INSP-Final Inspection | 10/14/2015 | 10/14/2015 | 10/15/2015 | P | PASS |
Thomas Walsh
|
|
|
Final Inspection passed. All previous discrepancies adequately corrected.
|
INSP-Sprinkler Rough-in/Hydro | 6/12/2015 | 6/12/2015 | 6/12/2015 | P | PASS |
Thomas Walsh
|
|
|
Final Inspection of Bldg D wet pipe fire sprinkler system.NOTE: One remaining item to be addressed under this permit is to extend the FDC connection adjacent to the main entry lobby from its current location to extend past the roof column that it is currently obstructed by. The contractor agreed to get this done - the final acceptance was issued with this agreement.
|
INSP-Final Inspection | 6/10/2015 | 6/11/2015 | 6/11/2015 | A | PART |
Thomas Walsh
|
|
|
Final inspection of Bldg D, includinfg commons area. Need to remove protective cap on A/S in main lobby (2nd floor). Will sign off when this is completed.
|
INSP-Sprinkler Rough-in/Hydro | 6/9/2015 | 6/10/2015 | 6/10/2015 | A | CANC |
Thomas Walsh
|
|
|
Sprinkler final inspection/sign off will be conducted after all fire alarm testing is completed.
|
INSP-Sprinkler Rough-in/Hydro | 6/5/2015 | 6/8/2015 | 6/8/2015 | P | PART |
Thomas Walsh
|
|
|
Inspection of fire alarm system interface, including water flows of system risers, tamper devices, control valves, etc. Waterflows came in at approx. 30-40 seconds. All device addresses appeared accurate.
|
INSP-Final Inspection | 6/1/2015 | 6/2/2015 | 6/3/2015 | P | CANC |
Thomas Walsh
|
|
|
Wet pipe final inspection pending completion of fire alarm interface, including waterflows and tampers.
|
INSP-Sprinkler Rough-in/Hydro | 5/21/2015 | 5/21/2015 | 5/21/2015 | P | PASS |
Thomas Walsh
|
|
|
Hydrotest Wing D and commons. 200psi @ hours - Passed
|
INSP-Sprinkler Rough-in | 4/13/2015 | 4/13/2015 | 4/13/2015 | P | PART |
Katie Marron
|
|
|
Inspection for cover at grid ceiling areas for wing D, first floor completed. Ok to cover. Noted three painted heads, misaligned branch and two sprinklers with wrong temperature rating.
|
INSP-Sprinkler Rough-in | 4/3/2015 | 4/6/2015 | 4/6/2015 | P | PART |
Scott Arellano
|
|
|
OK to cover hard lid areas only within corridor per approved plans and head locations.
|
INSP-Sprinkler Rough-in | 2/25/2015 | 2/25/2015 | 2/26/2015 | P | PART |
Forrest France
|
|
|
2nd floor area D entry sheetrock lid ceiling okayed for cover with conditions to include adequate clearance for branchline piping extending through framing.
|
INSP-Sprinkler Rough-in | 2/20/2015 | 2/20/2015 | 2/20/2015 | P | PART |
Forrest France
|
|
|
Overhead work at the sheetrock lid ceilings first floor area D east half to rated wall as annotated and dated on approved plans okay for cover.
|
INSP-Sprinkler Rough-in | 2/11/2015 | 2/12/2015 | 2/12/2015 | P | PART |
Forrest France
|
|
|
Okayed for cover hard lid soffit ceilings completed to date as noted and initialed on approved plan sheet- partial areas only, building section D.
|
INSP-Sprinkler Rough-in/Hydro | 2/10/2015 | 2/10/2015 | | P | |
Forrest France
|
|
|
Partial rough to cover bldg D 1st floor (soffits/hard lids ) ###-#### Leroy >> Inspection requested via web by Scott Carter II
|