BLD-Final | 3/31/2020 | 4/1/2020 | 4/1/2020 | A | PASS |
Mike Jordan
|
|
|
We finally got the step installed. Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
DOC - Permit Finaled | 4/1/2020 | 4/1/2020 | 4/1/2020 | P | PASS |
Mike Jordan
|
|
|
All issues resolved.
|
BLD-Final | 3/3/2020 | 3/4/2020 | 3/4/2020 | P | FAIL |
Mike Jordan
|
|
|
Front door is open Phone #: ###-#### Inspection requested via web by Joel Hirtle. Step from slider to patio exceeds the 7.75 max .
|
BLD-Blower Door Test Results | 3/4/2020 | 3/4/2020 | 3/4/2020 | P | DONE |
Mike Jordan
|
|
|
3.1
|
BLD-Energy code compliance | 1/21/2020 | 1/22/2020 | 1/22/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Framing/Rough-in | 1/21/2020 | 1/22/2020 | 1/22/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Framing/Rough-in | 1/17/2020 | 1/21/2020 | 1/21/2020 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Missed bearing point on F7 floor truss. Provide approved fix for cut top chord on F13 floor truss. Ok to insulate.
|
BLD-Wall Bracing | 1/10/2020 | 1/10/2020 | 1/10/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Wall Bracing | 1/8/2020 | 1/10/2020 | 1/10/2020 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
Routing - MECHANICAL | 1/2/2020 | | 1/3/2020 | | PASS |
Troy James
|
|
|
|
Plan Modification Accepted | | | 12/31/2019 | | DONE |
|
|
|
Gloria requested the workflow to be opened for new Manual J.
|
BLD-Foundation | 12/16/2019 | 12/17/2019 | 12/17/2019 | P | PART |
Mike Jordan
|
|
|
Dane- foundation wall Phone #: ###-####
|
BLD-Foundation | 12/13/2019 | 12/16/2019 | 12/16/2019 | P | NR |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 12/12/2019 | 12/13/2019 | 12/13/2019 | P | PART |
Mike Jordan
|
|
|
Dane - Phone #: ###-####
|
BLD-Foundation | 12/11/2019 | 12/12/2019 | 12/12/2019 | P | CANC |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 12/10/2019 | 12/11/2019 | 12/11/2019 | P | NR |
Mike Jordan
|
|
|
Dane Phone #: ###-####. No one on site. Concrete form work has not yet been constructed.
|
Issue PAID IN FULL permit | | | 11/26/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/26/2019 | | DONE |
|
|
|
|
Telephone call | | | 11/26/2019 | | DONE |
|
|
|
emailed permit to be signed to-permitting@cbhhomes.com EPLAN needs to be release
|
OVERRIDE | | | 11/25/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 11/25/2019 | 11/25/2019 | 11/25/2019 | | DONE |
Jenny Nelson
|
|
|
|
Plan assigned to (RDP) | 10/28/2019 | 10/28/2019 | 11/25/2019 | | DEFR |
Rob Patrick
|
|
|
11/12 sfd L1 ePlan
|
Routing - PLAN CHECK | 10/28/2019 | | 11/25/2019 | | PASS |
Jenny Nelson
|
|
|
|
1st review completed | | | 11/25/2019 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/25/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 11/25/2019 | | DONE |
|
|
|
met
|
Routing - MECHANICAL | 10/28/2019 | | 10/30/2019 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 10/28/2019 | 10/31/2019 | 10/29/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 10/28/2019 | | 10/28/2019 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 10/28/2019 | | 10/28/2019 | | PASS |
Doug Chausow
|
|
|
Corrected address: 10075 W Campville St
|
Routing - PUBLIC WORKS | 10/28/2019 | | 10/28/2019 | | PASS |
Candy A. Nichols
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/28/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/28/2019 | | DONE |
|
|
|
|
Intake Approval | | | 10/28/2019 | | PASS |
|
|
|
|
Application received | | | 10/25/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 25 2019 7:35AM
|