INSP-Sprinkler Rough-in | 7/16/2020 | 7/16/2020 | 7/16/2020 | P | FAIL |
Jim Page
|
|
|
Plans will need to be re-submitted to show use of flex drops in the grid ceiling. Add head where duct work is blocking coverage on first floor, notated on city approved drawing. Add sway brace that was not installed on level 2. Space under first floor stairs appears to be a combustible concealed pocket, if area is combustible then heads will have to be added or filled with non-combustilble insulation as discussed. Add upright head under duct work as notated on city approved drawings.
Please call Chris Ford Phone #: ###-#### Inspection requested via web by Jessia McLain
|
INSP-Sprinkler Rough-in | 7/6/2020 | 7/7/2020 | 7/7/2020 | A | PASS |
Troy Cobbley
|
|
|
1st floor piping above the hardlids, as marked on the plans, is ok for cover.
Please call Chris Ford rough-in on the 1st floor please Phone #: ###-#### Inspection requested via web by Jessia McLain
|