INSP-Final Inspection | 7/25/2019 | 7/26/2019 | 7/26/2019 | A | PASS |
Jim Page
|
|
|
Previously noted items that were notated on the city approved drawings has been corrected, final fire sprinkler inspection for area of work complete.
Clarence Phone #: ###-####
|
Plan Modification Accepted | | | 7/12/2019 | | DONE |
|
|
|
sprinkler heads
|
Plan assigned to (Stumbaugh) | 7/12/2019 | | 7/12/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 7/12/2019 | | 7/12/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/12/2019 | | DONE |
Mark Stumbaugh
|
|
|
Plan Mod Fee $150.00
|
Permit Ready to Issue | | | 7/12/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 7/12/2019 | | DONE |
|
|
|
plan mod
|
INSP-Final Inspection | 6/25/2019 | 6/25/2019 | 6/25/2019 | P | FAIL |
Jim Page
|
|
|
Dillon has the city approved drawings that have been notated, numerous areas has no sway bracing, sway bracing is shown on the city approved drawings, sway bracing needs to be installed or removed from the city approved drawings. Numerous heads under duct work and piping has been added but the approved drawings do not reflect the install. City approved drawings have been notated where corrections need to be made.
Dillon Phone #: ###-####
|
INSP-Final Inspection | 6/18/2019 | 6/19/2019 | 6/19/2019 | A | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with point of contact, city approved drawings/small documents could not be located, city approved drawings and small documents are required for inspection.
Dillion Phone #: ###-####
|
INSP-Final Inspection | 4/12/2019 | 4/12/2019 | 4/12/2019 | P | CANC |
Jim Page
|
|
|
Per conversation with my supervisor, Adele Schaffeld-Griffin, notes entered reading "Final fire sprinkler sign off of inspections for this permit will be completed at the same time as the life safety inspection is completed under the building permit." Please coordination with the general contractor to schedule the final inspections. Onsite inspection request for today will need to be rescheduled until coordinated inspections for the life safety can be scheduled.
Clarence Phone #: ###-####
|
INSP-Final Inspection | 7/30/2018 | 7/31/2018 | 7/31/2018 | P | PART |
Jim Page
|
|
|
Final fire sprinkler inspection complete, fire sprinkler permit will remain in issued status until project is complete due to possible obstructions needing coverage.
Chris Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 6/15/2018 | 6/18/2018 | 6/18/2018 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed at riser provided gauge.
Chris Phone #: ###-####
|
Fees Due Hold | 2/28/2018 | | 3/8/2018 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 1/25/2018 | | 2/27/2018 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 1/24/2018 | | 1/24/2018 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 1/24/2018 | | DONE |
|
|
|
Per email from Paul Marcolina, Micron will include this permit on their monthy statement.
|
Sprinkler Plan Check | 1/23/2018 | | 1/23/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/23/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 1/23/2018 | | DONE |
|
|
|
|
Issue and Print Permit | | | 1/23/2018 | | DONE |
|
|
|
Micron
|
Sprinkler Plan Check | 1/18/2018 | | 1/18/2018 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 1/18/2018 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 1/4/2018 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 1/4/2018 | | 1/4/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 1/4/2018 | | 1/4/2018 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 1/4/2018 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 1/4/2018 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 1/2/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 2 2018 12:19PM
|