Information based on query as of Monday, May 20, 2024.
Permit Information
Permit NumberBLD17-04133
StatusFinaled
Name ESI
Site Address 3266 E BARBER VALLEY DR
Project NameVeranda at Barber Station
Customer NumberBLD18-00230/FND BLD17-03587
ePlanReviewYes
Description
(VERANDA AT BARBER STATION Building A) (2 PERMITS IN EPLAN UNDER BLD17-04133) **PROJECT MANAGEMENT - Angie Brosious ""PLAN MODIFICATION 2 FOR MECHANICAL ALTERATIONS AND INSTALLATION OF A LIFT STATION 11/27/18"" ""PLAN MODIFICATION FOR MECHANICAL DUCTING, INSTALLATION OF A LIFT STATION AT THE GREASE INTERCEPTOR"" Permit for the construction of a 36,087 sq. ft. 45 room memory care center (foundation and site under BLD17-03587) with work to include the construction of a new wood framed building with all associated interior and exterior finsihes per the approved plans. This building is fully fire sprinklered for area increas and occupancy type. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  7/22/2019 DONE
Third Notice 6/12/20197/10/2019 DONE
mailed 7-11 with first follow up
First Follow up  7/10/2019 DONE
Third Notice 5/11/20196/7/2019 DONE
mailed 6-10
Second Notice 4/18/20195/6/2019 DONE
mailed 5-10-19
First Notice 3/17/20194/8/2019 DONE
mailed 4-11-19
Zoning Approval3/7/20193/7/20193/7/2019 PASS
DetailsKatelyn Menuge
Zoning Final
Permanent Occupancy  3/7/2019 DONE
CHANGE STATUS TO (ISS)  2/27/2019 DONE
should not have been final/closed
BLD-Final2/25/20192/25/20192/25/2019PPASS
DetailsBrandon Shaw
Scott Phone #: ###-####
DOC - Permit Finaled2/25/20192/25/20192/25/2019PPASS
DetailsBrandon Shaw
FIRE-Final Inspection2/22/20192/25/20192/25/2019APASS
DetailsJim Page
Final life fire safety inspection complete.

Scott Phone #: ###-####
PubWorks Occupancy Approval2/1/20192/1/20192/1/2019 DONE
DetailsTiffany Lowery
BLD-Final1/31/20191/31/20191/31/2019PPART
DetailsBrandon Shaw
Temp C of O has been OK'd...
FIRE-Final Inspection1/30/20191/30/20191/30/2019APART
DetailsJim Page
TCO for fire life safety approved per conversation with Ron Johnson for 30 days for vendor/employee training only. Once fire alarm permit is finaled then life fire safety can be signed off as finaled.

Schedule to come at the same time as the Fire Alarm inspection. Thanks Phone #: ###-#### Inspection requested via web by JT Turner
FIRE-Final Inspection1/28/20191/29/20191/29/2019ACANC
DetailsTroy Cobbley
Need the project related FIR permits scheduled and finaled prior to a life safety inspection.

Phone #: ###-#### Inspection requested via web by JT Turner
FIRE-Final Inspection1/28/20191/28/20191/28/2019PFAIL
DetailsJim Page
FIR permits for fire alarm, fire alarm communicator and hood suppression system needs to be completed and finaled before life fire safety inspection can be completed.

Phone #: ###-#### Inspection requested via web by JT Turner
Zoning Approval Temp1/25/20191/25/20191/25/2019 PASS
DetailsKatelyn Menuge
BND19-00025 Landscape
Routing - Addressing1/25/2019 1/25/2019 PASS
DetailsDoug Chausow
Corrected address to: 3266 E Barber Valley Dr.
Print Occupancy Form  1/25/2019 DONE
CHANGE STATUS TO (ISS)  1/24/2019  
Print Occupancy Form  1/24/2019 DONE
OVERRIDE  12/6/2018  
Plan assigned to (CDM)11/26/201811/26/201812/6/2018 PASS
DetailsCarl D Madsen
Plan Mod - Adjustments to the mechanical ductwork to provide additional heat into the "doghouses" on the roof as a solution to a requestfrom Tim Frost (City of Boise Fire Sprinkler Inspector) to insure that the fire sprinkler pipes in the "doghouses" would notfreeze if/when the outside air temperature reaches -25 F.
Routing - PLAN CHECK11/27/2018 12/6/2018 PASS
DetailsCarl D Madsen
Permit Ready to Issue  12/6/2018 DONE
Plan Mod Approved
DO NOT REISSUE (fees due)
Routing - MECHANICAL11/27/2018 11/29/2018 PASS
DetailsTroy James
Routing - PLUMBING11/27/2018 11/27/2018 PASS
DetailsDaryl Spivey
Per plan and ISPC. See redline marks.
