FIRE-Final Inspection | 12/6/2019 | 12/6/2019 | 12/6/2019 | P | FAIL |
Jim Page
|
|
|
Fire alarm panel has open circuit trouble on NAC circuit, panel needs to be normal for life fire safety inspection. A fire alarm vendor will need to be present for the life fire safety inspection, due to fire alarm devices being removed and re-installed during this scope of work a fire alarm test will be required to verify proper operation of fire alarm system in scope of work areas.
Tom Phone #: ###-####
|
BLD-Final | 11/7/2019 | 11/8/2019 | 11/14/2019 | P | PEND |
Dave Hannah
|
|
|
Tom Phone #: ###-#### needs fire first
|
FIRE-Final Inspection | 11/7/2019 | 11/8/2019 | 11/8/2019 | A | FAIL |
Jim Page
|
|
|
Architectural feature at bottom of escalator is not installed, fire sprinkler head is to far down from deck, feature needs to be in place for final sign off. Need a fire alarm vendor available to test fire alarm system as discussed as verbally discussed, audio visual devices were removed and re-installed during project, need to verify operation.
Tom Phone #: ###-####
|
BLD-Conference | 10/31/2019 | 11/1/2019 | 11/1/2019 | A | DONE |
Dave Hannah
|
|
|
Tom Phone #: ###-####
|
FIRE-Conference | 10/15/2019 | 10/16/2019 | 10/16/2019 | A | DONE |
Troy Cobbley
|
|
|
** Met with Tom. Discussed exit lighting, fire sprinkler, and fire alarm placement questions he had. He is going to meet with the architect to go over items we discussed.**MAS***Tom Phone #: ###-####
|
BLD-Framing/Rough-in | 9/4/2019 | 9/4/2019 | 9/5/2019 | P | PASS |
Dave Hannah
|
|
|
Tom Phone #: ###-####
|
BLD-Foundation | 7/17/2019 | 7/18/2019 | 7/18/2019 | P | PASS |
Dave Hannah
|
|
|
TOM- REBAR INSPECTION Phone #: ###-####
|
Inspection Record Card- Bld | | | 6/20/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/20/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/6/2019 | | DONE |
|
|
|
MET BRADY@GUHOCORP.COM
NEED
GC
Revised Certificate of Value
|
Plan assigned to (JAR) | 4/25/2019 | 4/25/2019 | 6/5/2019 | | DONE |
Julie Romig
|
|
|
06/10 - 2nd Rev - 1st Rev Comp - L3 Capitol Terrace
|
Routing - PLAN CHECK | 6/4/2019 | | 6/5/2019 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/5/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 5/23/2019 | 5/26/2019 | 5/23/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 5/23/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 4/25/2019 | | 5/23/2019 | | FAIL |
Julie Romig
|
|
|
Refer to ePlanReview changemarks for required corrections.
|
Routing - FIRE | 4/25/2019 | 4/25/2019 | 5/20/2019 | | PASS |
Erika Akin
|
|
|
No comments attached. New stairs added to exisiting structure. Fire extinguishers shown on plan sheets G101 and G102. Inspector to field verify life safety. Modifications to the existing automatic sprinkler system in this facility may be required for the improvements planned. The tenant improvement plans shall be reviewed by a licensed fire sprinkler contractor, to determine what, if any, modifications are necessary to maintain code compliance within the project area. A permit will be required for any necessary modifications to the sprinkler or alarm systems.
|
Routing Off Site - STRUCTURAL | 4/25/2019 | | 5/7/2019 | | PASS |
Julie Romig
|
|
|
|
Routing PW Drainage | 4/25/2019 | | 4/26/2019 | | PASS |
Brian Murphy
|
|
|
|
Routing - Addressing | 4/25/2019 | | 4/25/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 4/25/2019 | | 4/25/2019 | | PASS |
Morgan Webb
|
|
|
NO NEW PLUMBING
|
Routing - Design Review | 4/25/2019 | | 4/25/2019 | | PASS |
Andrea Tuning
|
|
|
|
Intake Approval | | | 4/23/2019 | | PASS |
|
|
|
|
Application received | | | 4/22/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 22 2019 2:36PM
|