INSP-Final Inspection | 8/11/2015 | 8/11/2015 | 8/11/2015 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 6/22/2015 | 6/22/2015 | 6/22/2015 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro from the backflow at the tank to the inside riser passed.
|
INSP-Supply line flush | 5/26/2015 | 5/27/2015 | 5/27/2015 | A | PASS |
Jim Page
|
|
|
Underground flush complete.
|
INSP-Sprinkler Rough-in/Hydro | 5/19/2015 | 5/20/2015 | 5/20/2015 | A | PASS |
Troy Cobbley
|
|
|
The underground hydro from the United Water outlet to the first coupling above the floor is passed.
|
INSP-Sprinkler Rough-in/Hydro | 4/10/2015 | 4/13/2015 | 4/13/2015 | A | NR |
Katie Marron
|
|
|
Not ready per phone call with contractor.
|
INSP-Sprinkler Rough-in | 3/19/2015 | 3/20/2015 | 3/20/2015 | A | PART |
Forrest France
|
|
|
Inspection for thrust blocking completed satisfactory- okay to cover at areas installed to date.
|
INSP-Sprinkler Rough-in | 3/17/2015 | 3/18/2015 | 3/18/2015 | A | PART |
Forrest France
|
|
|
Inspection for end caps at manifold and ductile risers/90's at tank supply and draft piping. Thrust blocking is not yet provided. Photo documentation recorded.
|
INSP-Sprinkler Rough-in | 3/5/2015 | 3/5/2015 | 3/6/2015 | P | PART |
Forrest France
|
|
|
Inspection for the extent of UG manifold work completed to date including three 18" x 16" tees, approx. 25' of 18" supply pipe, visual internal inspection of piping. Discussed project schedule, remainder of work etc.
|
INSP-Sprinkler Rough-in | 2/9/2015 | 2/9/2015 | 2/9/2015 | P | PART |
Forrest France
|
|
|
Inspection for hangers only at z-purlins prior to cover.
|
INSP-Sprinkler Rough-in | 1/22/2015 | 1/23/2015 | 1/23/2015 | A | PART |
Forrest France
|
|
|
Inspection for hanger attatchments at the riser room prior to vapor cover.
|
INSP-Sprinkler Rough-in | 1/22/2015 | 1/22/2015 | 1/22/2015 | P | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 11/3/2014 | 11/3/2014 | 11/3/2014 | A | PART |
Forrest France
|
|
|
Ref. dated plan annotations for areas inspected.
|
INSP-Sprinkler Rough-in | 10/31/2014 | 10/31/2014 | 10/31/2014 | P | PASS |
Craig D. Hanson
|
|
|
underground stub
|
INSP-Sprinkler Rough-in | 10/30/2014 | 10/30/2014 | 10/30/2014 | P | PART |
Forrest France
|
|
|
Ref. to stamped plans for portions okayed for bury.
|
INSP-Sprinkler Rough-in | 10/29/2014 | 10/30/2014 | 10/30/2014 | A | PART |
Forrest France
|
|
|
UG fire supply line ductile risers and stubs to a point approx. 15' beyond the stem wall as marked/dated on approved plans okayed for bury.
|