Permit Information
Permit NumberFIR20-00340
StatusIssued
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 790 N LANDERS ST
Project NameLSWRF PHASE 1 PACKAGE H HW
Customer Number 
ePlanReviewYes
Description
**QUICK PERMIT** THIS IS FOR THE UG PORTION ONLY OF THE HEADWATERS BUILDING.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Conference7/16/20207/16/20207/16/2020PDONE
DetailsJim Page
Fire conference is complete. Advised Dustin with MCALVAIN too email Joe Bruce, Fire Section Supervisor too see if a variance can be granted to have the PIV closer than 40 feet to the building. PIV location was compromised due too fire truck access, PIV is no longer in the parking lot island as designed, island had to be shortened for fire truck access. A re-submittal will be required for underground supply re-route as noted on previous inspection and too show new location for PIV.
INSP-Sprinkler Rough-in7/16/20207/16/20207/16/2020PCANC
DetailsJim Page
Request was for a conference, this request is cancelled.

Screened- Dustin Phone #: ###-####
INSP-Sprinkler Rough-in7/7/20207/8/20207/8/2020APART
DetailsTroy Cobbley
The 6" supply line is ok to cover except where the PIV needs to be installed and the connection to the IBR. The remote FDC piping can be covered from the building to the end of the first 21' of pipe.

Underground -Dustin *screened* Phone #: ###-####
INSP-Supply line flush7/2/20207/2/20207/2/2020ADONE
DetailsJim Page
Re-route supply main flush witnessed via video.
INSP-Sprinkler Rough-in7/1/20207/2/20207/2/2020APART
DetailsJim Page
Rough to cover inspection for fire service main underground re-route complete, plans need to reflect re-route before final inspection, re-route approved for cover at contractors descretion provided re-route does not effect water calculations for down-stream fire sprinkler services.

Dustin Phone #: ###-####
INSP-Sprinkler Rough-in6/30/20207/1/20207/1/2020PFAIL
DetailsTroy Cobbley
Need drawings and small documents, need piping uncovered for inspection, Shilo needs to be involved in installation as per state code, need flushing of the modified/new piping.

underground- Dustin *screened* Phone #: ###-####
INSP-Sprinkler Rough-in6/4/20206/4/20206/4/2020PPART
DetailsJim Page
Rough to cover inspection for IBR and FDC building stub in compete, areas inspected approved for cover. Remaining underground to be inspected at a later date.