Permit Information
Permit NumberBLD17-02704
StatusFinaled
Name PROJECT BUILDERS INC
Site Address 7402 W FAIRVIEW AVE
Project NameCVS Pharmacy - New Building
Customer Number 
ePlanReviewYes
Description
(CVS PHARMACY – NEW BUILDING AND TENANT IMPROVEMENT) (DRH17-00113) (CUP17-00018) (CVA17-00022) (10-9-18 PLAN MODIFICATION TO REMOVE THE WEST ACCESSIBLE CURB RAMP AT WILSHIRE DRIVE AND TO ADJUST THE VEHICLE ACCESS TO CONNECT INTO THE EXISTING VALLEY GUTTER SO THAT THE DISTURBANCE TO THE ADJACENT PROPERTY OWNER’S DRIVEWAY IS MINIMIZED. APPROVAL BY ACHD IS REQUIRED.) (8-22-18 PLAN MODIFICATION TO CONSTRUCT AN EXTERIOR RAMP ACCESSIBLE TO THE DISABLED [1:20 MAX. SLOPE], TO MODIFY THE FORMERLY PROPOSED EXTERIOR STEPS TO ADD MORE RISERS AND TREADS, TO CHANGE THE ROUTING OF STORM WATER DRAIN LINES, AND TO ADD A STORM WATER INFILTRATION SWALE. THE RAMP IS REQUIRED TO BE ACCESSIBLE TO THE DISABLED AS DEFINED BY CURRENT ACCESSIBILITY STANDARDS. HANDRAILS ARE REQUIRED ON THE STAIRWAY.) The fire sprinkler system is used for fire area. Three buildings and the East end of an existing retail sales building will be demolished to accommodate this new development. To construct a 12,648 square foot building (14,476 square feet including the 1,828 square foot enclosed mezzanine) to be used as a pharmacy and for retail sales. Work is to include concrete footings, concrete foundations, concrete slab on grade with slab edge insulation, masonry exterior walls, insulation installed on the inside of the masonry exterior walls, EIFS installed on the outside of masonry exterior walls, steel roof joists, steel roof deck, insulation installed on top of the roof deck, a roof membrane, exterior windows, exterior doors, an exterior roll-up door at the receiving area, suspended acoustical ceilings, gypsum board soffits, a VRC (Vertical Reciprocating Conveyor) with shallow pit and gates, a horizontal sliding security grill at the pharmacy, a hatch and ladder to the roof, interior nonbearing walls, two toilet rooms accessible to the disabled, display shelves, millwork, and finishes. Mezzanine work includes concrete footings, steel columns, steel girders, steel beams, concrete floor on a steel deck, and a steel stairway. Special Inspection is required for soils, concrete, masonry, anchors post-installed in hardened concrete or masonry, welding, and EIFS. All of the storage and display shelves will be less than 8 feet high. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. This permit is intended to establish a Certificate of Occupancy for this tenant and for the entire building. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  5/20/2019 DONE
Third Notice 4/13/20195/6/2019 DONE
mailed 5-10-19 with second follow up letter
Second Follow up  5/6/2019 DONE
Third Notice 3/16/20194/8/2019 DONE
mailed 4-11-19 with first follow up letter
First Follow up  4/8/2019 DONE
mailed 4-11-19
Third Notice 2/12/20193/11/2019 DONE
mailed 3-12
Third Notice 1/13/20192/7/2019 DONE
mailed 2-11-19
Second Notice 12/24/20181/8/2019 DONE
mailed 1-11-19
First Notice 12/7/201812/14/2018 DONE
mailed 12-17
BLD-Final11/27/201811/27/201811/27/2018PPASS
DetailsMike Jordan
Mark Phone #: ###-####. Ok for perm occ.
Zoning Approval11/27/201811/27/201811/27/2018 DONE
DetailsAndrea Tuning
Permanent Occupancy  11/27/2018 DONE
BLD-Final11/1/201811/2/201811/2/2018PPART
DetailsJim Sly
Mark Phone #: ###-####
OK for Temp. Occ. Zoning on Bond. OK for Perm Occ. when ........Zoning and ACHD signs off for Perm. Occ. Talked to Bill Gaul at ACHD 208 387 6100.
