Site Final | 12/24/2019 | 12/24/2019 | 12/24/2019 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 12/24/2019 | 12/24/2019 | 12/24/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/5/2019 | 11/5/2019 | 11/6/2019 | | PASS |
Andy J. Long
|
|
|
|
Random Inspection | 9/17/2019 | 9/17/2019 | 9/17/2019 | P | PASS |
Andy J. Long
|
|
|
No trackout or discharges. WIP on interior
|
General Inspection | 8/26/2019 | 8/26/2019 | 8/26/2019 | P | PASS |
Michael Zawacki
|
|
|
Exterior walls completed. Site has natural buffers, no dirt leaving site. Area is clean, has paved parking and storge, no esc issues.
|
Site Preparation | 4/12/2019 | 4/15/2019 | 4/15/2019 | A | PASS |
Andy J. Long
|
|
|
Jay Phone #: ###-####
Permit sign posted. Lined pit concrete washout installed. Using existing paved access to site.
Existing grass buffer preserved and wattle installed on east boundary to protect irrigation/drainage ditch.
Approved.
|
Issue & PRINT permit COM | | | 4/8/2019 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 1/4/2019 | | 1/4/2019 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Certified Plan Designer; need to identify certified RP prior to permit issue. Site Preparation inspection is REQUIRED.
|
Application received | | | 12/21/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 21 2018 9:14AM
|