INSP-Final Inspection | 9/2/2015 | 9/3/2015 | 9/3/2015 | A | PASS |
Thomas Walsh
|
|
|
Final inspection of fire sprinklers for the above parking lot areas of the building - PASSED. Contractor cert. of completion signed off and will be emailed to the PDS office.
|
INSP-Final Inspection | 8/10/2015 | 8/10/2015 | 8/10/2015 | P | PART |
Thomas Walsh
|
|
|
Reinspection of punchlist items for fire sprinkler systems final sign-off. All previous discrepancies adequately addressed. Contractor will schedule ROC docs sign off. Otherwise all systems are signed off.
|
INSP-Final Inspection | 8/6/2015 | 8/7/2015 | 8/7/2015 | A | PART |
Thomas Walsh
|
|
|
Final inspection of all sprinkler systems for above parking garage levels. Need riser placards on some risers, need signs for exterior wall hydrants, Need to replace riser gauge on southeast stairwell - 4th level. ROC paperwork not completed this visit.
|
INSP-Final Inspection | 8/6/2015 | 8/6/2015 | 8/6/2015 | P | FAIL |
Thomas Walsh
|
|
|
Final inspection requested for parking garage permit, however noted dissimilar sprinklers (temp ratings) for several sprinklers located in the stair enclosures. Contractor agreed to inspect all and change out as needed to reflect proper temp. ratings per plans. Also need signs (2) for exterior hose valves for FD use outside east parking level egress paths.
|
INSP-Sprinkler Rough-in/Hydro | 8/6/2015 | 8/6/2015 | 8/6/2015 | P | PASS |
Thomas Walsh
|
|
|
Hydrotest of clubhouse wet pipe system - 200 psi @ 2 hours - PASSED
|
INSP-Final Inspection | 8/5/2015 | 8/5/2015 | 8/5/2015 | P | PART |
Thomas Walsh
|
|
|
Pre-final inspection for fire sprinkler systems. All systems have been fully tested and are operational. Left contractor with a punchlist of minor items (mostly escutcheons missing). Also some of the wet systems are still shut down as some painted heads need to be changed out. Will reshedule final inspection when all work is completed.
|
INSP-Final Inspection | 8/3/2015 | 8/4/2015 | 8/4/2015 | A | PART |
Thomas Walsh
|
|
|
Final inspection of corridors and residential units for floors 2 and 3. 4th floor not ready for insection this visit.
|
INSP-Sprinkler Rough-in | 8/3/2015 | 8/4/2015 | 8/4/2015 | A | PASS |
Thomas Walsh
|
|
|
This is a dry system trip for 4/1 north.
|
INSP-Sprinkler Rough-in | 8/3/2015 | 8/3/2015 | 8/4/2015 | P | PASS |
Thomas Walsh
|
|
|
This is a trip test dry system trip for 4/1 north.
|
INSP-Final Inspection | 8/3/2015 | 8/4/2015 | 8/3/2015 | P | CANC |
Thomas Walsh
|
|
|
Final inspections pending completion of dry pipe valve trip testing. Final walkthroughs inspections will be conducted only after all painting is completed. Some stairwells still be ing painted.
|
INSP-Final Inspection | 8/3/2015 | 8/3/2015 | 8/3/2015 | P | CANC |
Thomas Walsh
|
|
|
Final inspection pending completion and passing of all dry pipe systems.
|
INSP-Final Inspection | 7/30/2015 | 7/31/2015 | 7/31/2015 | P | CANC |
Thomas Walsh
|
|
|
Final inspection of fire sprinklers not completed as ran out of time with the fire alarm testing. NOTE: Three of the dry pipe systems need to be modified with accelerators as they failed their 60 minute trip test. These are both systems for the parking garage, and the one dry system for the north side attic. These valves will be retested after these changes are made.
|
INSP-Final Inspection | 7/29/2015 | 7/30/2015 | 7/30/2015 | P | CANC |
Thomas Walsh
|
|
|
Ran out of time for this inspection. Will inspect first thing tomorrow morning as fire alarm testing continues.