FIRE-Final Inspection11/1/201811/2/201811/2/2018APASS
DetailsTroy Cobbley
Life safety passed

Mark Phone #: ###-####
Temporary Occupancy11/2/20181/31/201911/2/2018 DONE
DetailsBrittany Hill
Zoning Approval Temp11/2/201811/2/201811/2/2018 DONE
DetailsAndrea Tuning
Bond posted for courtyard, benches, sidewalks and two trees
FIRE-Final Inspection11/1/201811/1/201811/1/2018PCANC
DetailsTroy Cobbley
Mark Phone #: ###-####
FIRE-Final Inspection10/30/201810/31/201810/31/2018PFAIL
DetailsTroy Cobbley
Still need all of the emergency lights over the sales floor repaired and tested.

Mark Phone #: ###-####
PubWorks Occupancy Approval10/31/201810/31/201810/31/2018 DONE
DetailsTiffany Lowery
BLD-Final10/29/201810/30/201810/30/2018PNR
DetailsJim Sly
Mark Phone #: ###-####
FIRE-Final Inspection10/29/201810/30/201810/30/2018AFAIL
DetailsTroy Cobbley
Repair the exit discharge light at the stockroom exit door, provide exit sign on mezzanine, provide all emergency lighting as per the city approved plans.

Mark Phone #: ###-####
CHANGE STATUS TO (ISS)  10/29/2018 DONE
Plan Mod
OVERRIDE  10/9/2018  
Plan assigned to (CJW)9/27/20189/27/201810/9/2018 PASS
DetailsCarl Westfall
Plan Mod #2 - CVS Pharmacy (routed to other agencies)
Plan Reviewer's activity  10/9/2018 PASS
Plan mod approved
Permit Ready to Issue  10/9/2018 DONE
Plan Mod Approved
Do Not ReIssue
Routing - Design Review9/27/2018 10/8/2018 PASS
DetailsAndrea Tuning
FIRE-Conference10/2/201810/2/201810/2/2018PDONE
DetailsTroy Cobbley
Mark and I went over the typical life safety requirements. He did not have the updated plans or any of the small documents.

Mark Phone #: ###-####
Routing - PLANNING9/27/2018 9/28/2018 PASS
DetailsNicolette Womack
Plan Modification Accepted  9/27/2018 DONE
DetailsChristina Prado
Plan Mod #2 - ADA ramp along Wilshire Dr has been removed and the access adjusted to connect into the existing valley gutter to limit the disturbance of the adjacent property owners driveway. All changes have been approved by ACHD
Routing - PUBLIC WORKS9/27/2018 9/27/2018 PASS
DetailsBeverly Mountain
Routing - PLAN CHECK9/27/2018 9/27/2018 PASS
DetailsCarl Westfall
Plan mod plan intake review approved. Plan mod review approved.
BLD-Ceiling Grid Inspection9/7/20189/7/20189/10/2018PPASS
DetailsJim Sly
Mark Phone #: ###-####
BLD-Ceiling Grid Inspection8/30/20188/30/20188/30/2018PPEND
DetailsDave Hannah
just to do boarder tiles// Mark Phone #: ###-#### ok to cover main area after other trades sign off
CHANGE STATUS TO (ISS)  8/30/2018 DONE
Plan Mod
OVERRIDE  8/24/2018  
Plan assigned to (CJW)7/31/20187/31/20188/24/2018 PASS
DetailsCarl Westfall
Plan Mod - CVS Pharmacy (2nd done and routed)
PLANS/APPL TAKEN TO FRONT DESK  8/24/2018 DONE
Permit Ready to Issue  8/24/2018 DONE
Plan mod-Pleae do not re issue
Routing - Design Review8/22/2018 8/23/2018 PASS
DetailsAndrea Tuning
Plan resubmittals received  8/22/2018 DONE
Routing - PLAN CHECK8/22/2018 8/22/2018 PASS
DetailsCarl Westfall
BLD-Framing/Rough-in8/10/20188/13/20188/13/2018APASS
DetailsJim Storey
Mark Phone #: ###-#### pharm and receiving areas ok to cover
BLD-Framing/Rough-in8/2/20188/6/20188/6/2018APART
DetailsJim Sly
Mark ###-####
OK to cover Front Canopy, Corridor, restrooms and locker room.
