INSP-Final Inspection | 7/6/2020 | 7/8/2020 | 7/8/2020 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled per Jim
Contact Tanner Loomis ###-#### 30 min prior to Fire Final Insp start please. Tanner is requesting an AM insp. time if possible.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 6/3/2020 | 6/3/2020 | 6/3/2020 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed at riser provided gauge.
Contact Tanner Loomis ###-#### 30 Min prior to Hyrdo Insp start please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 6/2/2020 | 6/3/2020 | 6/3/2020 | A | CANC |
Jim Page
|
|
|
Contact Tanner Loomis ###-#### 30 Min prior to Hydro Insp start please Tanner is requesting a 9 AM Insp time please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Final Inspection | 6/2/2020 | 6/3/2020 | 6/3/2020 | A | FAIL |
Jim Page
|
|
|
23MAR2020 inspection notes stated some classroom walls went all the way to the deck, upright coverage was adjusted/added for extension of walls, city approved drawings need to be updated showing added haeds.
Contact Tanner Loomis ###-#### 20 min prior to Final Insp start please. Tanner would like to final after Hydro Insp sched for AM 6/3
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 6/2/2020 | 6/2/2020 | 6/2/2020 | P | CANC |
Jim Page
|
|
|
Cancelled per conversation with point of contact, visible leaks from sprinkler whips.
Contact Tanner Loomis ###-#### 30 Min prior to 2nd hydro insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 6/1/2020 | 6/2/2020 | 6/2/2020 | A | CANC |
Jim Page
|
|
|
Cancelled per conversation with point of contact, visible leaks from sprinkler whips.
Contact Tanner Loomis 208###-#### 30 min prior to Hydro Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Final Inspection | 6/1/2020 | 6/2/2020 | 6/2/2020 | A | PART |
Jim Page
|
|
|
Flow switch and tampers have been tested, all report to fire panel. Fire sprinklers to remain active and monitored after furntiure is moved into building.
Contact Tanner Loomis - ###-#### 30 min prior to Fire Final Insp start please. Note he''s scheduled a Hydro prior to Final insp.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 5/27/2020 | 5/28/2020 | 5/28/2020 | P | PART |
Jim Page
|
|
|
Rough in inspection for gymnasium area is complete. Rough to cover inspection for overhead fire sprinkler piping above hardlid type ceiling in center entry is complete, approved for cover.
Contact Tanner Loomis ###-#### 30 min prior to RTC Insp start please. Area to inspect is the high area in the middle of the building and the gym. Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 4/29/2020 | 4/30/2020 | 4/30/2020 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for corridor bwteen gym and main building complete to include office off of same hallway, area inspected approved for cover.
Contact Tanner Loomis ###-#### 30 Min prior to RTC Insp. start please, inspection is for "C" side .
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 3/24/2020 | 3/25/2020 | 3/25/2020 | P | FAIL |
Jim Page
|
|
|
During attic sprinkler coverage inspection the walls between the classrooms did not go all of the way to the bottom of the deck, since attic inspection the walls between classrooms is covered to the deck, upright coverage along walls between class rooms is overspaced in numerous areas.
Contact Tanner Loomis ###-#### RTC Insp for Areas A ; B sides, please contact Tanner 30 min prior to RTC Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 3/6/2020 | 3/6/2020 | 3/6/2020 | P | FAIL |
Jim Page
|
|
|
11.2 K factor heads are installed in an area that shows 5.6, 5 heads in opne area, 2 11.2 heads installed in an area that shows 4 5.6 heads on city approved drawings, cover is not approved, inspection stopped due to defeciencies.
Contact Tanner Loomis ###-#### 30 min prior to RTC Insp start please, this will be for the B side or Area B
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 1/3/2020 | 1/7/2020 | 1/7/2020 | P | PART |
Jim Page
|
|
|
Rough to cover ispection for hardlids and attic piping, wing A complete, attic piping approved for cover. Heads on east side of draft stop on Wing A are overspaced, will verify head coverage correction during next inspection. Area inspected on wing A approved for cover.
Contact Tanner Loomis - ###-#### 30 min prior to RTC insp start please this will be for Side A.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 12/16/2019 | 12/20/2019 | 12/20/2019 | A | PART |
Jim Page
|
|
|
Area for inspection was area B, rough in inspection for area B east of the fire doors complete, attic protection and hardlids east of fire door in area B approved for cover, a follow up cover ispection will be required for the finish pendant heads.
Contact Scott Carter - ###-#### 30 min prior to RTC Insp start please, this will be for Area A.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|