Permit Information
Permit NumberBLD18-01760
StatusFinaled
Name RRC CONTRACTORS
Site Address 999 W MAIN ST
Project NameJacobs - 10th & 12th Floor
Customer NumberBLD18-01055 VANILLA
ePlanReviewYes
Description
(JACOBS – 10th and 12th FLOOR) //Plan modification for fire wall locations and removal of room #105 repro room from scope of work on the 10th floor. 11-27-2018 JG// Permit is to remodel the 10th and 12th floor within the existing building (approximately 9,304 sq. ft. on the 10th floor and 17,572 sq. ft. on the 12th floor, tenant to occupy part of the 10th floor and all of the 12th floor) Note: the demo work was done under BLD18-01055. Approval is contingent upon adhering to the approved plans on file and plan review report. Work to include: on the construction of interior non-bearing walls creating tenant demising walls, offices, break rooms, storage room, equipment room, phone rooms, conference rooms, closets, wellness room, privacy rooms, lan room, work rooms, reception areas, server room and open office areas, new door/door frames, millwork, interior windows, suspended acoustic and gypsum ceilings/soffits, new light fixtures, electrical work, plumbing work, mechanical work and interior finishes in compliance with Ch. 8 of the current IBC. Note: corridor is to be 1-hour rated with 20 min. rated doors, the intervening restroom and small electric/telephone/closet rooms shall have the rated wall wrap around them. This building is fully Fire Sprinklered. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 4/16/20194/12/2019 DONE
This permit finaled on the web by derek cooper
Second Notice 3/17/20194/11/2019 DONE
mailed 4-12-19
First Notice 2/14/20193/7/2019 DONE
mailed 3-11
BLD-Final2/1/20192/4/20192/4/2019APASS
DetailsDave Hannah
Please call prior to arrival for access to building floors-Thank You. Phone #: ###-#### Inspection requested via web by Ron Oswald
Permanent Occupancy  2/4/2019 DONE
BLD-Final1/31/20192/1/20192/1/2019ANR
DetailsMike Jordan
Ron Phone #: ###-####
CHANGE STATUS TO (ISS)  1/31/2019 DONE
Plan mod
OVERRIDE  12/7/2018  
Plan assigned to (JG)11/13/201811/13/201812/7/2018 PASS
DetailsJavier Guzman
1st rev comp, Plan Mod Jacobs - 10th & 12th Floor
Routing - PLAN CHECK12/5/2018 12/7/2018 PASS
DetailsJavier Guzman
Permit Ready to Issue  12/7/2018 DONE
Plan Mod Approved
DO NOT REISSUE (fees due)
Routing - PLAN CHECK11/21/2018 11/28/2018 FAIL
DetailsJavier Guzman
Plan Reviewer's activity  11/16/2018 DONE
DetailsJavier Guzman
failed plan mod prescreen for the following
Provide and upload the following:
1. Revised plan sheets need to stamped, signed and dated by the Idaho licensed architect
2. Lobby opposite swing doors required at doors 200A, 200B, 100A and 100B
3. Provide keynote to what are the new walls or lines shown at MFP room 102 going towards room 103, at breakroom 101 and also across doors 101B, 118A through 123A
Plan Modification Accepted  11/13/2018 DONE
Modified fire wall location (a1.1 and a1.2)
BLD-Final10/29/201810/29/201810/29/2018PPART
DetailsDave Hannah
zack Phone #: ###-#### ok for tco
FIRE-Final Inspection10/29/201810/29/201810/29/2018PPASS
DetailsJim Page
Final life fire safety inspection for area of work complete.

Derek Phone #: ###-####
FIRE-Final Inspection10/26/201810/29/201810/29/2018ACANC
DetailsJim Page
zack Phone #: ###-####
BLD-Final10/26/201810/29/201810/29/2018ANR
DetailsDave Hannah
zack Phone #: ###-####
Temporary Occupancy10/29/20181/27/201910/29/2018 DONE
DetailsCandy A. Nichols
BLD-Final10/26/201810/26/201810/26/2018PNR
DetailsDave Hannah
Dereck-wants temp c of o Phone #: ###-####
FIRE-Final Inspection10/26/201810/26/201810/26/2018APART
DetailsJim Page
Partial final inspection for life fire safety inspection complete. TCO authorized for life safety pending fire alarm completion associated with project. Permit for life fire safety can be finaled when remaining noted items on fire alarm are complete.

