Information based on query as of Monday, May 20, 2024.
Permit Information
Permit NumberFIR18-00740
StatusFinaled
Name APEX INTEGRATED SECURITY SOLUTIONS
Site Address 8000 S FEDERAL WAY
Project NameMicron Bldg 36 Cafe Expansion
Customer Number 
ePlanReviewYes
Description
Micron Building 36 Cafeteria Expansion includes additional audible and visible notification and pull stations. Some existing devices are to remain. This work is associated with building permit BLD18-00803.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/2/20194/3/20194/3/2019APASS
DetailsTroy Cobbley
Permit finaled. Previous correction notes have been addressed and plan mods received.

As early as possible Phone #: 2088990672 >> Inspection requested via mobile web by Josiah
Miscellaneous action  4/3/2019 DONE
Record of completion received.
Plan resubmittals received  3/20/2019 DONE
Per Dante at Apex who requested new workflow, start workflow to upload as built
Plan assigned to (Lee)3/20/2019 3/20/2019 DONE
DetailsLee G Meredith
1st review completed  3/20/2019 PASS
Alarm Plan Check3/20/2019 3/20/2019 PASS
DetailsLee G Meredith
PLANS TAKEN FRONT DESK ALARM  3/20/2019 DONE
As built passed. No additional comments.
Permit Ready to Issue  3/20/2019 DONE
plan mod
CHANGE STATUS TO (ISS)  3/20/2019 DONE
plan mod
INSP-Final Inspection3/4/20193/5/20193/5/2019AFAIL
DetailsJim Page
Phone #: 2088990672 >> Inspection requested via mobile web by Josiah.

Numerous strobes at wrong height.One Visible coverage is inadequate at speaker SP1:30 in Kitchen. 15cd strobe PS:11:4:5 at vending brown bag needs to be removed. Adjust 11:4:1 to compensate. Its blocked by Refers. Strobes too low and/or blocked by shelves are 10:2:1, 10:2:210:1:4 and 20:2:4. All other equipment tested ok. Audible and visible needs to be retested.
INSP-Sprinkler Rough-in/Hydro3/4/20193/5/20193/4/2019ACANC
DetailsTroy Cobbley
Phone #: 2088990672 >> Inspection requested via mobile web by Josiah Inspection cancelled via mobile web on Monday, March 04, 2019.
Miscellaneous action  3/4/2019 DONE
Imported lumens per sq. ft calcs.
INSP-Alarm Testing2/22/20192/25/20192/25/2019APART
DetailsJim Page
Alarm testing for phase 4 and 5 areas complete, city approved drawings must be current for next inspection.

Phone #: 2088990672 >> Inspection requested via mobile web by Josiah
Miscellaneous action  2/25/2019 DONE
imported as built drawings.
INSP-Sprinkler Rough-in/Hydro2/22/20192/25/20192/22/2019ACANC
DetailsTroy Cobbley
Phone #: 2088990672 >> Inspection requested via mobile web by Josiah Froese Inspection cancelled via mobile web on Friday, February 22, 2019.
INSP-Alarm Testing2/21/20192/22/20192/22/2019AFAIL
DetailsTroy Cobbley
I was only able to check the sync of the devices today due to multiple a/v's that are overspaced. Plan modifications are required showing all of the changes required today and all of the changes that have been made on prior inspections. Phone #: 2088990672 >> Inspection requested via mobile web by Josiah
INSP-Alarm Testing1/17/20191/18/20191/18/2019APART
DetailsJim Page
Fire alarm testing for TCO requested area in kitchen serving area complete.

As early as possible Phone #: 2088308262 >> Inspection requested via mobile web by Tip Ioane
INSP-Alarm Testing1/14/20191/15/20191/15/2019ADONE
DetailsJim Page
Fire alarm testing for TCO requested area of cafeteria complete, horn strobes are in place, speaker strobes to be installed for final inspection.

As early as possible Phone #: 2088990672 >> Inspection requested via mobile web by Josiah Froese
INSP-Sprinkler Rough-in/Hydro1/14/20191/15/20191/14/2019ACANC
DetailsTroy Cobbley
As early as possible Phone #: 2088996072 >> Inspection requested via mobile web by Josiah Froese Inspection cancelled via mobile web on Monday, January 14, 2019.
INSP-Alarm Testing1/14/20191/14/20191/14/2019PCANC
DetailsTroy Cobbley
As late as possible Phone #: 2088990672 >> Inspection requested via mobile web by Josiah Froese Inspection cancelled via mobile web on Monday, January 14, 2019.
INSP-Final Inspection11/21/201811/21/201811/21/2018PPART
DetailsJim Page
Temporary notification has been placed in areas associated with phase 2, each phase will require a fire alarm inspection for audio visual notification before TCO authorization. Temp A/V devices for phase 2 complete and operational.
INSP-Final Inspection11/21/201811/21/201811/21/2018AFAIL
DetailsJim Page
Could not sound off audio visual devices due to lack of coordination with micron, inspection will need to be rescheduled.
INSP-Conference11/20/201811/21/201811/21/2018ADONE
DetailsJim Page
Conference complete.

Phone #: 2088308262 >> Inspection requested via mobile web by Tip Ioane
INSP-Alarm Testing11/20/201811/20/201811/20/2018ACANC
DetailsJim Page
Spoke with permit holding contractor, Micron needs more of a notice for fire alarm testing, alarm testing cannot be completed today based on conversation with Apex. This request is cancelled by request.

Call prior to going Phone #: 2088308262 >> Inspection requested via mobile web by Tip Ioane
Plan assigned to (Lee)9/25/2018 9/26/2018 DONE
DetailsLee G Meredith
1st review completed  9/26/2018 PASS
Alarm Plan Check9/25/2018 9/26/2018 DONE
DetailsLee G Meredith
PLANS TAKEN FRONT DESK ALARM  9/26/2018 DONE
Plans approved with review comments.
Permit Ready to Issue  9/26/2018 DONE
all requirements met
Issue and Print Permit  9/26/2018 DONE
Application received  9/25/2018 DONE
Application submitted via PDS Online on Sep 25 2018 1:26PM