Permit Information
Permit NumberESC18-01550
StatusFinaled
Name GEORGE COLLINGHAM
Site Address 5685 N COLLISTER DR
Project Name5685 Collister House
Customer Number 
ePlanReviewNo
Description
Per attached conditions
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection2/13/20202/13/20202/13/2020 CANC
DetailsMichael Zawacki
DOC - Permit Finaled2/13/20202/13/20202/13/2020PPASS
DetailsMichael Zawacki
General Inspection1/29/20201/29/20201/30/2020 CANC
DetailsAndy J. Long
General Inspection1/14/20201/14/20201/14/2020 PASS
DetailsMichael Zawacki
OK to close when bld closed
General Inspection12/27/201912/27/201912/27/2019 PASS
DetailsAndy J. Long
General Inspection12/12/201912/12/201912/12/2019 PASS
DetailsMichael Zawacki
General Inspection11/27/201911/27/201911/27/2019 PASS
DetailsMichael Zawacki
Exterior completed and lawn landscaped.
General Inspection11/8/201911/8/201911/8/2019 PART
DetailsMichael Zawacki
Exterior work completed. Front is dirty with old stucco and debris, mini excavator at site.
General Inspection10/24/201910/24/201910/24/2019PPASS
DetailsAndy J. Long
General Inspection10/16/201910/16/201910/16/2019 PART
DetailsMichael Zawacki
Exterior completed. Lots of dumped stucco around home, all contained to site.
General Inspection9/23/20199/23/20199/23/2019PPASS
DetailsMichael Zawacki
House has scaffolding and is prepped for stucco.
No stucco mixer on site. Some random trash around site, nothing major and nothing blowing.
General Inspection9/6/20199/6/20199/6/2019PPASS
DetailsMichael Zawacki
Owner talked to George and got RP situation resolved, George will be RP. Street was cleaned, washout and trash removed.
Called techs and let them know to lift hold.
General Inspection9/6/20199/6/20199/6/2019PCANC
DetailsMichael Zawacki
BMP Violation8/27/20198/30/20198/30/2019AFAIL
DetailsMichael Zawacki
Nothing done to clean site. Will issue parcel hold and request reinspection.
General Inspection8/27/20198/27/20198/27/2019PFAIL
DetailsMichael Zawacki
shout has beendumped on ground, dirt in gutter and road. Message sent to RP, follow up scheduled.
General Inspection7/23/20197/23/20197/23/2019PPASS
DetailsMichael Zawacki
Capitol paving and gas company both on site. Looks like driveway is being prepped, lot bare. Nothing leaving site.
General Inspection7/8/20197/8/20197/8/2019PPASS
DetailsMichael Zawacki
Gatorguard protecting perimeter. Lots of lumber scraps on lot.
General Inspection6/17/20196/18/20196/18/2019PPASS
DetailsMichael Zawacki
WIP on framing. Trash box on site and used. All word scraps in pile. Lots of lumber on sie.
General Inspection6/6/20196/6/20196/6/2019PPEND
DetailsMichael Zawacki
WIP on hooking up water. Some trackout from ini excavator. Have plumbing inspection scheduled for later this afternoon.