General Inspection | 4/21/2020 | 4/21/2020 | 4/23/2020 | | CANC |
Andy J. Long
|
|
|
|
Site Final | 4/23/2020 | 4/23/2020 | 4/23/2020 | P | PASS |
Andy J. Long
|
|
|
Project complete. Some contained within site need more vegetation, but no runoff issues are occuring. Second phase of project now in progress to the east, see ESC19-01767
|
General Inspection | 3/19/2020 | 3/19/2020 | 3/19/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 2/17/2020 | 2/17/2020 | 2/18/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/16/2020 | 1/16/2020 | 1/16/2020 | | DEFR |
Michael Zawacki
|
|
|
Need to check stabilazation, wait for area to thaw.
|
Site Final | 12/13/2019 | 12/16/2019 | 12/17/2019 | P | NR |
Andy J. Long
|
|
|
Stockpiles on adjacent lot and back slope revegetation does not seem to be establishing well
|
General Inspection | 12/13/2019 | 12/13/2019 | 12/13/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/12/2019 | 11/12/2019 | 11/12/2019 | P | PASS |
Michael Zawacki
|
|
|
Building exterior completed and parking lot paved.
|
Site Final | 10/22/2019 | 10/22/2019 | 10/22/2019 | P | NR |
Andy J. Long
|
|
|
Large stockpile from site is still on adjacnet lot. No material leaving site. Will leave open to figure out management of stockpile.
|
General Inspection | 10/22/2019 | 10/22/2019 | 10/22/2019 | | CANC |
Andy J. Long
|
|
|
reschedule for site final
|
General Inspection | 9/20/2019 | 9/20/2019 | 9/20/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/19/2019 | 8/19/2019 | 8/19/2019 | P | PASS |
Michael Zawacki
|
|
|
Parking lot paved, still needs landscaping. Job trailer still on east of site.
|
General Inspection | 7/18/2019 | 7/18/2019 | 7/18/2019 | | PASS |
Michael Zawacki
|
|
|
All current work is in interior of building. Entire lot is pit run, ecopan still at site.
|
General Inspection | 6/17/2019 | 6/17/2019 | 6/17/2019 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 5/28/2019 | 5/28/2019 | 5/28/2019 | P | PASS |
Michael Zawacki
|
|
|
Site is surrounded by pit run. Few workers on site, most in interior. No trackout, both exits are stabalized.
|
General Inspection | 5/2/2019 | 5/2/2019 | 5/2/2019 | P | PASS |
Michael Zawacki
|
|
|
Washout on site. Rear hill has been tracked. Tilt up building has walls up, trusses on site. No issues.
|
General Inspection | 3/29/2019 | 3/29/2019 | 3/29/2019 | P | PASS |
Michael Zawacki
|
|
|
No trackout to Franklin.
|
General Inspection | 3/7/2019 | 3/7/2019 | 3/7/2019 | P | PASS |
Michael Zawacki
|
|
|
Running 8 trucks hauling out backfill and bringing in pit run. Road is free from trackout. No one working in mud. Entrances have been built bigger and are being maintained. Ecopans on site.
|
Site Preparation | 2/11/2019 | 2/12/2019 | 2/12/2019 | A | PASS |
Michael Zawacki
|
|
|
Met with foreman Gene Hackman. Site has wattle and washout, entrance needs to be improved, said he will get some more rock. Entrance being used jointly between sites. Working on rear hillside to prep for wall, tracked equipment being used to track hillside, will be seeded in spring.
|