INSP-Final Inspection | 1/19/2017 | 1/23/2017 | 1/23/2017 | A | PASS |
Jim Page
|
|
|
Final fire alarm inspection passed/complete.
|
INSP-Alarm Testing | 10/19/2015 | 10/19/2015 | 10/19/2015 | A | PART |
Thomas Walsh
|
|
|
Fire alarm interface with heat tracing panels that monitor heat trace of fire sprinkler piping exposed to cold temps. See FIR 13-00461 for details of heat trace inspection.
|
INSP-Alarm Testing | 8/12/2015 | 8/13/2015 | 8/13/2015 | A | PART |
Thomas Walsh
|
|
|
Fire alarm testing (continuation) for abaove grade SDs, FSD, HVAC shutdowns, rolldown doors (floors 4 & 5) elevator smoke guard doors,etc. Checked monitoring for alarms received - OK. Also checked exterior bell for waterflow alarms - tested OK.
|
INSP-Alarm Testing | 8/12/2015 | 8/12/2015 | 8/12/2015 | A | PART |
Thomas Walsh
|
|
|
Continuation of fire alarm system testing for JUMP Bldg, including Helix, A/G parking structure and upper structures to the 6th floor. Testing mostly of in-duct HVAC shutdown purposes. All tested OK. More testing to commence tomorrow.
|
INSP-Alarm Testing | 8/11/2015 | 8/11/2015 | 8/11/2015 | P | PART |
Thomas Walsh
|
|
|
Continuation of fire alarm system testing, including test of two (2) PIVs, two (2) BFP devices - both valves, and a random etst of other fire sprinkler risers and sectional control valves. All tested OK. Started FSD test of in-duct SDs to ensure shutdown of FSDs for the parking level, 1st floor kitchen and lobby and 2nd floor lobby areas. All tested OK, except for one unit in the garage that needs to be retested. More FSDs need to be tested on the upper floors including rooftop HVAV duct detectors.
|
INSP-Alarm Testing | 8/7/2015 | 8/7/2015 | 8/7/2015 | A | PART |
Thomas Walsh
|
|
|
Test of elevator recall functions for service elevator and main elevator - the third elevator not ready for testing. All elevator functions tested OK. Shunt trip power monitoring not tested this visit.
|
INSP-Alarm Testing | 7/30/2015 | 8/3/2015 | 8/3/2015 | P | CANC |
Thomas Walsh
|
|
|
No inspections called in for this permit.
|
INSP-Alarm Testing | 7/30/2015 | 8/3/2015 | 8/3/2015 | A | PART |
Thomas Walsh
|
|
|
Initial fire alarm system testing, including test of notification (speaker/strobes) throuout the JUMP bldg. including the U/G parking garage the above ground parking garage, the helix and all rooms above grade. A few devices were not very load, and the contractor agreed to modify the devices in these areas to improve audibility. Also tested fire pump functions to coincide with the fire pump commissioning test. Also tested one (1) H&D system test for the 1st floor kitchen. NOTE: Elevators, HVAC, and FSDs not ready for test yet.
|
INSP-Alarm Testing | 7/12/2015 | 7/12/2015 | 7/12/2015 | P | PART |
Thomas Walsh
|
|
|
Initial testing of fire alarm system for the Jump building, including the Helix and A/G parking structure. NOTE: U/G parking structure under permit # 13-00178. Test included functional testing for all fire sprinkler systems (wet and dry) for all levels, and stairwells, including wet pipe water flows, dry pipe trip tests, low-air alarms, waterflows, tampers, etc. All systems tested OK. Some alarm descriptions need to be revised to reflect a better location of some of the systems. Simplex to make these changes, and wil confirm at the next inspection.
|
INSP-Conference | 10/1/2014 | 10/1/2014 | 10/1/2014 | P | DONE |
Forrest France
|
|
|
Site visit completed to discuss occupant notification in the vicinity of the 1st to 4th floor NE elevator lobby and stair tower areas, ground level courtyard. Also discussed dust collection equipment, fire door, heat tracing at sprinkler mains.
|