INSP-Sprinkler Rough-in/Hydro | 7/14/2020 | 7/14/2020 | 7/14/2020 | A | DONE |
Jim Page
|
|
|
Hydrostatic test witnessed, no pressure loss observed at riser provided gauge.
Call James before heading out, rough/hydro/tenting. Thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 7/14/2020 | 7/14/2020 | 7/14/2020 | A | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, cover is approved. All tenting in place at time of inspection.
|
INSP-Sprinkler Rough-in/Hydro | 7/13/2020 | 7/13/2020 | 7/13/2020 | A | FAIL |
Jim Page
|
|
|
Contractor was to meet at 0845 per text conversation, waited until 9AM for contractor. System was not pumped up at time of inspection, due to water on floor it appears a repair was made. Section of tenting missing by attic access, cover is not approved, proceeded to next inspection.
As built approved. Call James before heading out Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 7/13/2020 | 7/13/2020 | 7/13/2020 | A | PART |
Jim Page
|
|
|
Previously noted items have been corrected, install matches what is submitted, head has been added under stairs at top of closet.
|
INSP-Sprinkler Rough-in/Hydro | 7/9/2020 | 7/9/2020 | 7/9/2020 | A | FAIL |
Troy Cobbley
|
|
|
Inspection turned into a walk-through/conference. I noted that the plans do need to be resubmitted for changes and a head needs to be added at the top fo the under/stairs to meet NFPA 13D 8.2.7. No piping to be covered yet. Could not do hydro since a head needs to be added.
Call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|