Change Expiration Date Only | | | 5/1/2020 | | DONE |
Jason Blais
|
|
|
A 180 day extension is granted from 6/20/20. This is the first extension request for an issued permit.
|
BLD-Conference | 12/20/2019 | 12/23/2019 | 12/23/2019 | A | DONE |
Mike Jordan
|
|
|
Vlad- call prior Phone #: ###-####
|
BLD-Energy code compliance | 12/23/2019 | 12/23/2019 | 12/23/2019 | A | PASS |
Mike Jordan
|
|
|
Vlad- call prior Phone #: ###-####
|
BLD-Energy code compliance | 12/23/2019 | 12/23/2019 | 12/23/2019 | A | PASS |
Mike Jordan
|
|
|
Vlad- call prior Phone #: ###-####
|
BLD-Conference | 12/2/2019 | 12/2/2019 | 12/2/2019 | P | DONE |
Mike Jordan
|
|
|
Vlad- please try to call 20 prior Phone #: ###-####. Ok to sheet rock ceilings only.
|
BLD-Conference | 8/22/2019 | 8/22/2019 | 8/22/2019 | P | DONE |
Mike Jordan
|
|
|
David Phone #: ###-####
|
BLD-Framing/Rough-in | 9/24/2018 | 9/25/2018 | 9/25/2018 | A | PASS |
Mike Jordan
|
|
|
Call ten minutes before to meet // Vlad Phone #: ###-####. New patio framing ok. New entry framing ok. Ok to install windows tyvek and roofing.
|
BLD-Conference | 2/22/2018 | 2/23/2018 | 2/23/2018 | P | PASS |
Mike Jordan
|
|
|
Please call ahead for access - Vlad Phone #: ###-####
|
BLD-Wall Bracing | 2/23/2018 | 2/23/2018 | 2/23/2018 | P | PASS |
Mike Jordan
|
|
|
Please call ahead for access - Vlad Phone #: ###-####. New addition on west side.
|
BLD-Wall Bracing | 1/24/2018 | 1/25/2018 | 1/25/2018 | A | NR |
Mike Jordan
|
|
|
shear nail- Sanal Phone #: ###-####. Install all missing blocking per the engineering.
|
BLD-Framing/Rough-in | 11/22/2017 | 11/24/2017 | 11/24/2017 | A | PART |
Jim Sly
|
|
|
Please call ahead for access for floor framing - Vladmir Phone #: ###-#### Floor framing and Insulation.......OK.
|
BLD-Framing/Rough-in | 11/20/2017 | 11/21/2017 | 11/21/2017 | A | PART |
Mike Jordan
|
|
|
floor- call on your way please- Vlad Phone #: ###-####. Floor framing over existing garage slab. vapor barrier installed. Needs to insulate with R-30. Advised to dry under floor area prior to insulation and to keep dry.
|
Routing - MECHANICAL | 11/21/2017 | | 11/21/2017 | | PASS |
Chad Schwendiman
|
|
|
|
BLD-Framing/Rough-in | 10/30/2017 | 11/2/2017 | 11/2/2017 | P | CANC |
Mike Jordan
|
|
|
Cancel per Vladimir floor framing // Vlad Phone #: ###-####
|
BLD-Conference | 10/3/2017 | 10/4/2017 | 10/4/2017 | A | DONE |
Mike Jordan
|
|
|
Between 11:00 and 12:00. Needs electrical conferance.
|
BLD-Conference | 10/2/2017 | 10/3/2017 | 10/3/2017 | A | CANC |
Mike Jordan
|
|
|
Call half hour before to meet // Vlad Phone #: ###-####. Moved to am tomorrow.
|
BLD-Foundation | 6/9/2017 | 6/12/2017 | 6/12/2017 | A | PASS |
Jim Sly
|
|
|
Jose Phone #: ###-#### - 12pm please
|
BLD-Foundation | 6/5/2017 | 6/8/2017 | 6/8/2017 | P | CANC |
Dave Hannah
|
|
|
Jose Phone #: ###-####-would like around two if possible
|
BLD-Footing | 6/7/2017 | 6/8/2017 | 6/8/2017 | A | PASS |
Jim Storey
|
|
|
|
BLD-Footing | 6/7/2017 | 6/7/2017 | 6/7/2017 | P | NR |
Mike Jordan
|
|
|
|
BLD-Footing | 6/6/2017 | 6/7/2017 | 6/7/2017 | P | CANC |
Mike Jordan
|
|
|
Will be ready at 10 Phone #: ###-####. Moved to pm inspection per Juan via phone call.
|
BLD-Footing | 6/5/2017 | 6/6/2017 | 6/6/2017 | P | NR |
Mike Jordan
|
|
|
Jose Phone #: ###-####. Will recall for in the am.
|
OVERRIDE | | | 5/16/2017 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 5/11/2017 | 5/11/2017 | 5/16/2017 | | PASS |
Josh Bogle
|
|
|
wainting in Brian to double-check my work josh 5-11-17
|
1st review completed | | | 5/16/2017 | | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 5/16/2017 | | 5/16/2017 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 5/16/2017 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 5/16/2017 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/16/2017 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 5/16/2017 | | DONE |
|
|
|
|
Telephone call | | | 5/16/2017 | | DONE |
|
|
|
Spoke with Vladimir informing him that his permit is ready to be picked up and the amount due for issuance
|
Issue PAID IN FULL permit | | | 5/16/2017 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/9/2017 | | DONE |
|
|
|
Two copies of Structural Engineering Calculations, Two copies of sheets S1.0, S1.1, S1.2, S3.0, S4.0 and S4.1 taken to Josh B
|
Routing Walk-In (BLD) | 5/8/2017 | 5/8/2017 | 5/8/2017 | P | CANC |
Josh Bogle
|
|
|
permit tech took in resubmittals
|
Routing Walk-In (BLD) | 5/4/2017 | 5/4/2017 | 5/8/2017 | P | DONE |
Candy A. Nichols
|
|
|
|
Routing Walk-In (Zoning) | 5/4/2017 | 5/4/2017 | 5/4/2017 | P | PASS |
David Moser
|
|
|
|
Application received | | 5/4/2017 | | | |
|
|
|
|