INSP-Final Inspection | 6/5/2020 | 6/9/2020 | 6/9/2020 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete, irrigation shut-down on flow switch activation has been witnessed.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in/Hydro | 6/5/2020 | 6/9/2020 | 6/9/2020 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire srpinkler piping witnessed at city pressure, no pressure loss onserved at riser provided gauge.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in | 4/14/2020 | 4/15/2020 | 4/15/2020 | A | PASS |
Jim Page
|
|
|
Tenting has been corrected, cover is approved, sticker has been placed for cover approval.
tenting Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in | 4/13/2020 | 4/14/2020 | 4/14/2020 | A | FAIL |
Jim Page
|
|
|
Piping is completely wrapped in 4 areas, pocket is not provided for freeze protection. One area is not covered correctly, pocket between sheetrock and piping will be comprimised, cover is not approved.
cover is wrapped tenting Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in | 4/6/2020 | 4/8/2020 | 4/8/2020 | A | PART |
Jim Page
|
|
|
Rough in inspection is complete, minor modifications/head additions was required to be compliant with NFPA13R, drawings to be submitted showing head additions/changes made. No tenting installed at time of inspection, cover is not approved.