BLD-Final | 6/29/2020 | 6/29/2020 | 6/29/2020 | P | FAIL |
Brandon Shaw
|
|
|
Per R312.2 Fall protection... 4 loactions R308.4.2 safety glazing required, office door and window adjacent...
|
PubWorks Occupancy Approval | 6/18/2020 | 6/18/2020 | 6/18/2020 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department Jason Taylor ###-####.
|
BLD-Final | 5/28/2020 | 5/28/2020 | 5/28/2020 | P | NR |
Brandon Shaw
|
|
|
Need PW approval...
|
BLD-Other | 2/4/2020 | 2/5/2020 | 2/5/2020 | A | PASS |
Dave Hannah
|
|
|
cameron- inspection for footer for landscaping Phone #: ###-####
|
PubWorks Subgrade Approval | 2/5/2020 | 2/5/2020 | 2/5/2020 | | DONE |
Melissa Jannusch
|
|
|
Retaining wall footing for retaining wall on North side of residence.
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
CHANGE STATUS TO (ISS) | | | 1/31/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 1/24/2020 | | |
|
|
|
|
Plan assigned to (M_H) | 12/19/2019 | | 1/24/2020 | | DONE |
Michael Hanson
|
|
|
12/26 Plan mod - Residential - pending applicant document upload
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/24/2020 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 1/24/2020 | | DONE |
|
|
|
DO NOT ISSUE- plan mod
|
Routing - PLAN CHECK | 1/9/2020 | | 1/15/2020 | | PASS |
Michael Hanson
|
|
|
|
Routing - PLANNING | 1/9/2020 | | 1/15/2020 | | PASS |
Karla Nelson
|
|
|
This modification includes new retaining walls and an addition of a patio that were approved per CFH19-00090.
|
Routing - PUBLIC WORKS | 1/9/2020 | | 1/9/2020 | | PASS |
Candy A. Nichols
|
|
|
PLAN MOD
|
Meeting | | | 1/7/2020 | | DONE |
|
|
|
plan mod prescreen failed
Upload new CFH approval letter for plan modification. Upload rock face stability letter from MTI and any other new documents. Remove grading plan from October. CAT II approved. Melissa Jannusch ###-####
|
Telephone call | | | 12/20/2019 | | DONE |
|
|
|
Called Cameron to let him know I can't start a new plan mod in ePlan until they complete the one they started in October. I also instructed him that if he wants permissions to ePlan, to have the architect email us to add him to ePlan.
|
Plan Modification Accepted | | | 12/19/2019 | | DONE |
|
|
|
Cameron Brown requested a plan mod workflow started for a new site plan.
|
Plan Modification Accepted | | | 10/8/2019 | | DONE |
|
|
|
Plan mod workflow started for retaining wall and grading
|
BLD-Energy code compliance | 7/11/2019 | 7/12/2019 | 7/12/2019 | A | PASS |
Dave Hannah
|
|
|
Cameron Phone #: ###-####
|
BLD-Other | 7/9/2019 | 7/9/2019 | 7/9/2019 | P | CANC |
Brandon Shaw
|
|
|
cover with shingles on roof // Cameron Phone #: ###-####
|
BLD-Energy code compliance | 7/9/2019 | 7/9/2019 | 7/9/2019 | P | CANC |
Brandon Shaw
|
|
|
Cameron Phone #: ###-####
|
BLD-Framing/Rough-in | 7/9/2019 | 7/9/2019 | 7/9/2019 | P | PASS |
Brandon Shaw
|
|
|
OK to insulate...
|
Routing - MECHANICAL | 6/21/2019 | | 6/21/2019 | | PASS |
Troy James
|
|
|
New manual j report.
|
BLD-Wall Bracing | 5/16/2019 | 5/17/2019 | 5/17/2019 | A | PASS |
Dave Hannah
|
|
|
Inspection for Shear on exterior prior to installing Tyvek Phone #: ###-#### Inspection requested via web by Cameron Brown
|
BLD-Foundation | 3/21/2019 | 3/21/2019 | 3/21/2019 | P | PASS |
Brandon Shaw
|
|
|
Window wells, and Main enrty stair walls...
|
BLD-Foundation | 2/24/2019 | 2/25/2019 | 2/25/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 2/19/2019 | 2/20/2019 | 2/20/2019 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Cameron Brown
|
PubWorks Subgrade Approval | 2/19/2019 | 2/19/2019 | 2/19/2019 | | DONE |
Melissa Jannusch
|
|
|
Garage, continuous footings, southern half of west perimeter and south perimeter.
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Foundation | 2/11/2019 | 2/12/2019 | 2/12/2019 | A | PART |
Dave Hannah
|
|
|
Also need to inspect ufer for electrical we have a noon poor would like a inspection early morning Phone #: ###-#### Inspection requested via web by Cameron Brown part about 50 ft back wall and north wall ok
|
BLD-Footing | 1/31/2019 | 1/31/2019 | 2/1/2019 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Cameron Brown
|
BLD-Footing | 1/23/2019 | 1/24/2019 | 1/24/2019 | A | PASS |
Jim Storey
|
|
|
Please call me at your convenience in the morning I would appreciate it thank you very much Phone #: ###-#### Inspection requested via web by Cameron Brown
|
BLD-Foundation | 1/22/2019 | 1/23/2019 | 1/23/2019 | A | NR |
Mike Jordan
|
|
|
Cameron Phone #: ###-####. Needs public works subgrade approval first.
|
PubWorks Subgrade Approval | 1/23/2019 | 1/23/2019 | 1/23/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 11/5/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/5/2018 | | DONE |
|
|
|
|
Telephone call | | | 11/1/2018 | | DONE |
|
|
|
Spoke with Ian about permit expiring and possibly sending in a request for an extension
|
OVERRIDE | | | 10/31/2018 | | |
|
|
|
|
Plan assigned to (M_H) | 10/24/2018 | | 10/31/2018 | | DONE |
Michael Hanson
|
|
|
05/09 #404 L2 ePlan - 1st review completed - Pending PW Hillside approval. 10/24 MDH
|
Permit Ready to Issue | | | 10/31/2018 | | DONE |
|
|
|
NEED
GC- met
|
Routing PW Grading-Hillside | 10/24/2018 | | 10/31/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call ###-#### to schedule an inspection.