Routing - PUBLIC WORKS11/27/2018 11/27/2018 PASS
DetailsMorgan Webb
Plan Modification Accepted  11/26/2018 DONE
Adjustments to the mechanical ductwork to provide additional heat into the "doghouses" on the roof as a solution to a requestfrom Tim Frost (City of Boise Fire Sprinkler Inspector) to insure that the fire sprinkler pipes in the "doghouses" would notfreeze if/when the outside air temperature reaches -25 F.
BLD-Wall cover11/14/201811/15/201811/15/2018APART
DetailsBrandon Shaw
Need Engineer fix for two broken trusses at BLDG B main entry...
OK to isulate...
BLD-Energy code compliance10/5/201810/5/201810/5/2018PPART
DetailsBrandon Shaw
Air Seal inspection for area A.
CHANGE STATUS TO (ISS)  9/11/2018 DONE
(F) Reprint permit  9/11/2018 DONE
Print Occupancy Form  9/11/2018 DONE
OVERRIDE  9/6/2018  
Plan assigned to (CDM)8/22/20188/22/20189/6/2018 PASS
DetailsCarl D Madsen
Plan Mod - Adjustments to the mechanical ductwork in the kitchen to accommodate the space provided between the roof trusses and
ceiling.
Also the installation of an underground lift station on the outlet side of the grease interceptor, because of invert elevations
of sanitary sewer piping that were modified because of an electrical conduit bank running through the building.
Routing - PLAN CHECK8/27/2018 9/6/2018 PASS
DetailsCarl D Madsen
Routing PW Sewer Design8/27/2018 9/6/2018 PASS
DetailsDeAnn Brown
Plan Mod - Adjustments to the mechanical ductwork in the kitchen to accommodate the space provided between the roof trusses and
ceiling.
Also the installation of an underground lift station on the outlet side of the grease interceptor, because of invert elevations
of sanitary sewer piping that were modified because of an electrical conduit bank running through the building.
PLANS/APPL TAKEN TO FRONT DESK  9/6/2018 DONE
Permit Ready to Issue  9/6/2018 DONE
PLAN MOD (Do not change status to ISS without BLD18-00230 - all plan mod fees put on this permit)
BLD-Energy code compliance9/5/20189/5/20189/5/2018PPART
DetailsBrandon Shaw
Air seal BLDG- C to common area
Routing - MECHANICAL8/27/2018 9/4/2018 PASS
DetailsTroy James
BLD-Framing/Rough-in8/30/20188/30/20188/30/2018PPART
DetailsBrandon Shaw
Area C shower stall drywall and tape
Routing - PLUMBING8/27/2018 8/30/2018 PASS
DetailsBill VanDegrift
per plans and ISPC
BLD-Framing/Rough-in8/28/20188/29/20188/29/2018APART
DetailsBrandon Shaw
Corrections SAT...
Routing PW Environmental8/27/2018 8/29/2018 PASS
DetailsRick Christenson
Plan Mod - Adjustments to the mechanical ductwork in the kitchen to accommodate the space provided between the roof trusses and
ceiling.
Also the installation of an underground lift station on the outlet side of the grease interceptor, because of invert elevations
of sanitary sewer piping that were modified because of an electrical conduit bank running through the building.
Routing PW Flood Plain8/27/2018 8/28/2018 PASS
DetailsJason C. Taylor
Approved LOMR on File. No floodplain review required. If you have any questions, please call Jason Taylor at ###-####.
BLD-Framing/Rough-in8/27/20188/27/20188/27/2018PPART
DetailsBrandon Shaw
BLDG D- OK to cover exterior and one side of individual units
Routing - PUBLIC WORKS8/27/2018 8/27/2018 PASS
DetailsRachael Beierle
ROUTED TO PRETREATMENT FOR PLAN MOD
Plan Modification Accepted  8/22/2018 DONE
Plan Mod - Adjustments to the mechanical ductwork in the kitchen to accommodate the space provided between the roof trusses and
ceiling.
Also the installation of an underground lift station on the outlet side of the grease interceptor, because of invert elevations
of sanitary sewer piping that were modified because of an electrical conduit bank running through the building.
