Permit NumberBLD19-01312
StatusIssued
Name GUHO CORP
Site Address 780 W MAIN ST
Project NameCapitol Terrace Monument Stair
Customer Number 
ePlanReviewYes
Description
(CAPITOL TERRACE - MONUMENT STAIR) Permit for shell/core work to construct a new central stair off 8th Street and for restroom remodel. Work to include: demo of interior finishes and ceiling; construction of interior non-bearing partition walls, stair and structure; restroom remodel including new plumbing fixtures and exhaust fans; new lighting; new finishes in compliance with Ch. 8 of the 2015 IBC. Rated construction to be protected and maintained. Special inspections required per attached Form 310. This is a scope of work permit only with a certificate of completion to be issued upon completion and approval of the project. This building is fully Fire Sprinklered for high rise provisions. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JAR**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection12/6/201912/6/201912/6/2019PFAIL
DetailsJim Page
Fire alarm panel has open circuit trouble on NAC circuit, panel needs to be normal for life fire safety inspection. A fire alarm vendor will need to be present for the life fire safety inspection, due to fire alarm devices being removed and re-installed during this scope of work a fire alarm test will be required to verify proper operation of fire alarm system in scope of work areas.

Tom Phone #: ###-####
BLD-Final11/7/201911/8/201911/14/2019PPEND
DetailsDave Hannah
Tom Phone #: ###-#### needs fire first
FIRE-Final Inspection11/7/201911/8/201911/8/2019AFAIL
DetailsJim Page
Architectural feature at bottom of escalator is not installed, fire sprinkler head is to far down from deck, feature needs to be in place for final sign off. Need a fire alarm vendor available to test fire alarm system as discussed as verbally discussed, audio visual devices were removed and re-installed during project, need to verify operation.

Tom Phone #: ###-####
BLD-Conference10/31/201911/1/201911/1/2019ADONE
DetailsDave Hannah
Tom Phone #: ###-####
FIRE-Conference10/15/201910/16/201910/16/2019ADONE
DetailsTroy Cobbley
** Met with Tom. Discussed exit lighting, fire sprinkler, and fire alarm placement questions he had. He is going to meet with the architect to go over items we discussed.**MAS***Tom Phone #: ###-####
BLD-Framing/Rough-in9/4/20199/4/20199/5/2019PPASS
DetailsDave Hannah
Tom Phone #: ###-####
BLD-Foundation7/17/20197/18/20197/18/2019PPASS
DetailsDave Hannah
TOM- REBAR INSPECTION Phone #: ###-####