BLD-Final | 4/1/2020 | 4/1/2020 | 4/1/2020 | P | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 4/1/2020 | 4/1/2020 | 4/1/2020 | P | PASS |
Mike Jordan
|
|
|
All work is compl;eted. Structural engineer issued final letter.
|
BLD-Aging Inspection | 11/27/2018 | 11/27/2018 | 11/27/2018 | | PEND |
Mike Jordan
|
|
|
Final is pending fianl letter from engineer of record stating that all work is acceptable.
|
BLD-Conference | 7/30/2018 | 7/30/2018 | 7/30/2018 | A | DONE |
Mike Jordan
|
|
|
|
BLD-Conference | 7/19/2018 | 7/20/2018 | 7/20/2018 | A | DONE |
Mike Jordan
|
|
|
Work almost completed. Will start install of sky lights next week. Last portion of new built up roof being placed over area of gymnastics tenant and work on cap on parapet.
|
BLD-Framing/Rough-in | 7/16/2018 | 7/16/2018 | 7/16/2018 | A | PART |
Mike Jordan
|
|
|
Work in progress on installing rigid insulation, gluing of roof board.
|
BLD-Framing/Rough-in | 7/12/2018 | 7/13/2018 | 7/13/2018 | A | PART |
Mike Jordan
|
|
|
Noted that air handler/acunit has been hung using the 3/8 inch diameter x 3 inch long anchors to bottom chords of new roof joist. Spoke with Shawn Reader (engineer) and he has noted that this is acceptable. Shawn will email me anew detail with calcs showing this will work in place of previous detail.
|
BLD-Framing/Rough-in | 7/11/2018 | 7/12/2018 | 7/12/2018 | A | PART |
Mike Jordan
|
|
|
The remainder of of roof deck that is being replaced has been completed. Attacment was ok. No joist replacement needed. Also noted that mechanical contractor started work to reinstall the airhandler/ac unit this morning. Addirional blocking was not installed per the engineers details. 3/8 inch diameter x3 inch long anchors were installed on bottom chord of new roof joist. the existing airhandler/acunit had not yet been hung. Work was temporarily stopped in this area until the appropriate blocking per the approved engineers detail has been completed and inspected prior to reinstalling the existing airhandeler/ac unit. Engineer was notified (Shawn Reader) on anchor install. Noted that it should be ok if anchors were less than 1/2 inch in diameter. Mr. Reader has been notified of the actual diameter. Will proceed as needed if there are any changes.
|
BLD-Framing/Rough-in | 7/10/2018 | 7/11/2018 | 7/11/2018 | A | PART |
Mike Jordan
|
|
|
No joist replacement was needed at area of work. New roof sheathing attachment ok.
|
BLD-Conference | 7/10/2018 | 7/10/2018 | 7/10/2018 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 7/10/2018 | 7/10/2018 | 7/10/2018 | A | PART |
Mike Jordan
|
|
|
Rea of work consisted of replacing joist were mech units were installed. sheathing attacment ok as well. Area of work done today was the worst area that needed repaired.
|
BLD-Framing/Rough-in | 7/9/2018 | 7/9/2018 | 7/9/2018 | A | PART |
Mike Jordan
|
|
|
Roof sheathing attachment ok, no joist removal in area of work. mech. units were removed today.
|
BLD-Framing/Rough-in | 7/4/2018 | 7/6/2018 | 7/6/2018 | A | PART |
Dave Hannah
|
|
|
ok to cover roof sheeting done last night nailing ok no i joist replacement needed
|
BLD-Framing/Rough-in | 7/3/2018 | 7/3/2018 | 7/3/2018 | A | PART |
Mike Jordan
|
|
|
Work in progress. Area of work consisted of 2 joist replacement today. New joist were sistered next to existing joist. Noted approx. 1.25 inch deflection(sag) in existing joist. Exisiting joist were not removed due to sprinkler pipe hangars and conduit being attached. These will need to be moved and attached to new joist.