Dereck-wants temp c of o Phone #: ###-####wants temp c of o
FIRE-Conference10/25/201810/26/201810/26/2018ADONE
DetailsJim Page
Fire conference complete

Zack Phone #: ###-####
BLD-Ceiling Grid Inspection10/23/201810/23/201810/24/2018ADONE
DetailsDave Hannah
Derek Phone #: ###-####
BLD-Ceiling Grid Inspection10/24/201810/24/201810/24/2018APASS
DetailsDave Hannah
Derek Phone #: ###-####
BLD-Ceiling Grid Inspection10/22/201810/23/201810/23/2018ANR
DetailsMike Jordan
Please call Derek or Zach 30 Minutes prior to arriving.

Thank You, Phone #: ###-#### Inspection requested via web by Ron Oswald. No call back and no access to jobsite. Will need to reschedule.
BLD-Framing/Rough-in10/9/201810/9/201810/9/2018PPASS
DetailsDave Hannah
This inspection is for hard lid soffits on floor 10. Please call upon arrival and I will get you up to the floor. Thank You. Phone #: ###-#### Inspection requested via web by Ron Oswald
BLD-Ceiling Grid Inspection10/2/201810/3/201810/3/2018APART
DetailsBrandon Shaw
12th floor phase 1...
BLD-Framing/Rough-in9/18/20189/19/20189/19/2018APART
DetailsDave Hannah
Zack Phone #: ###-#### hard lids soffits ok to cover
BLD-Framing/Rough-in8/16/20188/16/20188/16/2018PPASS
DetailsDave Hannah
Rough framing on 10th floor minus plumbing wall at South west area. Please call upon arrival and I can bring you to the floor I will be back onsite at 1:00 pm today.

Thank You. Phone #: ###-#### Inspection requested via web by Ron Oswald
BLD-Framing/Rough-in8/6/20188/7/20188/7/2018APASS
DetailsDave Hannah
Please call upon arrival for access for 12th floor framing inspection. Thank You. Phone #: ###-#### Inspection requested via web by Ron Oswald
Permit Ready to Issue  7/23/2018 DONE
Need - MET
GC
Revised Cert of Value
Issue PAID IN FULL permit  7/23/2018 DONE
Print Occupancy Form  7/23/2018 DONE
Plan assigned to (JG)5/24/20185/24/20187/21/2018 PASS
DetailsJavier Guzman
1st rev comp, 6/06 L2 Jacobs ePlan
Routing - PLAN CHECK7/19/2018 7/21/2018 PASS
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  7/21/2018 DONE
Routing - PLAN CHECK6/29/2018 7/3/2018 FAIL
DetailsJavier Guzman
Routing - PUBLIC WORKS6/29/2018 6/29/2018 PASS
DetailsMorgan Webb
Route to Impact Fee Review6/13/20186/16/20186/14/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - PLAN CHECK5/24/2018 6/13/2018 FAIL
DetailsJavier Guzman
1st review completed  6/13/2018 FAIL
DetailsJavier Guzman
Routing - MECHANICAL5/24/2018 6/4/2018 PASS
DetailsTroy James
No mechanical work being done per architect.
Routing - Addressing5/24/2018 5/24/2018 PASS
DetailsDoug Chausow
Floors 10 and 12
Routing - PUBLIC WORKS5/24/2018 5/24/2018 FAIL
DetailsMorgan Webb
NEED PLUMBING PLANS SHOWING DEMOED AND NEW PLUMBING FIXTURES.
Intake Approval  5/24/2018 PASS
DetailsJavier Guzman
Intake Approval  5/21/2018 FAIL
DetailsBrian McGowan
No wall schedule and details were provided.
Floor plans do not note or designate new, to be removed or existing walls.
No Mechanical plans were provided.
Please provide the above mentioned.
Application received  5/17/2018 DONE
Application submitted via PDS Online on May 17 2018 5:03PM