CHANGE STATUS TO (ISS) | | | 1/22/2020 | | DONE |
|
|
|
|
Telephone call | | | 1/22/2020 | | DONE |
|
|
|
Called and left a message for JH to let them know the approved plan mod plans are here for them to pick up and they will need them for the final inspection.
|
OVERRIDE | | | 8/13/2019 | | |
|
|
|
|
Plan assigned to (BJM) | 8/5/2019 | 8/5/2019 | 8/13/2019 | | DONE |
Brian McGowan
|
|
|
grading plans to Melissa
|
Routing - PLAN CHECK | 8/5/2019 | | 8/13/2019 | | PASS |
Brian McGowan
|
|
|
Foundation, TW elevations stayed the same.
|
Routing - PUBLIC WORKS | 8/6/2019 | | 8/13/2019 | | PASS |
Morgan Webb
|
|
|
Modified Grading Plan
|
Telephone call | | | 8/13/2019 | | DONE |
|
|
|
Spoke with Eric to inform him the permit plan mod is ready and what fee is due.
|
Case Summary (BLD) | | | 8/13/2019 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 8/13/2019 | | DONE |
|
|
|
Plan Mod Approved DO NOT REISSUE
|
BLD-Conference | 8/8/2019 | 8/9/2019 | 8/9/2019 | A | DONE |
Brandon Shaw
|
|
|
Eric Phone #: ###-####
|
Routing PW Grading-Hillside | 8/7/2019 | | 8/7/2019 | | PASS |
Melissa Jannusch
|
|
|
PLAN MOD for updates to grading and drainage is approved.
|
Plan Reviewer's activity | | | 8/6/2019 | | |
Brian McGowan
|
|
|
Took resubmitted Grading Plan and original submitted Plans to Morgan for routing.
|
Plan Modification Accepted | | | 8/5/2019 | | DONE |
|
|
|
per Eric Allen from JH Development: for grading for Melissa.(gf)
Three copies of plan sheet 1.0 taken to Brian (blh)
|
BLD-Conference | 8/1/2019 | 8/1/2019 | 8/1/2019 | P | DONE |
Brandon Shaw
|
|
|
Pre-final walk thru...
|
BLD-Conference | 6/20/2019 | 6/20/2019 | 6/20/2019 | A | DEFR |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Aging Inspection | 6/20/2019 | 6/20/2019 | 6/20/2019 | | CANC |
Brandon Shaw
|
|
|
|
BLD-Aging Inspection | 6/19/2019 | 6/19/2019 | 6/19/2019 | | CANC |
Brandon Shaw
|
|
|
|
BLD-Energy code compliance | 2/4/2019 | 2/5/2019 | 2/5/2019 | A | PASS |
Brandon Shaw
|
|
|
Eric Phone #: ###-####
|
BLD-Framing/Rough-in | 1/3/2019 | 1/3/2019 | 1/3/2019 | P | PEND |
Brandon Shaw
|
|
|
OK to insulate pending..."cpvc piping compatibility with the insulation spray foam needs to be verified prior to cover on any of the vertical sprinkler lines." As per Troy Cobbley...
|
BLD-Foundation | 11/15/2018 | 11/15/2018 | 11/15/2018 | P | CANC |
Brandon Shaw
|
|
|
Inspection requested via web by Ben Sears.Pool permit is BLD18-03830
|
BLD-Footing | 11/8/2018 | 11/9/2018 | 11/9/2018 | P | CANC |
Brandon Shaw
|
|
|
Retaining wall
|
BLD-Footing | 11/8/2018 | 11/8/2018 | 11/8/2018 | A | NR |
Brandon Shaw
|
|
|
Need soil sub-grade submitted and approved by PW...
|
BLD-Wall Bracing | 10/22/2018 | 10/22/2018 | 10/22/2018 | P | PART |
Dave Hannah
|
|
|
call 1 hr before to meet (will be in nampa) // mike Phone #: ###-#### needs to install 6 hold downs retro 3 ok to rap house
|
Plan Modification Accepted | | | 10/18/2018 | | DONE |
|
|
|
New manual j report
|
Routing - MECHANICAL | 10/18/2018 | | 10/18/2018 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
BLD-Foundation | 6/21/2018 | 6/22/2018 | 6/22/2018 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Ben Sears Work in progress.....appears OK.
