Permit Information
Permit NumberESC18-00107
StatusFinaled
Name BRYAN MURDOCH
Site Address 3054 E BIRDSONG DR
Project Name 
Customer Number 
ePlanReviewNo
Description
Hillside new single family. ESC plan approved. Preserve existing vegetation around clearing limits, ESCP calls out fiber wattle below home to protect residence below to the west. Sediment protection on MS4 on Birdsong. Site preparation inspection required.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection2/4/20192/4/20192/4/2019PCANC
DetailsMichael Zawacki
DOC - Permit Finaled2/4/20192/4/20192/4/2019PPASS
DetailsMichael Zawacki
General Inspection1/2/20191/2/20191/2/2019PPASS
DetailsMichael Zawacki
Yard is landscaped and stable. Small area of home near entrance needs to be finished. Fence company on site finishing.
General Inspection10/2/201810/2/201810/2/2018PFAIL
DetailsAndy J. Long
Home near completion, yard not yet landscaped. No hillside erosion issues.

Corrections needed:

Loose dirt and debris on sidewalk and in culdesdac in front of home, some with potential to flow directly to storm drain. No storm drain sediment protection installed. Unlined concrete washout used, not per ESC plan construction details. Washouts should be lined leakproof containers.
General Inspection8/14/20188/14/20188/14/2018PPASS
DetailsMichael Zawacki
Most exterior work and stucco complete. Site is free from trash, Lots of old stucco laying around home.
General Inspection5/15/20185/17/20185/18/2018PPASS
DetailsMichael Zawacki
Follow up inspection.
Wattle and gator guard installed on bottom of lot, gravel bag check dams installed. Sediment has been scraped and swept from intersection of Windsong. Sediment has stained pavement, looks much worse than it is, unable to scrape any more dirt off.
Random Inspection5/16/20185/16/20185/16/2018PPASS
DetailsMichael Zawacki
Post rain inspection. No ESC issues.
Site Preparation3/15/20183/15/20183/15/2018PPASS
DetailsMichael Zawacki
Work has begun without site inspection. Currently there is a vegatation buffer. Excavator driven in and below road grade. Stabalized entrance will need to be installed when driveway is cut in.