Site Final | 1/3/2019 | 1/3/2019 | 1/3/2019 | P | PASS |
Jim Sly
|
|
|
|
DOC - Permit Finaled | 1/3/2019 | 1/3/2019 | 1/3/2019 | P | PASS |
Jim Sly
|
|
|
|
Site Final | 11/26/2018 | 12/13/2018 | 12/19/2018 | P | NR |
Andy J. Long
|
|
|
WIP pouring paving and ramps around new parking lot. No trackout or discharges
|
General Inspection | 11/26/2018 | 11/26/2018 | 11/26/2018 | | PASS |
Andy J. Long
|
|
|
Parking lot paved. Perimeter landscaping in progress been hydromulched. No trackout or discharges.
|
General Inspection | 10/10/2018 | 10/10/2018 | 10/10/2018 | | PASS |
Andy J. Long
|
|
|
No trackout, no disharges observed or evident to Bethel Street. No corrections requested.
|
General Inspection | 8/21/2018 | 8/21/2018 | 8/21/2018 | | PASS |
Andy J. Long
|
|
|
No trackout or fugitive dust at site. No storm drains on Bethel near project, very dry conditions. No crew onsite, no corrections at this time.
|
Random Inspection | 7/6/2018 | 7/6/2018 | 7/6/2018 | P | PASS |
Andy J. Long
|
|
|
Frame of steel structure is built. No trackout or other ESC issues observed. Approved.
|
General Inspection | 3/12/2018 | 3/27/2018 | 3/28/2018 | P | PASS |
Andy J. Long
|
|
|
Permit sign posted. WIP on foundation. No trackout. Stormwater is retained on site.
|
Site Preparation | 3/9/2018 | 3/12/2018 | 3/12/2018 | A | PASS |
Andy J. Long
|
|
|
will not be on site please call when on way // Curt Phone #: ###-####
Permit sign posted on east entrance. Flat, no MS4 on Bethel. Concrete washout pan provided for foundation work. Site is an active staging and equipment yard.
Approved for construction.
|