailsTroy Cobbley
The underground supply line is ok for cover
INSP-Sprinkler Rough-in6/13/20146/13/20146/13/2014PPASS
DetailsTroy Cobbley
The two hard lids for the second floor mens ands womens restrooms is ok to install.
INSP-Sprinkler Rough-in6/9/20146/10/20146/10/2014APASS
DetailsTroy Cobbley
See the city approved plans for location marked "ok" for piping that is ok for cover.
INSP-Sprinkler Rough-in5/27/20145/28/20145/28/2014APASS
DetailsTroy Cobbley
See the city approved plans for additional locations where piping can be covered.
INSP-Sprinkler Rough-in5/21/20145/22/20145/22/2014APART
DetailsForrest France
Overhead work okay to cover at both the east and west side feed mains to office areas on the 2nd, 1st, and basement floor levels. Okay to cover work at one additional room as marked and dated on plans- basement level. Noted floorplan changes from original drawings.
INSP-Sprinkler Rough-in5/12/20145/12/20145/12/2014PPASS
DetailsTroy Cobbley
See the city approved plans for locations where piping above hardlids can be covered in the basement and first floors. Overhead piping rough-in passed in these two areas as well but another cover inspection will be needed once the drops are installed.
INSP-Sprinkler Rough-in5/5/20145/6/20145/6/2014ACANC
DetailsTroy Cobbley
mark Phone #: ###-#### Inspection cancelled from web by: Jeff Packham
INSP-Sprinkler Rough-in4/30/20144/30/20144/30/2014PPASS
DetailsTroy Cobbley
Inspection for the hangers at teh deck passed and can be covered.