Plan resubmittals requested  8/2/2018 DONE
Routing - PLAN CHECK7/31/2018 8/1/2018 FAIL
DetailsCarl Westfall
Ramp and handrail details required
Routing - Design Review8/1/2018 8/1/2018 FAIL
DetailsAndrea Tuning
All light poles and fixtures shall be located outside of the required setbacks and landscape planters which contain trees as required by the landscape ordinance. All lighting shall also be designed and located so as to prevent glare or direct light from falling onto adjoining properties or streets. All new pole lighting shall feature 100 percent cut-off light fixtures and all new wall lighting shall have full cut-off shields.

Replace the Chanticleer Pear trees within the planter islands in the southwest corner of the site with Class II trees.
Routing - PUBLIC WORKS8/1/2018 8/1/2018 PASS
DetailsMorgan Webb
Routing PW Drainage8/1/2018 8/1/2018 PASS
DetailsBrian Murphy
Plan Modification Accepted  7/31/2018  
Plan Mod - Fairview Avenue and Cole Road was constructed higher than anticipated requiring the site to be re-graded and an
Accessible ramp constructed near the intersection. Also, shallow dry utilities (existing) required a change in routing of
storm drain lines. An infiltration swale was added near the Wilshire Drive access as a result of shallow dry utilities.
BLD-Framing/Rough-in7/20/20187/20/20187/20/2018PPART
DetailsJim Sly
Mark Phone #: ###-####
South 2/3 of bldg....OK
BLD-Framing/Rough-in7/5/20187/6/20187/6/2018APART
DetailsJim Sly
Mark Phone #: ###-####
OK to rock.......Elevator, Mezzanine and Walls 4 foot down from Ceiling.
BLD-Conference6/20/20186/20/20186/21/2018PDONE
DetailsJim Sly
Mark Phone #: ###-####
BLD-Other5/22/20185/22/20185/23/2018PPART
DetailsJim Sly
Mark -a rebar placement and masonery wall- 8 foot lift on columns and 12 ft lift on drive thru Phone #: ###-####
BLD-Other5/21/20185/21/20185/21/2018PPART
DetailsJim Sly
rebar in masonry wall // 24 foot lift west wall // Mark Phone #: ###-####
OK pending MTI insp, tests and approvals.
BLD-Other5/18/20185/18/20185/21/2018PPART
DetailsJim Sly
Mark Project--rebar replacemt masonery wall-24 foot lift so and west walls Phone #: ###-####
MTI on site
BLD-Other5/17/20185/17/20185/17/2018PPART
DetailsJim Sly
Mark-masonary wall to grout south and west wall 20'' Phone #: ###-####
OK pending MTI special inspection,tests and approvals.
BLD-Foundation5/15/20185/16/20185/16/2018ACANC
DetailsJim Sly
16ft lift south wall Rebar // Mark Phone #: ###-####
OK pending MTI special insp, tests and approvals.
BLD-Wall Bracing5/11/20185/11/20185/11/2018PPART
DetailsJim Sly
Mark-wall rebar placing-south wall and west wall 8 foot lift Phone #: ###-####MTI on site
BLD-Other5/9/20185/10/20185/10/2018APART
DetailsJim Sly
rebar- 4ft lift south wall Phone #: ###-####
OK pending MTI special insp, tests and approvals.
BLD-Foundation5/7/20185/8/20185/8/2018PPART
DetailsJim Sly
Rebar... 24ft lift north wall // Mark Phone #: ###-####
OK pending MTI special insp, tests and approvals.
BLD-Foundation5/7/20185/7/20185/7/2018PPART
DetailsBrandon Shaw
Rebar.. 24 ft. lift east wall
BLD-Foundation5/4/20185/4/20185/6/2018PPART
DetailsJim Sly
Mark-masonary rebar-pour time 2:00 noth wall 20 ft lifts Phone #: ###-####
BLD-Footing5/2/20185/3/20185/3/2018PPART
DetailsJim Sly
Masonry wall, rebar, 20ft lift N & E walls - Mark Phone #: ###-####
MTI on site
BLD-Foundation5/1/20185/2/20185/2/2018PPASS
DetailsJim Sly
Rebar... 16ft list mes.wall north and est // Mark Phone #: ###-####
OK pending MTI special insp, tests and approvals.
