Permit Information
Permit NumberESC18-01432
StatusFinaled
Name COREY HOCKERSMITH
Site Address 139 E WARM SPRINGS AVE
Project NameRonald McDonald House
Customer Number 
ePlanReviewNo
Description
site work and new building. Install BMPs per approved ESC site plan. Site Preparation Inspection is required.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final5/19/20205/22/20205/22/2020APASS
DetailsMichael Zawacki
General Inspection5/18/20205/18/20205/19/2020 PEND
DetailsMichael Zawacki
Sent RP message to come and remove inlet protection so permit can be closed.
Talked to RP, scheduled for final 5/22
Site Final3/30/20203/31/20203/30/2020ANR
DetailsMichael Zawacki
Landscapers still on site.
Inleet protection still installed in parking lot and road.
General Inspection3/30/20203/30/20203/30/2020 CANC
DetailsAndy J. Long
General Inspection2/12/20202/12/20202/14/2020 PASS
DetailsMichael Zawacki
Some landscaping still needed. DI protection installed in parking lot.
General Inspection12/27/201912/27/201912/27/2019 PASS
DetailsAndy J. Long
General Inspection11/11/201911/11/201911/18/2019 PASS
DetailsAndy J. Long
General Inspection9/24/20199/24/20199/24/2019 PASS
DetailsMichael Zawacki
Site is clean and contained. Rumble bars at entrance, no trackout. Masons are mixing mortar in buckets, no mixer, and are using outpak, no dumped mortar on site. Site is free from loose trash, has been sprayed to keep dust down.
General Inspection7/30/20197/31/20198/5/2019APASS
DetailsMichael Zawacki
Did site walkthrough with foreman. Site is clean and contained. Getting ready to closr lane on warm springs and remove sidewalk, currently in permitting with ACHD.
General Inspection3/26/20193/26/20194/1/2019PPASS
DetailsAndy J. Long
Site Preparation2/6/20192/6/20192/7/2019PPASS
DetailsAndy J. Long
Site walk through conducted with RP & site superintendent Cory w/ ESI.

Site entrance is at SE corner of project via Broadway (road to St. Luke's parking). Existing asphalt to remain. Rock construction exit with rumble bars is installed at SW end. Trucks will exit here and proceed to EB Warm Springs.

- surrounding MS4 storm drains have sediment protection. Private drain on St. Lukes road is also protected.
- ecopans will be used for washout
- secondary containment to be installed for onsite fueling

Approved for construction. Permit sign posted at entrance and on job trailer.
General Inspection1/11/20191/11/20191/11/2019PPASS
DetailsMichael Zawacki
Small area of parking lot fenced off, no work going on. Ne access to parking garage open, area still needs to be landscaped.
General Inspection1/10/20191/10/20191/11/2019PDEFR
DetailsMichael Zawacki
entry error
General Inspection11/7/201811/7/201811/9/2018PPASS
DetailsMichael Zawacki
Met with foreman, tried to request site prep online, didn't work.
BMPs installed, phase 1 is just new drive with curb and sidewalk, will be bringing in eco pan.
Phase 2 won't bee untill IDP relocates new services.