INSP-Final Inspection | 2/11/2020 | 2/12/2020 | 2/12/2020 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
George Jess is the contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Conference | 2/11/2020 | 2/11/2020 | 2/11/2020 | P | DONE |
Troy Cobbley
|
|
|
I spoke to George about re-hydro testing due to the cplg change out.
|
INSP-Final Inspection | 2/10/2020 | 2/10/2020 | 2/10/2020 | P | FAIL |
Jim Page
|
|
|
Install flexible couplings on riser, main climbing floor. Provide calc sticker on riser. Raise insulation/insulation covering in lower ceiling area off of heads. Points of attachment for sway bracing need to match detail on city approved drawings, ie through bolts and double lumber.
George Jess is the contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 2/5/2020 | 2/6/2020 | 2/6/2020 | A | CANC |
Troy Cobbley
|
|
|
To be cancelled per George Jess is the contact for this inspection. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 2/4/2020 | 2/5/2020 | 2/5/2020 | A | FAIL |
Troy Cobbley
|
|
|
Not ready for final due to the project related fire alarm permit. Previous corrections for sprinkler spacing have been corrected.
George Jess is the Contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 1/21/2020 | 1/22/2020 | 1/22/2020 | A | PASS |
Troy Cobbley
|
|
|
Overhead Hydro witnessed with no pressure loss. George is the contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 1/17/2020 | 1/21/2020 | 1/21/2020 | A | FAIL |
Troy Cobbley
|
|
|
Overhead hydo test failed based on visible loss of pressure at guage. George Jess is the contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 1/14/2020 | 1/14/2020 | 1/14/2020 | P | PART |
Troy Cobbley
|
|
|
Need all small documents prior to next inspection. Plan mods needed showing additional fittings in main piping, riser nipple lengths and pipe size changes. Upright sprinkler heads appear to obstructed in the low roof portioin of project. Need to meet three times rule. General rough in looks okay.
George Jess is the contact for this RTC Inspection. Thank you for your help and have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 12/19/2019 | 12/20/2019 | 12/20/2019 | A | PASS |
Troy Cobbley
|
|
|
The combustible concealed space below the ramp has been filled with insulation.
George Jess is the contact. This is for an overhead Hydro. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|