Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR15-00002
StatusIssued
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 1009 W MAIN ST
Project NameMulligans Pub Remodel
Customer Number 
ePlanReviewYes
Description
This is a new system in an existing building. Shilo's work to start after 6" stub. Building is to be fully protected by a fire sprinkler system.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIR-Aging Inspection3/3/20203/3/20203/11/2020 CANC
DetailsJim Page
INSP-Final Inspection6/9/20156/10/20156/10/2015APASS
DetailsJim Page
Fire sprinkler final inspection complete
INSP-Sprinkler Rough-in/Hydro6/9/20156/9/20156/9/2015PPASS
DetailsJim Page
Underground hydrostatic test passed/complete
INSP-Supply line flush6/8/20156/9/20156/9/2015APASS
DetailsJim Page
Underground flush passed/complete
INSP-Sprinkler Rough-in/Hydro6/6/20156/8/20156/8/2015ACANC
DetailsJim Page
Per conversation with jobsite point of contact, Matt with Shilo, phone # ###-####, underground hydrostatic test cancelled, underground service not turned on. Shilo fire will reshedule hydrostatic test for future date.
INSP-Supply line flush6/6/20156/8/20156/8/2015ACANC
DetailsJim Page
Per conversation with jobsite point of contact, Matt with Shilo, phone # ###-####, service has not been turned on, need service on to do flush, flush for the scheduled date of 8JUNE2015 cancelled, main line flush will be resheduled by Shilo Fire for a later date.
INSP-Supply line flush6/4/20156/5/20156/4/2015PCANC
DetailsJim Page
This is an underground flush request. Matt is the contact. Thanks. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in6/4/20156/4/20156/4/2015PPASS
DetailsJim Page
Underground 6in. fire sprinkler main approved for cover
INSP-Sprinkler Rough-in5/22/20155/26/20155/26/2015APART
DetailsTroy Cobbley
Previous corrections for the basement and second floor have been addressed except for the sidewall head in the stairs to the second floor is still overspaced. Still missing water supply and contractor needs to provide non-combustible blocking to the basement fireing range. Also still need plan modifications approved for the piping re-route and additional fittings.
INSP-Sprinkler Rough-in/Hydro5/22/20155/22/20155/22/2015PPART
DetailsForrest France
Overhead hydrostatic test of the new wet systems basement, first and second floors completed satisfactory.
INSP-Sprinkler Rough-in5/20/20155/21/20155/22/2015PPEND
DetailsForrest France
Regarding previous correction items
INSP-Sprinkler Rough-in/Hydro5/19/20155/20/20155/20/2015PFAIL
DetailsTroy Cobbley
Inspection today was for the basement and second floor rough-in and hydro tests. Hydro tests failed due to test pump and the need to modify the system. See the city approved plans for location and corrections needed which include overspaced heads, missing branchline restraints, missing flexible cplgs and missing coverage. Ball drip is installed in wrong side of check valve. Plans need to be resubmitted showing the pipin routing changes including riser nipples, additional piping heads and elevation changes.
INSP-Sprinkler Rough-in5/18/20155/19/20155/19/2015PCANC
DetailsTroy Cobbley
Overbooked. Rescheduled for tomorrow morning
INSP-Sprinkler Rough-in4/23/20154/24/20154/24/2015APART
DetailsKatie Marron
Ok to cover main and branch and arm overs on 1st floor. A few missing hangars, contractor to correct. Verified all uprights on 1st floor, except one located above back stair well and one under front stairwell, to be verified later. All pendant locations including dry pendant drops to be verifed later. Gave OK to change from pendant to sidewall in front stair well, to be installed centered on soffit and 4" below.
FIR-Aging Inspection8/6/20208/6/2020   
DetailsJim Page