|
INSP-Alarm Testing | 7/29/2015 | 7/30/2015 | 7/30/2015 | A | PART |
Thomas Walsh
|
|
|
Partial fire alarm system inspection for wet fire sprinklers, including all risers, except for the clubhouse. All waterflows, tampers, etc, tested OK
|
INSP-Final Inspection | 7/27/2015 | 7/27/2015 | 7/27/2015 | P | FAIL |
Jim Page
|
|
|
Rooms with items that need to be repaired/replaced & re-inspected: Section 2/2: rooms 230 wrong head in restroom, 232 restroom head cleaned and 2nd floor vending wrong head installed. Section 3/1: 302 painted head, 306 missing escutcheon, 307 painted head, 321 sidewalls painted, 320 sidewalls painted Section 3/2: 325 mech room head painted, 327bedroom head to 401 escutcheon, 328 incorrect head, 332 painted sidewall, 336 painted head restroom, 337 mech room head painted, 338 painted head restroom
|
INSP-Conference | 7/23/2015 | 7/23/2015 | 7/23/2015 | P | DONE |
Jim Page
|
|
|
Spoke with General contractor, approved for moving in furniture to building, sprinkler systems are to remain active, no tenant or overnight occupancy allowed until final certificate of occupancy is issued.
|
INSP-Final Inspection | 7/23/2015 | 7/23/2015 | 7/23/2015 | P | CANC |
Troy Cobbley
|
|
|
This is a final inspection for 3/1, 2/2, and 3/2. The contact is Mark. Thanks. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 7/22/2015 | 7/22/2015 | 7/22/2015 | P | PART |
Jim Page
|
|
|
Hydrostatic test passed/complete on wet systems supplying 2nd, 3rd and 4th floors, total of 6 wet systems tested, club house wet system still needs hydrostatically tested.
|
INSP-Sprinkler Rough-in/Hydro | 7/20/2015 | 7/21/2015 | 7/21/2015 | P | CANC |
Thomas Walsh
|
|
|
Hydrotest cancelled for all systems. Not ready
|
INSP-Sprinkler Rough-in | 7/20/2015 | 7/20/2015 | 7/20/2015 | P | PART |
Thomas Walsh
|
|
|
Rough to cover inspections for 4/1, 4/2, 4/3 and 4/4 corridors. Some penetrations needed fire caulking touch-up work, which were completed during inspection. OK to cover all corridors on the 4th floor.
|
INSP-Final Inspection | 7/20/2015 | 7/20/2015 | 7/20/2015 | P | CANC |
Thomas Walsh
|
|
|
Not ready for final inspections. No fire alarm system testing todate. Fire sprinklers cannot be finaled priot to alarm interface testing being completed.
|
INSP-Final Inspection | 7/13/2015 | 7/14/2015 | 7/14/2015 | A | PART |
Thomas Walsh
|
|
|
Called in for final inspection of 2nd floor area 1 portion of the building. Research of permit inspections has not identified any hydrotests of any of the wet systems for the building, or the dry systems in the PG. Primary contractor for this project will be back tomorrow. Will compare notes to confirm what further hydrotests are required. Additionally, final inspection of any sprinkler system cannot be granted until fire alarm interface testing can be performed, including water flows, tampers, etc.
|
INSP-Sprinkler Rough-in | 7/6/2015 | 7/7/2015 | 7/7/2015 | A | PART |
Thomas Walsh
|
|
|
Rough to cover inspection for the corridors on floors 2 and 3, in section 3 of the building. OK to cover pipe.
|
INSP-Sprinkler Rough-in | 6/22/2015 | 6/23/2015 | 6/23/2015 | P | PART |
Thomas Walsh
|
|
|
RTC inspection for 2nd and 3rd fllor corridors for section 2 of the bldg. PASSED - OK to cover.
|
INSP-Sprinkler Rough-in | 6/16/2015 | 6/17/2015 | 6/17/2015 | A | PART |
Thomas Walsh
|
|
|
RTC inspection for 3rd floor corridor for section 1 area of the building. OK to cover pipe in this area.
