Information based on query as of Sunday, May 12, 2024.
Permit Information
Permit NumberBLD18-01390
StatusFinaled
Name HC COMPANY INC
Site Address 7070 W OVERLAND RD
Project NameTaco Bell Overland
Customer Number 
ePlanReviewYes
Description
(TACO BELL - OVERLAND) // 10-08-18 PLAN MOD TO REMOVE AND REPLACE ALL ASPHALT IN PARKING LOT. JAR // **Permit for the demolition of an existing Taco Bell Restaurant main floor 2697 sq. ft with 1721 basement to be demolished. The construction of a new 2,530 sq. ft. one-story, wood-framed restaurant with drive thru and related site improvments. Special inspections required per attached Form 310. Approval is contingent upon adhering to the approved plans on file and attached engineering. This building is not Fire Sprinklered. **JAR**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/26/20193/27/20193/27/2019APASS
DetailsMike Jordan
Overland Taco Bell Phone #: ###-#### Inspection requested via web by Sean Worthington. Ok for perm occ.
BLD-Final1/3/20191/4/20191/4/2019PPEND
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Sean Worthington. Will be ok for Temp. occ. once public works signs off. Will be ok for perm. occ. once zoning signs perm.
FIRE-Final Inspection1/2/20191/3/20191/3/2019APASS
DetailsTroy Cobbley
Life safety passed

Sean ###-####
FIRE-Final Inspection12/28/20181/2/20191/2/2019AFAIL
DetailsTroy Cobbley
Life safety will be ok to final when the project related fire suppression permit is finaled.


Sean Phone #: ###-####
BLD-Ceiling Grid Inspection12/17/201812/18/201812/18/2018APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Sean Worthington
BLD-Wall Bracing11/19/201811/19/201811/19/2018PPASS
DetailsMike Jordan
Late pm if possible. Thank you. Interior shear. Phone #: ###-#### Inspection requested via web by Sean Worthington
BLD-Energy code compliance11/15/201811/16/201811/16/2018APASS
DetailsMike Jordan
Wall insulation Phone #: ###-#### Inspection requested via web by Sean Worthington
BLD-Energy code compliance11/14/201811/15/201811/15/2018APASS
DetailsMike Jordan
Marv''s said that they will be complete with energy seal by 10:30. Thank you Phone #: ###-#### Inspection requested via web by Sean Worthington. airseal ok.
BLD-Framing/Rough-in11/13/201811/14/201811/14/2018PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Sean Worthington
BLD-Foundation11/12/201811/13/201811/13/2018PDEFR
DetailsMike Jordan
Rebar inspection for the trash enclosure CMU. Phone #: ###-#### Inspection requested via web by Sean Worthington
BLD-Framing/Rough-in11/5/201811/5/201811/5/2018PPASS
DetailsMike Jordan
Exterior overbuild so we can cover. Phone #: ###-#### Inspection requested via web by Sean Worthington
BLD-Wall Bracing11/1/201811/2/201811/2/2018APASS
DetailsMike Jordan
Inspect shear wall nailing Phone #: ###-#### Inspection requested via web by Sean Worthington. Exterior shear nailing only ok.
BLD-Wall Bracing10/31/201811/1/201811/1/2018APART
DetailsMike Jordan
Shear // Dave Phone #: ###-####. roof nailing and hardware ok to cover. Needs to install missing hold downs and provide the additional rows of nailing at holdown locations as per endwall details. Enginner of record to provide alternate nailing detail for stud nailing at corners.
BLD-Concrete10/5/201810/8/201810/8/2018APART
DetailsMike Jordan
drive thru- Sean Phone #: ###-####. Welded wire mesh for exterior concrete slab on grade for drive through. Noted some clearance issues. Contractor to fix prior to concrete placement.
BLD-Other10/3/201810/4/201810/4/2018PPASS
DetailsBrandon Shaw
BUILDING SLAB // SEAN Phone #: ###-####
BLD-Footing9/24/20189/25/20189/25/2018APART
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Sean Worthington. Mono pour for dumpster enclosure ok.
BLD-Energy code compliance9/18/20189/18/20189/18/2018APASS
DetailsMike Jordan
e
Early if possible Phone #: ###-#### Inspection requested via web by Sean Worthington. Rigid insulation on interior of stemwall.
BLD-Foundation9/12/20189/13/20189/13/2018APART
DetailsMike Jordan
Late am. Thank you Phone #: ###-#### Inspection requested via web by Sean Worthington. Work in progres on interior mat footing for shear wall. Will be ok for concrete once special inspection has approved placement.
BLD-Foundation9/11/20189/12/20189/12/2018PPART
DetailsJim Sly
Early pm if possible. Thank you. Phone #: ###-#### Inspection requested via web by Sean Worthington
OK pending MTI special inspection, tests and approvals.
BLD-Foundation9/10/20189/11/20189/11/2018PCANC
DetailsDave Hannah
Late pm if possible. Thank you. Phone #: ###-#### >> Inspection requested via web by Sean Worthington Inspection cancelled from web by: Sean Worthington
BLD-Foundation9/10/20189/11/20189/10/2018ACANC
DetailsMike Jordan
Late am if possible. Thank you. We hope to pour at 2 pm. Phone #: ###-#### >> Inspection requested via web by Sean Worthington Inspection cancelled from web by: Sean Worthington
BLD-Footing8/29/20188/29/20188/29/2018PPART
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Sean Worthington. Work in progress. Will have special inspection.
BLD-Conference8/20/20188/20/20188/20/2018PDONE
DetailsBob Archibald
Received and approved engineering for below grade materials.
BLD-Conference8/16/20188/16/20188/16/2018PPEND
DetailsBob Archibald
Complaint that basement footing foundation being left inplace and not to be removed during demolition Spoke with demo contractor and requested a stamped document from design professional indicating that existing/remaining basement footings/walls will not compromise new construction and that failure to receive applicable documentation will result in removal.