Expiration Notice5/1/20185/22/20185/1/2018 DONE
DetailsBrittany Hill
Issue PAID IN FULL permit  5/1/2018 DONE
Print Occupancy Form  5/1/2018 DONE
OVERRIDE  4/18/2018  
Plan assigned to (CDM)11/27/201711/27/20174/18/2018 PASS
DetailsCarl D Madsen
Veranda at Barber Station
Routing PW Street Lights11/27/2017 4/18/2018 PASS
DetailsTom Marshall
Routing - PLAN CHECK4/13/2018 4/18/2018 PASS
DetailsCarl D Madsen
Routing - PLANNING4/13/2018 4/18/2018 PASS
DetailsTodd Tucker
Routing Off Site - STRUCTURAL4/13/2018 4/18/2018 PASS
DetailsCarl D Madsen
PLANS/APPL TAKEN TO FRONT DESK  4/18/2018 DONE
Permit Ready to Issue  4/18/2018 DONE
NEED
ACHD
RP
GC FORM
BLD17-03587 NEEDS TO BE FINAL
Routing - Design Review4/13/2018 4/13/2018 PASS
DetailsKatelyn Menuge
Routing - PLAN CHECK3/14/2018 4/11/2018 FAIL
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL3/14/2018 4/11/2018 FAIL
DetailsCarl D Madsen
Route to Impact Fee Review12/29/20171/1/20183/23/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing PW Flood Plain3/21/2018 3/21/2018 PASS
DetailsJason C. Taylor
Approved LOMR on File. No floodplain review required. JCT
Routing - PLUMBING3/14/2018 3/19/2018 PASS
DetailsBill VanDegrift
1) additional cross connection protection may be required.
2) backflow protection required on water service.
Routing PW Flood Plain3/14/2018 3/14/2018 FAIL
DetailsJason C. Taylor
Need LOMR uploaded to case files. Jason Taylor ###-####
Routing - Design Review3/14/2018 3/14/2018 FAIL
DetailsKatelyn Menuge
Need landscape modifications to L1.0
Routing PW Drainage1/17/2018 1/17/2018 PASS
DetailsBrian Murphy
1st review completed  12/29/2017 FAIL
Routing Off Site - STRUCTURAL11/27/2017 12/29/2017 FAIL
DetailsCarl D Madsen
Routing - PLAN CHECK11/27/2017 12/29/2017 FAIL
DetailsCarl D Madsen
Routing - FIRE11/27/201711/27/201712/7/2017 PASS
DetailsScott Arellano
Attached comments to case
Routing PW Sewer Design12/7/2017 12/7/2017 PASS
DetailsMike Sheppard
Routing PW Environmental11/27/2017 12/5/2017 PASS
DetailsRick Christenson
Per 1500 Gallon Exterior Interceptor Installed.
Routing - PLUMBING11/27/2017 12/4/2017 FAIL
DetailsBill VanDegrift
change mark
1) provide secondary roof drainage system
red line
1) additional cross connection protection may be required
2) backflow protection required on the water service
Routing PW Drainage11/27/2017 11/30/2017 FAIL
DetailsBrian Murphy
need apdex j patio runoff anti crowned streets
Routing - MECHANICAL11/27/2017 11/29/2017 PASS
DetailsTroy James
Routing PW Flood Plain11/27/2017 11/28/2017 FAIL
DetailsJason C. Taylor
Need LOMR uploaded to case files. Jason Taylor ###-####
Routing - Design Review11/27/2017 11/28/2017 FAIL
DetailsKatelyn Menuge
Prior to sign-off, applicant must vacate and relocate any easement lines where structures are proposed, and complete ROS17-00088.
Routing - PLANNING11/27/2017 11/27/2017 PASS
DetailsDavid Moser
Current Planning Review is not required and the development was reviewed under DRH17-00358 and DRH17-00525
Routing - Addressing11/27/2017 11/27/2017 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS11/27/2017 11/27/2017 PASS
DetailsRachael Beierle
PERMIT UNDER SWR17-01374
Routing - Erosion and Sediment11/27/2017 11/27/2017 PASS
DetailsMichael Zawacki
RP needed. Dewatering plan may be needed, area is know for shallow water table, no dewatering allowed without approved plan.
Site walk through required prior to ground disturbing activities.
Routing PW Solid Waste11/27/2017 11/27/2017 PASS
DetailsEvan Carpenter
Intake Approval  11/27/2017 PASS
Intake Approval  11/15/2017 FAIL
DetailsJulie Romig
1. Architectural Stamp/Signature on the specification manual cover.
2. Provide either a completed CDHD application or stamped CDHD approved plan.
3. Lighting COMcheck - separate file not found.
4. Reduce size of all drawing sheets over 1 MB and re-upload with same file name. Files larger than 1 MB are very slow to open and read, delaying review times.
Application received  11/13/2017 DONE
Application submitted via PDS Online on Nov 13 2017 2:14PM
Temporary Occupancy2/27/20195/28/2019