INSP-Final Inspection | 4/17/2018 | 4/18/2018 | 4/18/2018 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
Plan Modification Accepted | | | 4/17/2018 | | DONE |
|
|
|
|
Sprinkler Plan Check | 4/17/2018 | | 4/17/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/17/2018 | | DONE |
|
|
|
|
Issue and Print Permit | | | 4/17/2018 | | DONE |
|
|
|
|
INSP-Final Inspection | 4/11/2018 | 4/12/2018 | 4/12/2018 | A | FAIL |
Troy Cobbley
|
|
|
Provide clearance around the underground supply. It appears the backflow preventor is causing the flow switch to "cycle". This issue needs resolve. The forward flush passed but if the backflow assembly is changed it will need redone. Plans may need to be resubmitted if changes are made.
George Jess is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 4/10/2018 | 4/11/2018 | 4/11/2018 | P | CANC |
Troy Cobbley
|
|
|
George Jess is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
Plan Modification Accepted | | | 4/10/2018 | | DONE |
|
|
|
|
Sprinkler Plan Check | 4/10/2018 | | 4/10/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/10/2018 | | DONE |
|
|
|
|
(F) Reprint permit | | | 4/10/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/10/2018 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 4/10/2018 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in | 3/23/2018 | 3/26/2018 | 3/26/2018 | A | PASS |
Troy Cobbley
|
|
|
Coreections have been made. Piping can be covered
George Jess is the contact for this rough to cover inspection. Thanks for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 3/19/2018 | 3/20/2018 | 3/20/2018 | A | PART |
Troy Cobbley
|
|
|
Provide flexible couplings on both sides of the CMU wall, provide sprinkler protection in small room as discussed, provide branchline restraints as shown on the plans, provide verification that the CC heads are listed for 9' off of walls. Provide all of the missing small documents
George Jess is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 2/15/2018 | 2/16/2018 | 2/16/2018 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|
INSP-Sprinkler Rough-in/Hydro | 2/14/2018 | 2/15/2018 | 2/15/2018 | P | CANC |
Troy Cobbley
|
|
|
I'm unable to make it back for this hydro test. To be rescheduled for tomorrow
George Jess is the contact for this overhead hydro. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 1/31/2018 | 1/31/2018 | 1/31/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located above hardlids complete, hardlids approved for cover.
|
INSP-Sprinkler Rough-in | 1/29/2018 | 1/29/2018 | 1/29/2018 | P | CANC |
Troy Cobbley
|
|
|
To be re-scheduled per George.
George Jess is the contact for this rough in inspection. He is hoping for an appointment in the pm. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 11/29/2017 | 11/30/2017 | 11/29/2017 | A | CANC |
Troy Cobbley
|
|
|
Bryan Collins is the contact for this Underground Rough-in. Thank you for your time. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
Issue and Print Permit | | | 11/29/2017 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/22/2017 | | 11/22/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/22/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 11/22/2017 | | DONE |
|
|
|
|
Intake Approval | | | 11/20/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 11/20/2017 | | 11/20/2017 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 11/14/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 14 2017 8:15AM
|