Description
The fire sprinkler scope of work consists of 6”x46± C-900 underground piping with a yard PIV.

To construct a new 11,850 square foot, one story, wood framed skilled nursing facility and related site improvements. This nursing home will contain 16 sleeping units with individual restrooms, as well as, a kitchen, dining and hearth room social area. This building will also contain a hair salon, laundry, storage and mechanical areas. This building is divided into two smoke compartments by a one-hour smoke barrier wall. This building will be fully fire sprinkled. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/27/201510/29/201510/29/2015APASS
DetailsThomas Walsh
Final inspection of FS U/G supply line. PIV and BFP valve tampers tested with fire alarm system test. All tested OK.
INSP-Sprinkler Rough-in/Hydro7/29/20157/30/20157/30/2015ACANC
DetailsThomas Walsh
Wrong permit # called in for this inspection. See permit # FIR14-00750 for inspection conducted today (7/30).
INSP-Sprinkler Rough-in7/29/20157/30/20157/30/2015ACANC
DetailsThomas Walsh
Wrong permit called in for this inspection - see permit # FIR14-00750 for inspections conducted today (7/30).
INSP-Final Inspection5/29/20156/1/20156/1/2015PCANC
DetailsThomas Walsh
Final signoff on FSUG cannot be granted until fire alarm system interface components, including tampers and waterflows, can be completed.
INSP-Sprinkler Rough-in/Hydro5/27/20155/27/20155/27/2015APASS
DetailsThomas Walsh
FSUG hydrotest from city connection to A/S BOR - 200 psi @ 2 hours - PASSED
INSP-Sprinkler Rough-in/Hydro5/26/20155/27/20155/27/2015ACANC
DetailsThomas Walsh
Hydrotest of FSUG supply lie=ne from city connection to BOR - 200 psi at 2 hours - PASSED.
INSP-Supply line flush4/21/20154/21/20154/23/2015PCANC
DetailsKatie Marron
Cancelled overbooked, rescheduled for later date.
INSP-Supply line flush4/22/20154/22/20154/22/2015PPART
DetailsKatie Marron
Supply line flush for bldg K completed satisfactory.
INSP-Supply line flush4/17/20154/17/20154/17/2015PCANC
DetailsKatie Marron
Cancelled by contractor.
INSP-Sprinkler Rough-in9/12/20149/15/20149/15/2014PPART
DetailsForrest France
UG fire supply line including the PIV and ductile riser okay for bury provided a plan modification is done to reflect changes in pipe route, added 45 and 90, and relocated riser room.