Permanent Service | 8/19/2019 | 8/20/2019 | 8/20/2019 | P | CANC |
Tom Saunders
|
|
|
Permanent service for streets light pedestal. Phone #: ###-#### Inspection requested via web by Kevin Burke....needed to pull new permit for work...contractor notified
|
Final | 8/19/2019 | 8/20/2019 | 8/20/2019 | A | PASS |
Tom Saunders
|
|
|
exterior final...complete final for building ok
|
Final | 8/19/2019 | 8/19/2019 | 8/19/2019 | P | NR |
Tom Saunders
|
|
|
Exterior Phone #: ###-#### Inspection requested via web by Kevin Burke.... not ready...rescheduled for next day morning
|
Final | 8/16/2019 | 8/16/2019 | 8/16/2019 | A | PART |
Tom Saunders
|
|
|
Last 6 units south Phone #: ###-#### Inspection requested via web by Kevin Burke...units 100, 102, 201, 202 301, 302...ok to final exterior remaining
|
Final | 7/31/2019 | 7/31/2019 | 7/31/2019 | P | PART |
Tom Saunders
|
|
|
Partial final on next 6 units from the North. Phone #: ###-#### Inspection requested via web by Kevin Burke... units 103 104, 203 204, 303 304
|
Final | 7/25/2019 | 7/26/2019 | 7/26/2019 | A | PART |
Tom Saunders
|
|
|
2nd six units from north end Phone #: ###-#### Inspection requested via web by Kevin Burke... RMs 105,106,205,206,305,306 ok to final
|
Final | 7/24/2019 | 7/25/2019 | 7/25/2019 | P | CANC |
Tom Saunders
|
|
|
2nd six units from north end Phone #: ###-#### Inspection requested via web by Kevin Burke... spoke with onsight contact...NR...rescheduled to AM next day
|
Final | 7/14/2019 | 7/15/2019 | 7/15/2019 | A | PART |
Tom Saunders
|
|
|
1st 6 units for final starting from the north Phone #: ###-#### Inspection requested via web by Kevin Burke.... units 107 108, 207 208, 307 308 ok
|
Electrical Rough-In | 7/10/2019 | 7/11/2019 | 7/11/2019 | P | CANC |
Tom Saunders
|
|
|
3rd set of (6) units from the north Phone #: ###-#### >> Inspection requested via web by Kevin Burke Inspection cancelled from web by: Kevin Burke
|
Electrical Rough-In | 6/17/2019 | 6/17/2019 | 6/17/2019 | A | CANC |
Tom Saunders
|
|
|
Call please Phone #: ###-#### Inspection requested via web by Kevin Burke... discussed permit for next building
|
Rough-In Permanent Service | 6/3/2019 | 6/4/2019 | 6/4/2019 | A | PASS |
Tom Saunders
|
|
|
Last 6 units and service Phone #: ###-#### Inspection requested via web by Kevin Burke... rough in ok last 6 units p/s u/g new ok 13 meters
|
Electrical Rough-In | 5/22/2019 | 5/22/2019 | 5/22/2019 | P | PASS |
Rock A. Hudson
|
|
|
Late afternoon if possible. Phone #: ###-#### Inspection requested via web by Kevin Burke Called and attached to BLD18-03116. Units 103, 104, 203, 204, 303, 304. 2nd 6 from south rough in ok cover.
|
Electrical Rough-In | 5/6/2019 | 5/7/2019 | 5/7/2019 | P | PASS |
Eric Story
|
|
|
2nd set of 6 from the north Phone #: ###-#### Inspection requested via web by Kevin Burke Middle 6 units ok to cover
|
Permanent Service | 4/22/2019 | 4/23/2019 | 4/23/2019 | A | PASS |
Tom Saunders
|
|
|
North side meters // Clint Phone #: ###-#### p/s u/g new ok...13 meters total
|
Electrical Rough-In | 4/16/2019 | 4/17/2019 | 4/17/2019 | A | PASS |
Tom Saunders
|
|
|
Clint-firrst 6 units on the left side Phone #: ###-####... rough ok to cover...north 6 units
|