All disturbed slopes included in the construction of this project must be stabilized and approved by Public Works before a Final Occupancy Permit is granted. If weather conditions prohibit revegetation and stabilization activities, the contractor shall provide a bond/surety agreement or an irrevocable letter of credit in the amount of 110% of the cost estimated by the project engineer to enable stabilization of the site. Call ###-#### for an inspection.
|
Plan assigned to (RDP) | 4/20/2018 | 4/20/2018 | 10/24/2018 | | DEFR |
Rob Patrick
|
|
|
05/09 sfd L2 ePlan...5/9 Failed: Corrections Req'd...5/17 Failed: Corrections Still Required. 8/15 Failed; re-submittals have been uploaded.
|
Routing - PLANNING | 10/24/2018 | | 10/24/2018 | | PASS |
Nicolette Womack
|
|
|
Retaining Wall and Railings within the front 20' setback shall not exceed 3' in combined height from finished grade.
|
Routing - PLAN CHECK | 10/23/2018 | | 10/24/2018 | | PASS |
Michael Hanson
|
|
|
|
Routing - PUBLIC WORKS | 10/23/2018 | | 10/24/2018 | | PASS |
Morgan Webb
|
|
|
|
Extend Review Timeline | | | 10/22/2018 | | DONE |
|
|
|
1st Approved 180 day extension per Adele. See documents
|
Routing - PLAN CHECK | 8/15/2018 | | 8/15/2018 | | FAIL |
Rob Patrick
|
|
|
No re-submittals have been uploaded.
|
Routing PW Grading-Hillside | 6/15/2018 | | 6/15/2018 | | FAIL |
Melissa Jannusch
|
|
|
Changemarks not resolved. Have requested meeting with applicant to go over revision requests.
|
Routing PW Grading-Hillside | 5/30/2018 | | 6/7/2018 | | FAIL |
Melissa Jannusch
|
|
|
See changemarks from 5-24-18 -MMJ
|
Routing PW Grading-Hillside | 5/24/2018 | | 5/24/2018 | | FAIL |
Melissa Jannusch
|
|
|
See changemarks. Need geotech report (requested on 4-30-18 review). Need CFH conditions/revisions to be addressed (requested in CFH letter on 3-2-18)
|
Routing - PLANNING | 4/20/2018 | | 5/21/2018 | | FAIL |
Sue Cummings
|
|
|
Retaining Walls in the Side Setback shall not exceed 6' in exposed height. Incorrect Grading Plan submitted.
Sue C for Nicolette
|
Routing - PLANNING | 5/21/2018 | | 5/21/2018 | | PASS |
Nicolette Womack
|
|
|
Driveways shall not exceed 33' in width within the front yard setback.
|
Routing - PLAN CHECK | 5/18/2018 | | 5/18/2018 | | FAIL |
Rob Patrick
|
|
|
Failed: Corrections Still Required
|
1st review completed | | | 5/9/2018 | | FAIL |
Rob Patrick
|
|
|
Multiple Corrections req'd.
|
Routing - PLAN CHECK | 4/20/2018 | | 5/9/2018 | | FAIL |
Rob Patrick
|
|
|
Multiple Corrections Req'd.
|
Route to Impact Fee Review | 4/20/2018 | 4/23/2018 | 4/30/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing PW Grading-Hillside | 4/23/2018 | | 4/30/2018 | | FAIL |
Melissa Jannusch
|
|
|
See changemarks in ePlan
|
Routing - FIRE | 4/20/2018 | 4/20/2018 | 4/25/2018 | | PASS |
Tim Frost
|
|
|
5/03 house eplan
|
Routing - Erosion and Sediment | 4/20/2018 | | 4/25/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Certified RP designated. Site preparation inspection is required.
|
Routing - MECHANICAL | 4/20/2018 | | 4/24/2018 | | PASS |
Troy James
|
|
|
Plans were submitted without manual j report. Called applicant and he asked for the mechanical to be deferred. Had to comply since the plans have already been submitted. No review at this time.
|
Routing - Addressing | 4/20/2018 | | 4/23/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 4/20/2018 | | 4/23/2018 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/20/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/20/2018 | | DONE |
|
|
|
|
Intake Approval | | | 4/20/2018 | | PASS |
|
|
|
|
Intake Approval | | | 4/4/2018 | | FAIL |
|
|
|
Appeal period does not end until 5pm on 4/13/18
|
Intake Approval | | | 11/29/2017 | | FAIL |
|
|
|
Geotechnical report needs to be stamped.
114 P&Z Application needs to be approved and approval letter uploaded before building application can start review.
|
Intake Approval | | | 11/20/2017 | | FAIL |
|
|
|
Must go throught PW first, need to separate and individually name, Manual J, Anchor bolts, attic/crawl space locations, electrical plans are too light to read, sqft on app was marked incorrectly and soil & geotech report.
|
Application received | | | 11/17/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 17 2017 5:01PM
|
Routing PW Grading-Hillside | 1/9/2020 | | | | PASS |
Melissa Jannusch
|
|
|
PLAN MOD Approved. A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|