|
BLD-Foundation | 6/20/2018 | 6/21/2018 | 6/21/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Foundation | 6/20/2018 | 6/20/2018 | 6/20/2018 | P | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Ben Sears Inspection cancelled from web by: Ben Sears
|
BLD-Footing | 6/13/2018 | 6/14/2018 | 6/14/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress Last footing pour for this permit
|
BLD-Foundation | 6/1/2018 | 6/1/2018 | 6/1/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 5/17/2018 | 5/18/2018 | 5/18/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress- rain/standing water
|
BLD-Footing | 5/16/2018 | 5/17/2018 | 5/17/2018 | A | NR |
Brandon Shaw
|
|
|
Dewater and clear sediment/mud as needed
|
PubWorks Subgrade Approval | 5/10/2018 | 5/10/2018 | 5/10/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 5/8/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 5/7/2018 | | |
|
|
|
|
Inspection Record Card- Bld | | | 5/7/2018 | | DONE |
|
|
|
|
Telephone call | | | 5/7/2018 | | DONE |
|
|
|
Spoke with Eric informing him this permit is ready and the fee amount due for issuance
|
Permit Ready to Issue | | | 5/7/2018 | | DONE |
|
|
|
MET-ESC18-00109 is for the grading permit as well and has already been issued
|
Plan assigned to (BJM) | | 3/22/2018 | 5/4/2018 | | DONE |
Brian McGowan
|
|
|
1st review done- failed-need Mechanical to sign off 4-10 sfd L2 paper
|
Routing - PLAN CHECK | 5/4/2018 | | 5/4/2018 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 5/4/2018 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/4/2018 | | DONE |
Brian McGowan
|
|
|
|
Plan resubmittals received | | | 4/30/2018 | | DONE |
|
|
|
one copy of Foundation plan with grades, stamped and taken to BJM
|
Routing - PLAN CHECK | 4/24/2018 | | 4/27/2018 | | FAIL |
Brian McGowan
|
|
|
Top of foundation and footings note noted at foundation steps
|
Plan resubmittals received | | | 4/24/2018 | | DONE |
|
|
|
Two copies of engineering, two copies of sheets 1 of 12, 2 of 12, unmarked sheet, 5 of 12, 8 of 12 wui products.Taken to Brian Mc
|
Routing - MECHANICAL | | | 4/12/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLAN CHECK | 4/12/2018 | | 4/9/2018 | | FAIL |
Brian McGowan
|
|
|
|
1st review completed | | | 4/9/2018 | | FAIL |
Brian McGowan
|
|
|
Foundation plan and engineering calculations
|
Routing - FIRE | 3/29/2018 | 3/22/2018 | 4/3/2018 | | PASS |
Erika Akin
|
|
|
Plans were reviewed for FD access, availability of hydrants and defensible space. Fire sprinklers were required by Assitant Fire Marshal under CFH17-00071.
|
Routing - Erosion and Sediment | 3/29/2018 | | 3/29/2018 | | PASS |
Andy J. Long
|
|
|
ESC18-00109/GRD18-00005
|
Routing - PLANNING | 3/28/2018 | | 3/29/2018 | | PASS |
David Moser
|
|
|
CFH17-00071; Copy of recorded cross access easment for driveway was provided on 3-29-18
|
Routing - PUBLIC WORKS | | | 3/28/2018 | | PASS |
|
|
|
|
Routing PW Grading-Hillside | 3/22/2018 | | 3/28/2018 | | PASS |
Melissa Jannusch
|
|
|
ESC18-00109/GRD18-00005
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
|
Routing - PUBLIC WORKS | 3/28/2018 | | 3/28/2018 | | PASS |
Rachael Beierle
|
|
|
|
Route to Impact Fee Review | 3/22/2018 | 3/25/2018 | 3/23/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 3/22/2018 | | 3/22/2018 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/22/2018 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 3/22/2018 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/22/2018 | | DONE |
Christina Prado
|
|
|
|
Application received | | 3/22/2018 | | | |
|
|
|
|