|
INSP-Sprinkler Rough-in | 6/10/2015 | 6/11/2015 | 6/11/2015 | A | PART |
Thomas Walsh
|
|
|
Rough to cover inspection for 2nd floor corridor for section 1 - OK to Cover. Also coverage for rotunda and skylight in clubhouse. NOTE: Need HT head for top of skylight.
|
INSP-Sprinkler Rough-in | 6/6/2015 | 6/8/2015 | 6/8/2015 | A | PART |
Thomas Walsh
|
|
|
Rough to cover inspection for east side of clubhouse wet system. OK to Cover. NOTE: Proper coverage of garage type door on east wall - opening to pool, will be checked after door is installed.
|
INSP-Sprinkler Rough-in/Hydro | 5/22/2015 | 5/26/2015 | 5/26/2015 | A | PART |
Thomas Walsh
|
|
|
This is a rough in inspection that was mistakenly entered under FIR14-00866 on 5/20 for completion on 5/21. It needs to be completed under this FIR# and is for the soffits on Level 4, Section 3 Units included in this inspection are 417, 418, 419, 420, 421, 422, 423, 424, 425, 426, 427, 428, 429 and 430..
|
INSP-Sprinkler Rough-in/Hydro | 5/12/2015 | 5/13/2015 | 5/15/2015 | A | PASS |
Thomas Walsh
|
|
|
Dry system hydrotest
|
INSP-Sprinkler Rough-in | 5/7/2015 | 5/8/2015 | 5/13/2015 | A | PART |
Thomas Walsh
|
|
|
3rd floor, section 3 & Clubhouse.
|
INSP-Sprinkler Rough-in | 5/6/2015 | 5/6/2015 | 5/7/2015 | P | PART |
Thomas Walsh
|
|
|
Lusk St. Apartments - Soffit inspection - 2nd floor Section 3 (Units 219, 221, 222, 224, 223, 226, 228 & 230 - PASSED
|
INSP-Sprinkler Rough-in | 5/6/2015 | 5/6/2015 | 5/6/2015 | A | FAIL |
Thomas Walsh
|
|
|
Seperate inspection under this permit. Clubhouse rough inspection for attic dry-pipe system - FAILED (need to add 2 A/S - see on-site plans).
|
INSP-Sprinkler Rough-in | 5/5/2015 | 5/5/2015 | 5/6/2015 | P | PART |
Thomas Walsh
|
|
|
Section 3 unit soffit inspection 2nd floor.
|
INSP-Sprinkler Rough-in | 5/4/2015 | 5/4/2015 | 5/4/2015 | P | PART |
Thomas Walsh
|
|
|
Mark - Shilo FP Tenting inspection of 4th floor sprinkler pipe for section 3 - all units (414 thru 430). Found multiple areas where touch-up insulation work was required - all were fixed before end of inspection.
|
INSP-Sprinkler Rough-in | 4/29/2015 | 4/29/2015 | 4/29/2015 | P | PART |
Katie Marron
|
|
|
Tenting inspection complete 4th floor, sec 2 living units only with the exception of RMs 414, 415, 416 to be inspected at a later date. The following correction notice items were fixed on the spot: Rm 408 pipe in contact with exhaust vent pipe, supplied insulation between Rm 412 pipe in contact with exhaust vent pipe in two spots, supplied insulation between. Rms 413, 411 and 406 had sections unfinished, completed by end of inspection.
|
INSP-Sprinkler Rough-in | 4/23/2015 | 4/27/2015 | 4/27/2015 | A | PART |
Katie Marron
|
|
|
Tenting inspection complete at 4th floor, section 1. Noted that a barrier should be placed between exhaust fan piping to exterior and sprinkler piping where they share inter-joist space. Rm 441 especially. Corrections were being made on spot.
