BLD-Final | 7/10/2020 | 7/13/2020 | 7/13/2020 | P | PART |
Tony Young
|
|
|
screened // Ryan Phone #: ###-####// ok after adding tempered glass by main stairs and blower door test results
|
BLD-Conference | 7/9/2020 | 7/10/2020 | 7/10/2020 | A | PART |
Tony Young
|
|
|
Ryan Phone #: ###-####,, walk through for final next week// verbal
|
BLD-Conference | 7/9/2020 | 7/9/2020 | 7/10/2020 | P | PART |
Tony Young
|
|
|
Ryan Phone #: ###-####// verbal
|
BLD-Aging Inspection | 5/13/2020 | 5/13/2020 | 5/14/2020 | | PEND |
Tony Young
|
|
|
|
BLD-Conference | 5/5/2020 | 5/6/2020 | 5/6/2020 | A | PART |
Tony Young
|
|
|
Ryan Phone #: ###-####// ? on front steps
|
BLD-Energy code compliance | 12/28/2019 | 12/30/2019 | 12/30/2019 | A | PASS |
Dave Hannah
|
|
|
Call Scott 30 min prior to inspection. Thank you Phone #: ###-#### Inspection requested via web by Ryan Parker
|
BLD-Framing/Rough-in | 12/23/2019 | 12/23/2019 | 12/23/2019 | P | PART |
Tony Young
|
|
|
Ryan - call for access Phone #: ###-####// ok to insulate,, see paint for c/n,, fire block,, insulate rim areas,, headroom on the stairs, etc
|
BLD-Wall Bracing | 11/7/2019 | 11/8/2019 | 11/8/2019 | A | PASS |
Tony Young
|
|
|
Shear // Ryan Phone #: ###-####,, straps and upper shear ok on exterior
|
BLD-Wall Bracing | 10/16/2019 | 10/16/2019 | 10/16/2019 | P | PART |
Tony Young
|
|
|
Ryan Phone #: ###-####,, main level ok
|
BLD-Conference | 10/15/2019 | 10/15/2019 | 10/15/2019 | P | DONE |
Tony Young
|
|
|
Ryan Phone #: ###-####,, A-35s on blocks ok
|
BLD-Footing | 9/19/2019 | 9/19/2019 | 9/19/2019 | P | PASS |
Dave Hannah
|
|
|
Ryan Phone #: ###-####
|
BLD-Foundation | 9/12/2019 | 9/13/2019 | 9/13/2019 | P | PASS |
Brandon Shaw
|
|
|
Ryan Phone #: ###-####
|
BLD-Footing | 9/10/2019 | 9/11/2019 | 9/11/2019 | A | PART |
Tony Young
|
|
|
Ryan Phone #: ###-####,, basement footings ok after digging out to 14" thick all the way,,
|