INSP-Final Inspection | 9/14/2015 | 9/15/2015 | 9/15/2015 | A | PASS |
Thomas Walsh
|
|
|
Test of new control valve for horizontal exit standpipes. Also signed off Certificate of Completion forms.
|
INSP-Final Inspection | 8/19/2015 | 8/20/2015 | 8/20/2015 | P | CANC |
Thomas Walsh
|
|
|
Revised plans for this permit have been submitted to Tim Frost for review prior to final sign off. Contractor will request final sign off after this review is completed.
|
INSP-Final Inspection | 8/14/2015 | 8/14/2015 | 8/14/2015 | P | PART |
Thomas Walsh
|
|
|
Completed 24 hour air tests of the two dry pipe valves for the parking garage. PASSED
|
INSP-Sprinkler Rough-in/Hydro | 8/12/2015 | 8/12/2015 | 8/12/2015 | P | PART |
Thomas Walsh
|
|
|
Rough to cover inspection for 5th floor corridors - both north and south wings. OK to cover pipe in this area. Also Hydrostatic pressure test of the two (2) dry-pipe systems for the parking garage, and the wet system for the first floor leasing offtice area. - PASSED. Also hydrotest of the wet systems for floors 3 and 4 - noth and south sides - PASSED
|
INSP-Sprinkler Rough-in | 8/10/2015 | 8/10/2015 | 8/10/2015 | P | PART |
Thomas Walsh
|
|
|
RTC inspection for the dry ppe fire sprinkler system protecting the east-side of the parking garage. Except for two (2) heads that need to be added - one on the east entry rollup gate and the other at the south-west corner of the system, it is OK to cover the pipe for this system. Will reinspect to ensure that these 2 sprinklers get installed prior to hydrotest.
|
INSP-Sprinkler Rough-in/Hydro | 8/4/2015 | 8/4/2015 | 8/4/2015 | P | PART |
Thomas Walsh
|
|
|
RTC inspection for west dry system in parking garage. Need to add 4 DP heads in south west corner. Otherwise OK to cover the pipe for this system.
|
INSP-Sprinkler Rough-in | 7/15/2015 | 7/17/2015 | 7/17/2015 | A | PART |
Thomas Walsh
|
|
|
RTC inspection for first floor wet-pipe system protecting the office area - hard lid areas. OK to cover pipe in this area.
|
INSP-Sprinkler Rough-in | 6/25/2015 | 6/26/2015 | 6/26/2015 | A | CANC |
Thomas Walsh
|
|
|
Wrong permit for this day's inspection. See FIR14-00096 for inspections completed today (6/26).
|
INSP-Sprinkler Rough-in | 5/19/2015 | 5/20/2015 | 5/20/2015 | P | PART |
Thomas Walsh
|
|
|
Hard lid inspection for pool room. See plans for a/s inspected.
|
INSP-Sprinkler Rough-in | 1/20/2015 | 1/20/2015 | 1/20/2015 | A | PART |
Forrest France
|
|
|
Intended for 5th floor wet system.
|
INSP-Sprinkler Rough-in | 1/14/2015 | 1/15/2015 | 1/16/2015 | P | PART |
Forrest France
|
|
|
OH cover inspection completed for the 5th floor soffit lower lid ceilings at room units 530-537 tower one.
|