Print Statement | | | 4/19/2019 | | DONE |
|
|
|
sent 1st late notice
|
Print Statement | | | 1/15/2019 | | DONE |
|
|
|
|
First Notice | | 12/23/2018 | 1/8/2019 | | DONE |
|
|
|
mailed 1-11-19
|
Permanent Occupancy | | | 12/13/2018 | | DONE |
|
|
|
|
BLD-Final | 12/10/2018 | 12/11/2018 | 12/11/2018 | P | PASS |
Mike Jordan
|
|
|
Tim Phone #: ###-####. ok for perm occ.
|
FIRE-Final Inspection | 12/10/2018 | 12/11/2018 | 12/11/2018 | A | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags. Final life fire safety inspection for area of work complete.
Tim Phone #: ###-####
|
BLD-Final | 12/6/2018 | 12/7/2018 | 12/7/2018 | P | NR |
Jim Storey
|
|
|
Tim Phone #: ###-####
|
FIRE-Final Inspection | 12/6/2018 | 12/7/2018 | 12/7/2018 | A | FAIL |
Troy Cobbley
|
|
|
Relocate the fire extinguisher as discussed, repair the exit sign and provide inspection/final for the fan shutdown.
Tim Phone #: ###-####
|
FIRE-Final Inspection | 12/7/2018 | 12/7/2018 | 12/7/2018 | P | CANC |
Jim Page
|
|
|
Tim Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 11/20/2018 | 11/21/2018 | 11/21/2018 | A | PASS |
Jim Storey
|
|
|
Tim Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 10/31/2018 | 11/1/2018 | 11/1/2018 | A | PASS |
Jim Storey
|
|
|
Tim Phone #: ###-####
|
BLD-Framing/Rough-in | 10/16/2018 | 10/16/2018 | 10/16/2018 | P | PASS |
Jim Storey
|
|
|
Tim Phone #: ###-####
|
BLD-Framing/Rough-in | 10/5/2018 | 10/8/2018 | 10/8/2018 | P | PASS |
Jim Storey
|
|
|
dave Phone #: ###-#### meet with engineer of record// ok to cover/ ceilling
|
Permit Ready to Issue | | | 9/20/2018 | | DONE |
|
|
|
met
|
Issue PAID IN FULL permit | | | 9/20/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/20/2018 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 8/9/2018 | 8/9/2018 | 9/19/2018 | | PASS |
Carl Westfall
|
|
|
(1st done) 08/27/18 (L3 - 15 days) (ePlan - 31 sheet) D-Bat
|
Plan resubmittals received | | | 9/19/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/19/2018 | | 9/19/2018 | | PASS |
Carl Westfall
|
|
|
2nd plan review approved
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/19/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 9/14/2018 | 9/17/2018 | 9/17/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 8/9/2018 | | 9/14/2018 | | FAIL |
Carl Westfall
|
|
|
|
1st review completed | | | 9/14/2018 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 9/14/2018 | | DONE |
|
|
|
|
Routing - FIRE | 8/9/2018 | 8/9/2018 | 9/5/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - MECHANICAL | 8/20/2018 | | 8/20/2018 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 8/9/2018 | | 8/13/2018 | | FAIL |
Troy James
|
|
|
Left voicemail to mechanical engineer to call
|
Routing - PLUMBING | 8/9/2018 | | 8/10/2018 | | PASS |
Bill VanDegrift
|
|
|
See redline marks and install per ISPC.
|
Routing - Addressing | 8/9/2018 | | 8/10/2018 | | PASS |
Doug Chausow
|
|
|
Suite 140
|
Routing - PUBLIC WORKS | 8/9/2018 | | 8/10/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLANNING | 8/9/2018 | | 8/9/2018 | | PASS |
Brent Moore
|
|
|
|
Intake Approval | | | 8/7/2018 | | PASS |
|
|
|
|
Application received | | | 8/1/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 1 2018 10:45AM
|