|
BLD-Framing/Rough-in | 7/2/2018 | 7/2/2018 | 7/2/2018 | A | PART |
Mike Jordan
|
|
|
Work in progress. Roff sheathing nailing ok at area of work. No new joist.
|
BLD-Conference | 6/28/2018 | 6/29/2018 | 6/29/2018 | A | DONE |
Troy Cobbley
|
|
|
I verified that the sprinkler head distance still meets NFPA 13 for distance from the deck/bottom of joist. It appears that they are ok, as I was only able to inspect in one area. I verified this with Tim Frost in Plan Review.
|
BLD-Conference | 6/28/2018 | 6/29/2018 | 6/29/2018 | A | DONE |
Dave Hannah
|
|
|
Meet at 8:30 am.
|
BLD-Framing/Rough-in | 6/28/2018 | 6/29/2018 | 6/29/2018 | A | PART |
Mike Jordan
|
|
|
Work in progress. Inspected nailing on new roof decking at area of work. No joist replacement today.
|
BLD-Conference | 6/28/2018 | 6/28/2018 | 6/28/2018 | A | CANC |
Troy Cobbley
|
|
|
|
BLD-Framing/Rough-in | 6/28/2018 | 6/28/2018 | 6/28/2018 | A | PART |
Mike Jordan
|
|
|
Work in progress. No joist replacement. Inspected nailing on sheathing ok.
|
BLD-Framing/Rough-in | 6/27/2018 | 6/27/2018 | 6/27/2018 | A | PART |
Mike Jordan
|
|
|
Work in progress on sheathing replacement. All roof joist in area of work did not require replacement per contractor. Inspected new sheathing attacment ok.
|
BLD-Framing/Rough-in | 6/26/2018 | 6/26/2018 | 6/26/2018 | A | PART |
Mike Jordan
|
|
|
Area of work inspected today were the 4 new roof joist installed that were identified yesterday. work is in progress. Mech. units not yet removed to replace joist.
|
BLD-Framing/Rough-in | 6/25/2018 | 6/25/2018 | 6/25/2018 | A | PART |
Mike Jordan
|
|
|
work in progress. Section were roof joist has been damaged not yet removed, mech units still in place. Also another section has has been identified were roof joist will ned to be replaced. Area inspected missing fasteners in roof decking. areas were marked.
|
BLD-Framing/Rough-in | 6/22/2018 | 6/22/2018 | 6/22/2018 | A | PART |
Mike Jordan
|
|
|
Arrived on site to inspect portion of work that has been in progress and completed. Section that has been opened up is the section of roof were the Roof joists are sagging anf failing. Only on replacement was completed when arrived on site. Also noted that there are mech units that have been mounted to the bottom chords of roof joist that are failing. mech units are being removed so that joist in this are can be replaced. Engineering and details will be required prior to reinstalling mech units.
|
BLD-Framing/Rough-in | 6/20/2018 | 6/21/2018 | 6/21/2018 | A | PART |
Mike Jordan
|
|
|
Work in progress on replacing a portion of roof decking. Roof joist appear ok in this area. Joist hangars do not, noted excessive rust and corrosion. Took some picture and will discuss with engineer of record.
|
BLD-Framing/Rough-in | 6/20/2018 | 6/20/2018 | 6/20/2018 | A | PART |
Mike Jordan
|
|
|
Work in progress on re-roof. no roof joist replacemet in area of work. Inspected new sheathing attachment, ok to cover.
|
BLD-Conference | 6/19/2018 | 6/19/2018 | 6/19/2018 | P | DONE |
Mike Jordan
|
|
|
A Correction notice was issued to provide a structural analysis on damaged roof joist, joist hangars and the ventilation system. Noted roof sheathing and joist damage to excessive moisture from aquarium tanks and possible damage to joist hangars from corrosion due to salt water.
|