BLD-Final | 7/16/2020 | 7/16/2020 | 7/16/2020 | P | PASS |
Dave Hannah
|
|
|
screened // Joe Phone #: ###-####
|
DOC - Permit Finaled | 7/16/2020 | 7/16/2020 | 7/16/2020 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 7/9/2020 | 7/9/2020 | 7/13/2020 | | PEND |
Tell Riley
|
|
|
|
BLD-Final | 2/24/2020 | 2/25/2020 | 2/25/2020 | A | PART |
Tell Riley
|
|
|
Kevin Phone #: ###-####//electrical final complete//building complete per plans//need landing at door,,width of door and 3 feet projection//ok to use building, call for re-inspect when landing is complete//
|
BLD-Final | 2/20/2020 | 2/20/2020 | 2/20/2020 | P | NR |
Tell Riley
|
|
|
Kevin Phone #: ###-####
|
BLD-Framing/Rough-in | 2/3/2020 | 2/3/2020 | 2/3/2020 | P | PASS |
Tell Riley
|
|
|
Kevin Phone #: ###-####//per plans//
|
Routing Walk-In (BLD) | 1/31/2020 | 1/31/2020 | 1/31/2020 | P | PASS |
Josh Bogle
|
|
|
|
BLD-Wall Bracing | 1/17/2020 | 1/21/2020 | 1/21/2020 | A | PASS |
Tell Riley
|
|
|
shear // Joseph Phone #: ###-####//ok when hot dipped nails added to PT plate-discussed with contractor onsite//
|
Routing Walk-In (BLD) | 1/17/2020 | 1/17/2020 | 1/17/2020 | P | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 1/17/2020 | | 1/17/2020 | | PASS |
Josh Bogle
|
|
|
no PR fee
|
Case Summary (BLD) | | | 1/17/2020 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 1/17/2020 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 1/17/2020 | | DONE |
|
|
|
no fee per josh
|
BLD-Wall Bracing | 1/10/2020 | 1/13/2020 | 1/13/2020 | A | FAIL |
Tell Riley
|
|
|
shear // Nate Phone #: ###-####//CN posted//need hot dipped in PT and need to add anchor bolts per plans//see plans for header sizes//
|
BLD-Footing | 12/9/2019 | 12/9/2019 | 12/9/2019 | P | PASS |
Tell Riley
|
|
|
Chuck Phone #: ###-####//pin located//5 foot side tight-hold over to meet setbacks//blankets onsite//per plans//
|
BLD-Footing | 12/5/2019 | 12/6/2019 | 12/6/2019 | A | FAIL |
Tell Riley
|
|
|
Jason Phone #: ###-####//please locate and mark property corner pin and mark property lines for setback inspeciton//
|
Routing Walk-In (Zoning) | 11/1/2019 | 11/1/2019 | 11/1/2019 | P | PASS |
Nicolette Womack
|
|
|
|
Routing Walk-In (BLD) | 11/1/2019 | 11/1/2019 | 11/1/2019 | P | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 11/1/2019 | | 11/1/2019 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 11/1/2019 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 11/1/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 11/1/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/1/2019 | | DONE |
Josh Bogle
|
|
|
ESC no -Energy no
|
Permit Ready to Issue | | | 11/1/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/1/2019 | | DONE |
|
|
|
|
Application received | | 11/1/2019 | | | |
|
|
|
|