Permit Information
Permit NumberBLD19-04254
StatusFinaled
Name CBH HOMES
Site Address 10003 W CAMPVILLE ST
Project NameLOT 04 BLK 11 UNION SQUARE SUB
Customer Number 
ePlanReviewYes
Description
Permit for the construction of a new 2,002sq' two-story (1st story 922sq', 2nd story 1,080 sq') single family dwelling with 4 bedrooms, 2.5 bathrooms, approximately 36sq' of covered patio/porch and a 462sq' attached garage per the approved plans, any notations, local codes & ordinances. R-2D zoning and setbacks per Planning. **JAB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final2/26/20202/26/20202/26/2020PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Joel Hirtle
DOC - Permit Finaled2/26/20202/26/20202/26/2020PPASS
DetailsMike Jordan
BLD-Blower Door Test Results2/26/20202/26/20202/26/2020PDONE
DetailsMike Jordan
4.4
BLD-Energy code compliance1/13/20201/14/20201/14/2020PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Joel Hirtle
BLD-Framing/Rough-in1/10/20201/13/20201/13/2020APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Joel Hirtle
BLD-Framing/Rough-in1/6/20201/10/20201/10/2020ANR
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Needs mech. rough in inspection.
Routing - MECHANICAL1/8/2020 1/9/2020 PASS
DetailsChad Schwendiman
Plan Modification Accepted  1/7/2020 DONE
Gloria from CBH requested a plan mod workflow for Manual J
BLD-Wall Bracing12/27/201912/30/201912/30/2019APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Ok to cover exterior. will Check LIB and north column repair on framing inspection.
BLD-Foundation12/5/201912/6/201912/6/2019PPART
DetailsMike Jordan
Dane Phone #: ###-####
BLD-Footing12/4/201912/5/201912/5/2019PPASS
DetailsMike Jordan
Dane Phone #: ###-####
BLD-Footing12/3/201912/4/201912/4/2019PPASS
DetailsMike Jordan
Dane Phone #: ###-####
OVERRIDE  11/22/2019  
Plan assigned to (JAB) Josh11/22/201911/22/201911/22/2019 PASS
DetailsJosh Bogle
11/12 sfd L1 ePlan
Plan assigned to (RDP)10/28/201910/28/201911/22/2019 DEFR
DetailsRob Patrick
11/12 sfd L1 ePlan
Routing - PLAN CHECK10/28/2019 11/22/2019 PASS
DetailsRob Patrick
1st review completed  11/22/2019 DONE
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  11/22/2019 DONE
DetailsJosh Bogle
Permit Ready to Issue  11/22/2019 DONE
met
Issue PAID IN FULL permit  11/22/2019 DONE
Inspection Record Card- Bld  11/22/2019 DONE
Route to Impact Fee Review10/28/201910/31/201910/29/2019 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Routing - MECHANICAL10/28/2019 10/28/2019 PASS
DetailsTroy James
Routing - PLANNING10/28/2019 10/28/2019 PASS
DetailsEthan Mansfield
Routing - Addressing10/28/2019 10/28/2019 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS10/28/2019 10/28/2019 PASS
DetailsCandy A. Nichols
Plans ACCEPTED BY PLAN TECH  10/28/2019 DONE
Recd Pcfee & Taken To Pln CK  10/28/2019 DONE
Intake Approval  10/28/2019 PASS
Application received  10/25/2019 DONE
Application submitted via PDS Online on Oct 25 2019 6:38AM
Intake Approval  10/25/2019 FAIL
Must provide ACCA report (Manual J)