Permit Information
Permit NumberBLD17-01656
StatusFinaled
Name CHAMISA BUILDING CO INC
Site Address 7500 W MOSSY CUP ST
Project NameNxEdge-Spray Booth & 2nd story
Customer Number 
ePlanReviewYes
Description
(NXEDGE INC. – ACOUSTIC SPRAY BOOTHS AND 2ND STORY) (CZC17-00064) (7-28-18 PLAN MODIFICATION TO CHANGE SOME SIDE-HINGED SWINGING DOORS TO HORIZONTAL SLIDING DOORS WHERE THE OCCUPANT LOAD SERVED BY THE DOORS IS 10 OR LESS.) (1-23-18 PLAN MODIFICATION TO CREATE TWO SEPARATE CLEAN ROOMS (272 SQUARE FEET AND 387 SQUARE FEET) AND A CLEAN ROOM VESTIBULE (62 SQUARE FEET) ENCLOSED BY WALLS, HARD CEILINGS, AND FLOORS WITHIN THE EXISTING BUILDING. SEE THE DESCRIPTION IN THE COMMENTS SECTION OF THIS PERMIT FOR MORE INFORMATION. (11-16-17 PLAN MODIFICATION TO CONSTRUCT A GUARD AT THE EDGE OF AN EQUIPMENT MEZZANINE AND TO MOVE THE PREVIOUSLY APPROVED LADDER. THE EQUIPMENT MEZZANINE IS AN UNOCCUPIED SPACE WHERE STORAGE IS PLACED AND RETRIEVED BY A FORK LIFT ONLY AND ACCESS IS INFREQUENT AND ONLY FOR EQUIPMENT MAINTENANCE.) (10-9-17 PLAN MODIFICATION TO CREATE A 566 SQUARE FOOT STORAGE AND MECHANICAL AREA HAVING A LIVE LOAD CAPACITY OF 125 PSF ABOVE BUFFING ROOM 100 AND SERVED ONLY BY A LADDER, TO INSTALL ADDITIONAL EXHAUST FANS, AND TO PLACE EXTERIOR CONCRETE EQUIPMENT SLABS.) The fire sprinkler system is used for building area increase, for story increase, to allow the H-3 Occupancy, and for fire area. This building was originally constructed in Ada County and then later annexed into the City of Boise. The H-3 Occupancy and its fire separation from the rest of the building is not being altered. The rest of the building is considered to be one control area. The total quantity of hazardous materials located outside of the H-3 Occupancy is not allowed to exceed the maximum allowable quantity per control area as limited by the 2012 IFC. To remodel several interior areas having a total floor area of about 9,128 square feet (including a 1,876 square foot 2nd story) within an existing 27,680 square foot building (29,556 square feet including the 1,876 square foot 2nd story). About 328 square feet of an existing 640 square foot mezzanine will be demolished. The remaining mezzanine will be expanded by about 1,564 square feet to be a 1,876 square foot 2nd story. The design floor load of the 2nd story is 125 pounds per square foot. 2nd story work includes concrete footings, bearing walls, floor joists, and floor sheathing. The 2nd story will be served by an existing stairway and a new stairway. A separate new 242 square foot equipment mezzanine served by a ladder will also be constructed. The existing roof structure will be modified to support added roof-top equipment loads. Work includes blocking below equipment point loads, blocking around new roof openings, and strengthening existing roof trusses. Work also includes a new exterior wall and double leaf door, interior nonbearing walls, suspended acoustical ceilings, gypsum board ceilings, an interior airlock pass-thru, interior windows, interior sliding doors, interior side-hinged swinging doors, and equipment. Three new pre-manufactured acoustic spray booths with exhaust ducts and dust collection systems and served by roof top make-up air units and air cooled chillers will be installed. Exterior equipment slabs and exterior chain link equipment enclosures at grade will also be constructed. All equipment shall be listed and labeled per the 2014 National Electrical Code (NEC) with approval from the PDS Electrical Inspection Team. This permit is intended to establish a Certificate of Occupancy for the entire building. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/24/20189/24/20189/24/2018PPASS
DetailsMike Jordan
Zach Phone #: ###-####. ok for perm occ.
FIRE-Final Inspection9/20/20189/20/20189/20/2018PPASS
DetailsMike Jordan
Jack Phone #: ###-####. All issues have been resolved.
FIRE-Final Inspection7/5/20187/5/20187/6/2018PFAIL
DetailsTroy Cobbley
Need plan review approval of the doors being sliding not swinging out of Corridor 105 and that the door hardware is approved on the sliding doors (it requires fingers to open).