BLD-Other4/30/20184/30/20184/30/2018PPART
DetailsBrandon Shaw
rebar placement & masonry wall east and north walls
OK pending MTI special insp, tests and approvals.
BLD-Footing4/27/20184/27/20184/27/2018PPART
DetailsJim Sly
sub-grade rebar - Mark Phone #: ###-####
OK pending MTI special insp, tests and approvals.
BLD-Foundation4/27/20184/27/20184/27/2018PPART
DetailsJim Sly
Mark-8'' lift-east wall and north wall Phone #: ###-####
OK pending MTI special insp, tests and approvals.
BLD-Foundation4/25/20184/25/20184/25/2018PPART
DetailsJim Sly
Mark-rebar on 4ft lift masonary wall on east and north walls Phone #: ###-####
OK pending MTI special inspection, Tests and Approvals.
BLD-Footing4/23/20184/23/20184/23/2018PPART
DetailsJim Sly
Mark-rebar Phone #: ###-####
OK pending MTI special insp, tests and approvals.
BLD-Footing4/17/20184/18/20184/18/2018PPART
DetailsJim Sly
Mark-pour time 2:30 Phone #: ###-####
Exterior Wall footings....OK pending MTI special inspections, tests and approvals.
(F) Reprint permit  3/5/2018 DONE
(F) Reprint permit  3/5/2018 DONE
Issue PAID IN FULL permit  3/1/2018 DONE
Print Occupancy Form  3/1/2018 DONE
Print Occupancy Form  3/1/2018 DONE
OVERRIDE  2/26/2018  
Plan assigned to (CJW)8/16/20178/16/20172/26/2018 PASS
DetailsCarl Westfall
(3rd done) (Sept 19 - 25 days) (83 sheets) CVS Pharmacy
PLANS/APPL TAKEN TO FRONT DESK  2/26/2018 DONE
Permit Ready to Issue  2/26/2018 DONE
Routing - PLANNING Land Div2/17/2018 2/26/2018 PASS
DetailsTodd Tucker
Routing - Design Review2/17/2018 2/26/2018 PASS
DetailsAndrea Tuning
Routing - PLANNING2/17/2018 2/21/2018 PASS
DetailsNicolette Womack
Routing - PLAN CHECK2/16/2018 2/17/2018  
DetailsCarl Westfall
routed drawings
Plan resubmittals received  2/16/2018 DONE
Plan resubmittals requested  1/2/2018 DONE
Routing PW Drainage12/21/2017 12/29/2017 PASS
DetailsBrian Murphy
Sheet C4.10 changed a little. Please copy your approval stamp to the latest version
Routing - PLANNING Land Div12/21/2017 12/28/2017 FAIL
DetailsTodd Tucker
ROS has not been completed.
Routing - Design Review12/21/2017 12/27/2017 FAIL
DetailsAndrea Tuning
Record of Survery is not complete.
Routing - PLANNING12/21/2017 12/21/2017 FAIL
DetailsNicolette Womack
ROS has not been completed. Alternative to provide demo bond and hold harmless letter not provided either.
Plan resubmittals received  12/21/2017 DONE
Routing - PLAN CHECK12/21/2017 12/21/2017 PASS
DetailsCarl Westfall
Plan resubmittals requested  11/14/2017 DONE
Routing Off Site - STRUCTURAL11/8/2017 11/10/2017 PASS
DetailsCarl Westfall
Chris Holladay (AHJ)
Routing - PLAN CHECK11/7/2017 11/8/2017 PASS
DetailsCarl Westfall
Pending structural
Routing - PLANNING11/8/2017 11/8/2017 FAIL
DetailsNicolette Womack
ROS has not been completed. Alternative to provide demo bond and hold harmless letter not provided either.
Routing - PLANNING Land Div11/8/2017 11/8/2017 FAIL
DetailsTodd Tucker
ROS has not been completed. Alternative to provide demo bond and hold harmless letter not provided either.
