INSP-Final Inspection | 1/28/2019 | 1/30/2019 | 1/30/2019 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Contact is Tod Ketterling. Thank you for all that you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 1/24/2019 | 1/25/2019 | 1/25/2019 | A | DONE |
Jim Page
|
|
|
Fire pump commissioning complete.
Todd Ketterling is the contact for this inspection. He is needing a pump commissioning inspection. He is hoping for a call before hand to let him know what time appointment will be tomorrow so he can be ready. We thank you for your help. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 1/21/2019 | 1/22/2019 | 1/22/2019 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed.
Todd Ketterling is the contact for this over head hydro. Thank you for your help. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 12/14/2018 | 12/17/2018 | 12/17/2018 | A | PASS |
Jim Page
|
|
|
Rough in inspection for overhead fire sprinkler associated with core and shell complete, any areas outside of corr and shell will require a cover inspection.
Todd Ketterling is the contact for this RTC inspection. Thank you for your help. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
|
Plan resubmittals received | | | 10/10/2018 | | DONE |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 10/10/2018 | | 10/10/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/10/2018 | | 10/10/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/10/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 10/10/2018 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 10/10/2018 | | DONE |
|
|
|
|
Sprinkler Plan Check | 10/9/2018 | | 10/9/2018 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 10/9/2018 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 10/9/2018 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Plan assigned to (Tim) | 10/5/2018 | | 10/5/2018 | | DONE |
Tim Frost
|
|
|
|
Intake Approval | | | 10/5/2018 | | PASS |
Tim Frost
|
|
|
|
Application received | | | 10/4/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 4 2018 11:40AM
|