INSP-Final Inspection | 6/23/2020 | 6/24/2020 | 6/24/2020 | A | PASS |
Jim Page
|
|
|
Final inspection complete.
Underground Final Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Supply line flush | 5/29/2020 | 6/1/2020 | 6/1/2020 | A | DONE |
Jim Page
|
|
|
Underground main line flush witnessed.
Scheduled for 9am with Stacy at Suez. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 5/27/2020 | 5/27/2020 | 5/27/2020 | P | DONE |
Jim Page
|
|
|
Hydrostsic test for underground supply witnessed, no pressure loss observed at gauge before backflow.
Underground hydro. Ready any time, call James before heading out. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 11/26/2019 | 11/26/2019 | 11/26/2019 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
|
INSP-Sprinkler Rough-in | 11/25/2019 | 11/25/2019 | 11/25/2019 | A | FAIL |
Jim Page
|
|
|
Underground not installed at time of inspection.
Call before heading out, underground rough to bury (hydro in warm weather or closer to final) Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|