Routing - Design Review11/8/2017 11/8/2017 FAIL
DetailsAndrea Tuning
Record of Survey is not complete
Plan resubmittals received  11/7/2017 DONE
Plan resubmittals requested  10/30/2017 DONE
Routing Off Site - STRUCTURAL10/20/2017 10/27/2017 FAIL
DetailsCarl Westfall
Chris Holladay (AHJ)
Routing - PLAN CHECK10/20/2017 10/23/2017 FAIL
DetailsCarl Westfall
Structural sheets do not match the architecural sheets.
Routing - PLANNING10/20/2017 10/23/2017 FAIL
DetailsNicolette Womack
Record of Survey has not been completed.
Routing - PLANNING Land Div10/20/2017 10/23/2017 FAIL
DetailsTodd Tucker
Record of Survey has not been completed.
Routing - Design Review10/20/2017 10/23/2017 FAIL
DetailsAndrea Tuning
Record of Survery is not complete
Plan resubmittals received  10/20/2017 DONE
Telephone call  10/16/2017 DONE
Discussed the plan review report with the Architect
Route to Impact Fee Review10/7/201710/10/201710/10/2017 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  10/7/2017 DONE
Plan resubmittals requested  10/7/2017 DONE
Routing - PLAN CHECK8/16/2017 10/7/2017 FAIL
DetailsCarl Westfall
8 days late
Routing PW Environmental8/17/2017 9/15/2017 PASS
DetailsRick Christenson
Routing - FIRE8/16/20178/16/20178/29/2017 PASS
DetailsScott Arellano
Attached comments to plans.
Routing Off Site - STRUCTURAL8/16/2017 8/29/2017 FAIL
DetailsCarl Westfall
Chris Holladay (AHJ)
Routing PW Drainage8/17/2017 8/23/2017 PASS
DetailsBrian Murphy
Routing PW Street Lights8/17/2017 8/21/2017 PASS
DetailsTom Marshall
Routing - Design Review8/16/2017 8/18/2017 FAIL
DetailsAndrea Tuning
Record of Survery is not complete and the 25% facade transparecny on Fairview Avenue has not been met.
Routing - Erosion and Sediment8/16/2017 8/18/2017 PASS
DetailsAndy J. Long
ESC plan with site map and narrative submitted. Need to designate RP at time of contract bid. Site preparation inspection required.
Routing PW Solid Waste8/17/2017 8/17/2017 PASS
DetailsEvan Carpenter
Routing - MECHANICAL8/16/2017 8/17/2017 PASS
DetailsTroy James
Routing - PLUMBING8/16/2017 8/17/2017 PASS
DetailsBill VanDegrift
see redlines, cross connection control, pipie sizing, venting
Routing - PLANNING8/16/2017 8/17/2017 FAIL
DetailsNicolette Womack
Property Line Adjustment/Parcel Consolidation has not been finalized.
Routing - PLANNING Land Div8/16/2017 8/17/2017 FAIL
DetailsTodd Tucker
Property Line Adjustment/Parcel Consolidation has not been finalized.
Routing - Addressing8/16/2017 8/17/2017 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS8/16/2017 8/17/2017 PASS
DetailsRachael Beierle
Intake Approval  8/16/2017 PASS
Intake Approval  8/15/2017 FAIL
DetailsJulie Romig
4. Reduce file size of sheets A2.12, A2.15, and A2.16 and re-upload - sheets are too large to open. Files should be 1 MB or less.
Plan Reviewer's activity  8/15/2017 DONE
DetailsJulie Romig
Emailed applicant regarding file size.
Intake Approval  8/9/2017 FAIL
DetailsJulie Romig
Provide the following:
1. Verification of Legal Lot and Parcel Forms need to be signed by Planning. Contact Todd Tucker at TTucker@cityofboise.org.
2. CDHD Stamped Approval - indicated on checklist but not uploaded.
3. Fire Riser room details - indicated on FP1, but sheet is not uploaded.
4. Reduce file size of sheets A2.12, A2.15, and A2.16 and re-upload - sheets are too large to open.
5. Hazardous Material Inventory & Classification Report indicated on checklist but not found. Upload or provide location of report.
6. Modifications to code, alternative materials indicated, on checklist but not found. Upload or provide location of report.
Application received  8/2/2017 DONE
Application submitted via PDS Online on Aug 2 2017 2:26PM