Jack Phone #: ###-####
FIRE-Final Inspection6/29/20187/2/20187/2/2018PFAIL
DetailsTroy Cobbley
Provide exit signs/repair exit signs as shown on the city approved plans, provide annual inspection for the expired fire extinguishers, provide plan review approval of the door hardware/door swing in the new areas.

Jack Phone #: ###-####
BLD-Ceiling Grid Inspection6/13/20186/13/20186/13/2018PPASS
DetailsMike Jordan
Matt Phone #: ###-####
BLD-Other3/29/20183/30/20183/30/2018ADONE
DetailsBrandon Shaw
Jack--pre-final for one area

No issues
BLD-Framing/Rough-in3/1/20183/2/20183/2/2018APASS
DetailsBrandon Shaw
Phase 4- OK to cover
BLD-Ceiling Grid Inspection1/18/20181/18/20181/18/2018PPEND
DetailsMike Jordan
Matt Phone #: ###-####. Pending plan mod. resubmittal.
BLD-Framing/Rough-in1/3/20181/4/20181/4/2018PPEND
DetailsMike Jordan
Jack Phone #: ###-####. Phase 4 interior steel stud framed walls and lids fro future grid. new drawings and engineering has been completed and is being submitted as a plan mod for review. noted to contractor ok to sheet rock interior walls with the understanding that any changes from plan rewiew will need to be corrected. ceiling id grid geilng and will be accesible for inspections if needed.
BLD-Framing/Rough-in12/20/201712/22/201712/22/2017PFAIL
DetailsMike Jordan
early afternoon- Matt Phone #: ###-####. Resubmit to plan review to reflect actual work.
BLD-Framing/Rough-in11/9/201711/9/201711/9/2017PPASS
DetailsMike Jordan
CO2 room and buffering rooms are now ok.
BLD-Framing/Rough-in11/8/201711/9/201711/9/2017AFAIL
DetailsMike Jordan
Matt Phone #: ###-####. Install the additional holdown, missing strapping and blocking.
BLD-Footing10/25/201710/26/201710/26/2017APART
DetailsMike Jordan
Matt Phone #: ###-####. Interior footing for new shear wall. Rebar cage was placed at and angle due to pre existting concrete under slab. Contractor to get RFI for fix or to leave as is.
BLD-Framing/Rough-in10/25/201710/25/201710/25/2017PPART
DetailsBrandon Shaw
Phase I, copper booth- framing- OK to cover
BLD-Ceiling Grid Inspection10/25/201710/25/201710/25/2017PPART
DetailsBrandon Shaw
Phase I, A booth- ceiling grid- OK to cover
BLD-Footing10/25/201710/25/201710/25/2017PCANC
DetailsBrandon Shaw
interior slab - Matt Phone #: ###-####
BLD-Footing10/5/201710/5/201710/5/2017PPASS
DetailsMike Jordan
Chuck Phone #: ###-####. Exterior slab on grades for new equipment pads, west side of building.
BLD-Framing/Rough-in9/29/201710/2/201710/2/2017APASS
DetailsMike Jordan
Matt-phase 1-Matt said this inspection doesn't have anything to do with the plan mod Phone #: ###-####. Interior steel stud framed walls and wood I-joist ok, phase 1.