Permit Information
Permit NumberESC17-00392
StatusFinaled
Name JOHN WYMAN
Site Address 2214 E GOODMAN ST
Project NameWARM SPRINGS APARTMENTS-GOODMA
Customer Number 
ePlanReviewNo
Description
21 UNIT APARTMENTS IN 2 BUILDINGS OF 3 STORIES. PHASE ONE IS 9 UNITS BUILDING "A". CMPs: SCE, DI protection on S&G traps, staging area with waste containment and CW.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection8/19/20198/19/20198/19/2019 CANC
DetailsMichael Zawacki
DOC - Permit Finaled8/19/20198/19/20198/19/2019PPASS
DetailsMichael Zawacki
General Inspection7/2/20197/2/20197/2/2019PPASS
DetailsMichael Zawacki
Work completed, site stable. Will final when other permits closed.
General Inspection5/21/20195/21/20195/21/2019 PASS
DetailsMichael Zawacki
Building and exterior work completed. Some landscape material stored in road. Some flooding in rear of lot and neighboring parking lot.
General Inspection4/5/20194/5/20194/5/2019 PASS
DetailsAndy J. Long
General Inspection1/1/20191/1/20191/2/2019 PART
DetailsMichael Zawacki
Some trackout on road and sidewalk from mini excavator. No inlet protection in road. Some areas of sidewalk still needs to be poured, did not see a washout on site, also didn't see any dumped washout. Site is currently frozen solid.
General Inspection11/16/201811/16/201811/16/2018PPASS
DetailsMichael Zawacki
Roofing and siding contractors on site, only remaining external work. Site still needs to be landscaped. Nothing leaving site.
General Inspection11/9/201811/9/201811/9/2018 PASS
DetailsMichael Zawacki
Parking lot, curb, and sidewalk complete. Irragation lines on site, area needs landscaping. Majority of exterior complete, genie lift operating on site.
General Inspection9/24/20189/24/20189/24/2018 PART
DetailsMichael Zawacki
Work in road is complete and area has been patched. Site is contained, no dirt leaving.
Lots of loose trash around site.
General Inspection8/9/20188/9/20188/9/2018PFAIL
DetailsAndy J. Long
Trackout from unpaved parking lot to Goodman. Newly installed storm drain does not have sediment protection installed. Broken sand bags in gutter. Some loose trash around perimeter in bushes and landscaping.

Corrections needed:

- sweep Goodman Street at entrance
- have crew pick up any loose trash around perimeter
- install sediment protection (witches hat, coco mat)
General Inspection7/16/20187/16/20187/18/2018 PASS
DetailsMichael Zawacki
Site is contained. Goodman St is now patched. No ESC issues at site.
Tracking Control5/23/20185/29/20185/30/2018AFAIL
DetailsMichael Zawacki
Still lots of dirt on road, obvious transition after job ends. Workers are parking on shoulder, no stabalized entrance at site.
General Inspection5/22/20185/22/20185/23/2018 FAIL
DetailsAndy J. Long
Muddy street, trackout not cleaned up. Works parking in the mud.

Stormwater swale north of building is not driaining. Need to check with owner and provide sediment protection in between swale and runoff from site.
Site Preparation4/6/20184/6/20184/6/2018PPART
DetailsAndy J. Long
Road work and muddy parking lot is causing trackout. Crew is in process of installing curb.

RP stated that once curb is in they will provide stabilized access with roadmix. In meanwhile they will scrape/sweep up trackout. Trackout not extending to Warm Springs.

Permit sign posted. Trash is picked up.
General Inspection3/13/20183/13/20183/14/2018 PASS
DetailsMichael Zawacki
Site is lower than surrounding grade. Workers are parked on street, only genie lift running on property. There shouldn't be any trackout as long as genie doesn't leave property. Lots of loose lumber scraps that need to be picked up.
General Inspection1/22/20181/25/20181/26/2018PCANC
DetailsAndy J. Long
General Inspection1/12/20181/18/20181/22/2018PCANC
DetailsAndy J. Long
General Inspection1/22/20181/22/20181/22/2018PPEND
DetailsAndy J. Long
Trash along back of building on west side has been picked up. No significant trackout beyond site, no construction entrance installed and some vehicles parking next to building will cause trackout.

Will follow up later this week on schedule for Suez to pave over new water construction.
General Inspection1/12/20181/12/20181/12/2018PPART
DetailsAndy J. Long
Vertical construction in progress on apartment building. Site is not yet paved, most worker vehicles are parked on street to prevent trackout. Some minor trackout to Goodman, but does not extend to Warm Springs. Permit sign posted, trash container onsite. Site is below grade of surrounding area and retains stormwater.

Correction request:
- pick up loose trash around site, in particular on the NW side of building.
- continue to do regualar cleaning of trackout until curb and sidewalk is installed and new road mix base can be put in parking lot. Note: Suez water to return to pick up asphalt pile and small stock pile.
- sweep dirt in entrance to adjacent dental office.
General Inspection2/18/20192/18/2019   
DetailsAndy J. Long