|
INSP-Sprinkler Rough-in | 4/23/2015 | 4/24/2015 | 4/24/2015 | A | PART |
Katie Marron
|
|
|
Sofits at sec 2 on 3rd floor ok to cover. One drop in RM 315 at bathroom to be straightened. Verifed previous C/N items in rooms 420, 424, 426, 423, 414 and 412 corrected satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 4/22/2015 | 4/23/2015 | 4/23/2015 | A | PART |
Katie Marron
|
|
|
24 hr air test for dry systems 1 and 2 completed satisfactory. End pressures recorded, system one 40.5 psig, system two 43 psig. Completed rough-in for dry system 3 on fourth floor. Correction items are as follows straighten on two heads in rm 424, and one head each in rms 426 and 423. RM 420 has two obstructed heads to be relocated and 2 missing hangars. Rm 414 has a head located under vent to be moved to side. Previous C/N items were not able to be corrected due to pressure system, to be verified at next inspection.
|
INSP-Sprinkler Rough-in/Hydro | 4/22/2015 | 4/22/2015 | 4/22/2015 | A | PART |
Forrest France
|
|
|
Begin 24 hr pneumatic test of new dry systems one and two at 10:00AM- System one @41.5psig System two at 43psig.
|
INSP-Sprinkler Rough-in | 4/20/2015 | 4/22/2015 | 4/22/2015 | A | PART |
Forrest France
|
|
|
Completed remainder of overhead rough-in inspection for dry system one as noted on plan sheet FP25 and FP28. Corrections needed at units 412 and 413- sprinkler deflectors at some locations are too close to the deck per listing and obstructed by truss webs. Also verified previous C/N items for completion plan sheet FP28- units 400, 435, and 437.
|
INSP-Sprinkler Rough-in | 4/20/2015 | 4/21/2015 | 4/21/2015 | A | CANC |
Troy Cobbley
|
|
|
Overbooked. I spoke to Jeff about rescheduling.
|
INSP-Sprinkler Rough-in | 4/16/2015 | 4/17/2015 | 4/17/2015 | P | PART |
Katie Marron
|
|
|
Part of dry system 1 rough in completed as marked on plans. Corrections items noted were missing head rm 400, missing hangar and head misaligned room 437, head misaligned rm 435 and remove comm cabling along hallway main. Verified draft stops per plan.
|
INSP-Sprinkler Rough-in/Hydro | 4/15/2015 | 4/16/2015 | 4/16/2015 | A | PART |
Katie Marron
|
|
|
2hr Hydrostatic pressure test on Dry system # 2 on the 4th floor completed ok. System #2 is the small system.
|
INSP-Sprinkler Rough-in | 4/13/2015 | 4/15/2015 | 4/15/2015 | P | DEFR |
Katie Marron
|
|
|
Rescheduled for 4/16 per discussion with contractor
|
INSP-Sprinkler Rough-in/Hydro | 4/7/2015 | 4/14/2015 | 4/14/2015 | P | PART |
Katie Marron
|
|
|
Hydro test on dry system #1 satisfactory completed.
|
INSP-Sprinkler Rough-in | 4/7/2015 | 4/13/2015 | 4/13/2015 | P | PART |
Forrest France
|
|
|
Partial inspection performed on Friday the 10th. One minor problem missing sprinkler in room 427 open piping. - TRF
___________
Not part of this inspection however, mentioned to Jeff the foreman. The roof outlet hose in the stairwell was to high. The valve must be accessible from standing on the landing. In addition, a ball drip on top of the valve is required.
|
INSP-Sprinkler Rough-in | 4/7/2015 | 4/10/2015 | 4/10/2015 | P | PASS |
Tim Frost
|
|
|
Passed, will required an insulation inspection at a later date.
|
INSP-Sprinkler Rough-in | 4/7/2015 | 4/9/2015 | 4/9/2015 | P | PASS |
Tim Frost
|
|
|
Area 1, level 4, Wet System. OK for cover except the floor will require an insulation inspection. Access will need to be provided for observation.
