Information based on query as of Saturday, May 18, 2024.
Permit Information
Permit NumberESC17-01792
StatusFinaled
Name ELDON OYADOMARI
Site Address 11350 W FRANKLIN RD
Project NameIdaho Power BOC expansion
Customer Number 
ePlanReviewNo
Description
see GRD for detailed project description. SWPPP prepared for project. Structural fill will be placed onsite after removal of topsoil. Excavation for stormwater retention and infiltration facilities will also occur. Heavy duty construction entrance required for access to Franklin and silt fence perimeter on west and north side of project. Site preparation inspection required.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final1/28/20191/29/20191/29/2019APASS
DetailsMichael Zawacki
Call me if you need access to the site. Gate is locked. Phone #: ###-#### Inspection requested via web by Eldon Oyadomari
General Inspection1/23/20191/23/20191/23/2019 DONE
DetailsMichael Zawacki
No activity, gate was locked.
General Inspection11/27/201811/27/201811/27/2018 PASS
DetailsMichael Zawacki
Training area looks complete. Rock entrance still at site, no issues.
General Inspection10/11/201810/11/201810/11/2018 PASS
DetailsMichael Zawacki
Met with foreman on site. Entrance is off Franklin, crushed rock entrance in place, some people have been driving around it, said they will make sure everyone uses it. Multiple washouts for mortar on site. All materials stored cleanly, no trash on site. Activity is on active traing grounds.
Site Final5/21/20185/22/20185/22/2018APASS
DetailsMichael Zawacki
Kyle -please call ahead Phone #: ###-####
General Inspection4/10/20184/10/20184/10/2018PPASS
DetailsMichael Zawacki
Eldon with Idaho Power is taking care of SWPPP. Knife River on site grading. Rock entrance going out to Franklin is installed. WHen they start running haul trucks they are going to exit through Idaho Power complex to keep tracking off ACHD roads and avoid running trucks head to head.
Site Preparation2/21/20182/21/20182/21/2018PPASS
DetailsAndy J. Long
Site walk through with RP Eldon.

Heavy duty rock construction entrance installed, DI protection on south side of Franklin (may be for ITD/ACHD road project per Eldon). No concrete or cement work for project, will be Idaho Power training yard and linemen practice area. Project is to be from February - May/June. Fugitive dust control may be required during import of material and grading.

Approved for construction.

Perimter silt fence properly installed.