Third Notice | | 1/4/2020 | 2/5/2020 | | DONE |
|
|
|
This permit finaled on the web by Charlene Meadows
|
Second Notice | | 12/6/2019 | 12/30/2019 | | DONE |
|
|
|
mailed 1-1-20
|
First Notice | | 10/26/2019 | 11/26/2019 | | DONE |
|
|
|
mailed 12-2-19
|
BLD-Final | 10/16/2019 | 10/16/2019 | 10/16/2019 | P | PASS |
Mike Jordan
|
|
|
Inspection requested via web by James Hibbard. Ok for perm occ.
|
FIRE-Final Inspection | 10/15/2019 | 10/16/2019 | 10/16/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. No card on site to sign.
7am Phone #: ###-#### Inspection requested via web by James Hibbard
|
FIRE-Alarm Testing | 10/15/2019 | 10/16/2019 | 10/16/2019 | A | FAIL |
Troy Cobbley
|
|
|
Fire alarm testing needs to be scheduled with the project related FIR permit. 7am Phone #: ###-#### Inspection requested via web by James Hibbard
|
Permanent Occupancy | | | 10/16/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/15/2019 | | DONE |
|
|
|
PLAN MOD
|
CHANGE STATUS TO (ISS) | | | 10/15/2019 | | DONE |
|
|
|
plan mod fee paid change status to ISS
|
Plan assigned to (JHB) | 10/4/2019 | 10/4/2019 | 10/11/2019 | | PASS |
Joe Bruce
|
|
|
10/15 (plan mod) St Alphonsus - suite #300
|
Routing - MECHANICAL | 10/8/2019 | | 10/11/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 10/8/2019 | | 10/10/2019 | | PASS |
Joe Bruce
|
|
|
|
Routing - PLUMBING | 10/8/2019 | | 10/9/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Route to Impact Fee Review | 10/4/2019 | 10/7/2019 | 10/7/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
FIRE-Final Inspection | 10/3/2019 | 10/4/2019 | 10/4/2019 | A | FAIL |
Troy Cobbley
|
|
|
Need the project related fire alarm and fire sprinkler permits finaled. I noted that doors have been revised but there were no stamped plans showing the changes had been approved on site. The single main exit door has been changed to a double door with door magnets. It appears to need to meet IFC chapter 10 "sensor controled door" which will require a sensor and interconnection with the fire alarm system. Please contact Jim at ###-####
|
Plan Modification Accepted | | | 10/4/2019 | | DONE |
|
|
|
hardware schedule updated per associated changes
|
BLD-Ceiling Grid Inspection | 9/10/2019 | 9/10/2019 | 9/10/2019 | A | PASS |
Mike Jordan
|
|
|
Mike can you be here after 10 am to inspect the ceiling grid. Phone #: ###-#### Inspection requested via web by James Hibbard
|
BLD-Ceiling Grid Inspection | 9/9/2019 | 9/9/2019 | 9/9/2019 | P | FAIL |
Mike Jordan
|
|
|
James Hibbard is the contact on 3rd floor of the Mulvaney building Phone #: ###-#### Inspection requested via web by James Hibbard. Noted missing clips and wires not tied.
|
FIRE-Sprinkler Rough-in | 6/5/2019 | 6/5/2019 | 6/5/2019 | P | CANC |
Troy Cobbley
|
|
|
Wrong permit called in for the inspection type requested.
Contact Jim Hibbard for any questions Phone #: ###-#### Inspection requested via web by James Hibbard
|
BLD-Framing/Rough-in | 6/3/2019 | 6/3/2019 | 6/3/2019 | P | PASS |
Mike Jordan
|
|
|
contact Jim Hibbard for any questions Phone #: ###-#### Inspection requested via web by James Hibbard. Interior steel stud framed walls only ok.
|
BLD-Framing/Rough-in | 5/23/2019 | 5/28/2019 | 5/28/2019 | A | NR |
Mike Jordan
|
|
|
Contact Jim Hibbard for any questions Phone #: ###-#### Inspection requested via web by James Hibbard. Needs electrical permit and rough in inspections first.
|
Issue PAID IN FULL permit | | | 4/30/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/30/2019 | | DONE |
|
|
|
|
Plan assigned to (JHB) | 3/18/2019 | 3/18/2019 | 3/28/2019 | | PASS |
Joe Bruce
|
|
|
03/27 (L2) SARMC Cons. Gen. Surgery ePlan
|
Routing - FIRE | 3/18/2019 | 3/18/2019 | 3/28/2019 | | PASS |
Mark Scharfen
|
|
|
IFC Review 03.28.2019.pdf uploaded.
|
1st review completed | | | 3/28/2019 | | DONE |
Joe Bruce
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/28/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/28/2019 | | |
|
|
|
MET ERIN@EKCCONSTRUCTION.COM
Need
GC FORM
CERT OF VALUE
|
Plan Reviewer's activity | | | 3/26/2019 | | DONE |
Joe Bruce
|
|
|
Spoke with Mark Hirschi and received clarification that this is NOT an ambulatory care facility. The procedure rooms will be used for minor procedures that do not render the patient incapable of self-preservation. **JHB**
|
Routing - PLAN CHECK | 3/18/2019 | | 3/26/2019 | | PASS |
Joe Bruce
|
|
|
|
Routing PW Environmental | 3/18/2019 | | 3/25/2019 | | PASS |
Terry Alber
|
|
|
No Pretreatment issues apparent.
|
Routing PW Solid Waste | 3/18/2019 | | 3/21/2019 | | PASS |
Evan Carpenter
|
|
|
No changes to solid waste.
|
Routing - MECHANICAL | 3/18/2019 | | 3/19/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 3/18/2019 | | 3/18/2019 | | PASS |
Daryl Spivey
|
|
|
per plan and ISPC.
|
Routing - Addressing | 3/18/2019 | | 3/18/2019 | | PASS |
Doug Chausow
|
|
|
Suite 300
|
Routing - PUBLIC WORKS | 3/18/2019 | | 3/18/2019 | | PASS |
Angela Hardy
|
|
|
|
Intake Approval | | | 3/14/2019 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 3/11/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 11 2019 1:41PM
|