One room with sprinkler coverage that needs to be slightly altered. On one room with open pipe no sprinkller. Will verify corrections with Jeff on 04-10-2015.
|
INSP-Sprinkler Rough-in | 4/7/2015 | 4/8/2015 | 4/8/2015 | P | PART |
Tim Frost
|
|
|
Looked at four sprinklers. I clouded the areas on the drawings.
|
INSP-Sprinkler Rough-in | 3/25/2015 | 3/25/2015 | 3/25/2015 | P | PART |
Forrest France
|
|
|
Area one 2nd floor soffits okayed for cover. Exceptions include missing sprinkler coverage at the concealed space electrical chase, sheetrock mud obstructing one upright sprinkler at a concealed space, three drops yet to be cut in at unit mechanical closets.
|
INSP-Sprinkler Rough-in | 3/19/2015 | 3/20/2015 | 3/20/2015 | A | PART |
Forrest France
|
|
|
Rough-in inspection at living units 2nd floor area 3- sheets FP11 and FP9 completed. Need to relocate one blocked sprinkler at unit 227. Remainder okayed, refer to dated annotations.
|
INSP-Sprinkler Rough-in | 3/13/2015 | 3/18/2015 | 3/18/2015 | A | DEFR |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 3/13/2015 | 3/17/2015 | 3/17/2015 | A | PART |
Forrest France
|
|
|
Overhead rough-in inspection completed at living units 3rd floor area 3- refer to dated annotations on approved plans. Need corrections at unit 317, 320, 325, 327, and utility room 364- including missing heads, obstructed coverage, provide ssu at utility room, 2" CPVC main at unit 327 mechanical closet must meet listing criteria for the installation if intended to remain exposed.
|
INSP-Sprinkler Rough-in | 3/13/2015 | 3/16/2015 | 3/16/2015 | A | PART |
Forrest France
|
|
|
Refer to plans for rough-in inspection areas completed at living units 2nd floor sheets FP9, FP10, and FP11. Corrections needed at units 216,212,210 and 209 as noted.
|
INSP-Sprinkler Rough-in | 3/6/2015 | 3/9/2015 | 3/10/2015 | P | PART |
Troy Cobbley
|
|
|
Inspection is on the 3rd floor, area 2. See the city approved plans for rooms hi-lighted that are ok to cover and also areas marked with corrections such as missing heads/drops, overspaced heads and wrong heads installed.
|
INSP-Sprinkler Rough-in | 2/25/2015 | 2/26/2015 | 2/26/2015 | A | PART |
Forrest France
|
|
|
Completed rough-in inspection at the 3rd floor area 4 sheet FP17 as noted on approved plans. Relocate overspaced coverage at unit 334, min. spacing at unit 332 is not met.
|
INSP-Sprinkler Rough-in | 2/24/2015 | 2/25/2015 | 2/26/2015 | A | PART |
Forrest France
|
|
|
Overhead rough-in inspection at the 3rd floor area 2 as noted sheet FP15 completed. Need to provide standard pendent heads per plan at the electrical and mechanical rooms, verify floorplan as installed in the "type A" unit 301 is accurate and adjust coverage as necessary.
|
INSP-Sprinkler Rough-in | 2/23/2015 | 2/24/2015 | 2/24/2015 | P | CANC |
Forrest France
|
|
|
This is a OH/RTC inspection. Jeff is your contact on site. Please call 1/2 hour prior to inspection. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 2/17/2015 | 2/18/2015 | 2/18/2015 | A | PART |
Forrest France
|
|
|
Requesting UG/Flush inspection. Jeff C is your contact. Please call 1/2 prior to inspection. Phone #: ###-#### Inspection requested via web by Stan Beus * *UG fire supply line flush completed satisfactory* Note- UG permit work attatched to FIR14-00477.
|
INSP-Sprinkler Rough-in/Hydro | 2/16/2015 | 2/17/2015 | 2/17/2015 | A | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic test completed acceptable.
|
INSP-Sprinkler Rough-in | 2/12/2015 | 2/13/2015 | 2/13/2015 | A | PART |
Forrest France
|
|
|
Rough-in at the 2nd floor section one living units south-side of the north corridor completed. Missing hanger at bedroom unit 229, overspaced sprinkler coverage at unit 234. Discussed coverage at concealed pipe chases per plan. Verified previous correction items at the north side units.
|
INSP-Sprinkler Rough-in | 2/10/2015 | 2/12/2015 | 2/13/2015 | P | PART |
Forrest France
|
|
|
Completed rough-in inspection for the 2nd floor section one living units north side of corridor only. Noted missing head at the NW corner unit, overspaced coverage at unit 233.
|