Print Statement | | | 7/23/2019 | | DONE |
|
|
|
|
Third Notice | | 6/12/2019 | 7/10/2019 | | DONE |
|
|
|
mailed 7-11 with first follow up
|
First Follow up | | | 7/10/2019 | | DONE |
|
|
|
|
First Follow up | | | 7/10/2019 | | DONE |
|
|
|
|
Third Notice | | 5/11/2019 | 6/7/2019 | | DONE |
|
|
|
mailed 6-10
|
Third Notice | | 4/13/2019 | 5/6/2019 | | DONE |
|
|
|
mailed 5-10-19
|
Second Notice | | 3/21/2019 | 4/8/2019 | | DONE |
|
|
|
mailed 4-11-19
|
First Notice | | 3/2/2019 | 3/11/2019 | | DONE |
|
|
|
mailed 3-12-19
|
BLD-Final | 2/19/2019 | 2/20/2019 | 2/20/2019 | A | PASS |
Mike Jordan
|
|
|
Tony- please call 45 min ahead for access Phone #: ###-####. OK for perm occ.
|
Permanent Occupancy | | | 2/20/2019 | | DONE |
|
|
|
|
BLD-Final | 2/15/2019 | 2/15/2019 | 2/15/2019 | P | NR |
Jim Sly
|
|
|
Tony Phone #: ###-#### Need fire final.....
|
FIRE-Final Inspection | 2/15/2019 | 2/15/2019 | 2/15/2019 | P | DONE |
Jim Page
|
|
|
Life fire safety inspection passed per Troy's notes on 05FEB2019.
Tony Phone #: ###-####
|
BLD-Conference | 2/12/2019 | 2/12/2019 | 2/12/2019 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Final | 2/11/2019 | 2/12/2019 | 2/12/2019 | A | CANC |
Mike Jordan
|
|
|
Please call 45 minutes before arrival. Thank you Phone #: ###-#### Inspection requested via web by Tony Dondero. Moved to pm.
|
FIRE-Final Inspection | 2/11/2019 | 2/12/2019 | 2/12/2019 | A | CANC |
Troy Cobbley
|
|
|
Please call 45 minutes before arrival. Thank you Phone #: ###-#### >> Inspection requested via web by Tony Dondero Inspection cancelled from web by: Tony Dondero
|
Print Occupancy Form | | | 2/11/2019 | | DONE |
|
|
|
|
BLD-Final | 2/6/2019 | 2/7/2019 | 2/8/2019 | P | CANC |
Mike Jordan
|
|
|
Tony Phone #: ###-####
|
FIRE-Final Inspection | 2/6/2019 | 2/7/2019 | 2/7/2019 | A | CANC |
Troy Cobbley
|
|
|
Tony Phone #: ###-####
|
Case Summary (BLD) | | | 2/7/2019 | | DONE |
|
|
|
|
Temporary Occupancy | 2/6/2019 | 5/7/2019 | 2/6/2019 | | DONE |
Candy A. Nichols
|
|
|
|
BLD-Conference | 2/5/2019 | 2/5/2019 | 2/5/2019 | P | CANC |
Mike Jordan
|
|
|
Tony Phone #: ###-####
|
BLD-Final | 2/5/2019 | 2/5/2019 | 2/5/2019 | P | PASS |
Mike Jordan
|
|
|
Tony Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 2/4/2019 | 2/5/2019 | 2/5/2019 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
Tony Phone #: ###-####
|
FIRE-Final Inspection | 2/4/2019 | 2/4/2019 | 2/4/2019 | P | FAIL |
Troy Cobbley
|
|
|
Need the project related fire alarm permit finaled, need door hardware installed, need fire extinguishers. Exit lights/emergency lights did function.
Tony Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 1/23/2019 | 1/23/2019 | 1/23/2019 | A | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 12/24/2018 | 12/26/2018 | 12/26/2018 | A | PASS |
Dave Hannah
|
|
|
Please call 45 minutes before arrival. Thank you Tony Donddero Phone #: ###-#### Inspection requested via web by Tony Dondero
|
Issue PAID IN FULL permit | | | 12/12/2018 | | DONE |
|
|
|
emailed jnorton@jwci.com to sign buolding permit and send back
|
Print Occupancy Form | | | 12/12/2018 | | DONE |
|
|
|
emailed jnorton@jwci.com permits to sign and send back
|
Plan assigned to (JG) | 11/30/2018 | 11/30/2018 | 12/11/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 12/05 L1 Tikker Engineering ePlan
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/11/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/11/2018 | | DONE |
|
|
|
DO NOT ISSUE WITHOUT BLD18-04376
MET
Need
Revised Cert of Value
GC FORM
|
Routing - PLAN CHECK | 12/5/2018 | | 12/6/2018 | | PASS |
Javier Guzman
|
|
|
|
Route to Impact Fee Review | 12/4/2018 | 12/7/2018 | 12/5/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 12/4/2018 | | DONE |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 11/30/2018 | | 12/4/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLUMBING | 11/30/2018 | | 12/4/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - PUBLIC WORKS | 11/30/2018 | | 12/3/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - MECHANICAL | 11/30/2018 | | 12/3/2018 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 11/30/2018 | | 11/30/2018 | | PASS |
Doug Chausow
|
|
|
See BLD18-01807
|
Intake Approval | | | 11/29/2018 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 11/26/2018 | | FAIL |
Michael Hanson
|
|
|
Provide planning and zoning approval letter for exterior modifications.
|
Application received | | | 11/21/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 21 2018 10:47AM
|